Hospital of the Future Construction Update as of Dec. 3, 2010
Hospital of the Future West side of the building.
Hospital of the Future View of brick work from Springfield Street.
Hospital of the Future Green Roof (install spring 2011).
Hospital of the Future Basement boiler started early Nov. to provide temporary heat during construction.
Hospital of the Future Basement air handler unit started in early Dec. for temporary heat during construction.
Hospital of the Future Endovascular procedure rooms support steel duct installation ongoing.
Hospital of the Future Endovascular procedure room coordination complete, released for fabrication.
Endovascular procedure room coordination (each room = 200 hours of configuration).
Hospital of the Future 2 nd Floor: CARE area drywall underway.
Hospital of the Future 3 rd Floor: Rough-in complete; drywall underway.
2011 Facility Milestones to Come: Finished ceilings begin. Exterior landscaping begins. Final painting begins. Phase 1 construction complete NEW PATIENT AREAS OPEN!