Machine Protection System Commissioning plans

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
1 MPS Commissioning Report from the MPSC subgroup Jan Uythoven For the Members of the MPSC subgroup.
PAC June LHC Machine Protection Rüdiger Schmidt R.Assmann, E.Carlier, B.Dehning, R.Denz, B.Goddard, E.B.Holzer, V.Kain, B.Puccio, B.Todd, J.Uythoven,
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
BP & RS: BIS & SLP for AB/CO Review, 23 h Sept Realisation of the interlocking between SPS, LHC and CNGS and open issues Beam Interlock Systems.
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
Schedule IT General Schedule 9 th, September 09 Today.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
CLIC Interlock System study: from Principle to Prototyping Patrice Nouvel TE-MPE-EP TE-MPE Technical Meeting : 22/03/2012.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
V. Kain AB/OP1Chamonix XV What is required to safely fill the LHC? V.Kain AB/OP Input from: B.Goddard, M.Jonker, Y.Kadi, R.Losito, V.Mertens, B.Puccio,
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Data providers Volume & Type of Analysis Kickers
The TV Beam Observation system - BTV
Beam Interlock System SPS CIBU Connection Review
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Dependability Requirements of the LBDS and their Design Implications
Minimum Hardware Commissioning – Disclaimer
The HL-LHC Circuits: Global View and Open Questions
Overview of CERN BIS and Communication Hardware
Summary of first LHC logging DB meeting
LINAC4 50 MeV phase BIS STATUS
SPS extraction, transfer lines, injection
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
M.Jonker CTC MPO-WG status
J. Uythoven for the MPE-MI & MS Teams
SPS CC: Final plan for interlocking of crab cavities in SPS
Rüdiger Schmidt and Karl Hubert Mess
MPS Commissioning and Status
Initial Experience with the Machine Protection System for LHC
MPSC Procedures An update
Distributed BI Systems
Remote setting of LHC BLM thresholds?
Machine Protection Xu Hongliang.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Interlocking of CNGS (and other high intensity beams) at the SPS
Agenda 9:00-10:00 Beam Interlock System Changes Following the 2006 Audit Benjamin Todd 10:00-11:00 Beam Dump System follow-up from the 2008 Audit Jan Uythoven.
M. Zerlauth, I. Romera 0v1.
Beam Dump and Injection Inhibits
Planning at 5 o’clock meeting Friday
Machine Protection during Beam Commissioning
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
1v1.
Will We Ever Get The Green Light For Beam Operation?
Beam Interlocks for Detectors and Movable Devices
The LHC Beam Interlock System
Interlocking strategy
Wednesday 23/2 Thanks CRYO!!!.
Review of hardware commissioning
What systems request a beam dump? And when do we need them?
Close-out.
SPS Injection BIS - Draft requirements
Presentation transcript:

Machine Protection System Commissioning plans Jan Uythoven Many thanks to the Members of the MPS Commissioning Working group, The MP Working Group and the LHC Commissioning Working Group. Special thanks to R. Schmidt and J. Wenninger

Outline Introduction The Commissioning of the MPS has started! Plans for further Commissioning and follow-up Conclusions Jan Uythoven, AB /BT MAC, 15th June 2007

Introduction Core elements of the LHC Machine Protection System Beam Interlock System Beam Dumping System Beam Loss Monitoring System Collimation System Quench Protection System & Powering Interlocks Injection System Together with other elements they will need to guarantee the ‘safety’ of the LHC = equipment protection Detect any equipment state or beam state that is potentially dangerous Dump the beam before damage to equipment can occur This safety of the system needs to be guaranteed (SIL 3) by Good system design Redundancy between subsystems Redundancy within critical subsystems Reliable system components Careful follow-up during production and installation Thorough commissioning of the system Individual System Tests System commissioning with and without beam Jan Uythoven, AB /BT MAC, 15th June 2007

The LHC Machine Protection System & Interfaces Devices Movable Detectors Beam Loss Monitors BCM Experimental Magnets Collimator Positions Environmental parameters Safe Beam Parameter Distribution LHC Devices LHC Devices SpecialBLMs Safe LHC Parameter Software Interlocks Sequencer Operator Buttons CCC LHC Experiments Transverse Feedback Beam Aperture Kickers Collimation System Beam Dumping System Beam Interlock System Safe Beam Flag Injection Interlock Powering Interlocks sc magnets Powering Interlocks nc magnets Magnet Current Monitor RF System Beam loss monitors BLM Beam LifetimeFBCM Access System Vacuum System Screens / Mirrors BTV Timing System (Post Mortem Trigger) Magnets Power Converters Monitors aperture limits (some 100) Monitors in arcs (several 1000) QPS (several 1000) Power Converters ~1500 AUG UPS Cryo OK Doors EIS Vacuum valves Access Safety Blocks RF Stoppers Jan Uythoven, AB /BT MAC, 15th June 2007

Commissioning has Started! LHC Hardware Commissioning Individual System Tests of LHC on the way Experience of MPS equipment with the powering of the first LHC sector SPS operation 2006 and 2007 Fast Magnet Current Change Monitoring in 2006 and later in 2007 Beam Interlock Systems following same design as LHC BIS being used for CNGS and TT40/TT60 (towards LHC!) extraction interlocking SPS ring interlock in 2007 LHC-like beam permit loop with clients connected to the dump through one of the 6 BICs connected to the loop Safe Beam Flag for CNGS operation Proof of the hardware and the design choices that have been made Experience concerning commissioning and operations of systems similar to those that will be used in the LHC Jan Uythoven, AB /BT MAC, 15th June 2007

SPS Extraction towards to LHC Using SPS Extraction BIS Inputs 8 to 14 are always maskable Inputs 1 to 7 are always un-maskable Mask status Safe Beam Flag status Software Interlock System Input J.Wenninger Jan Uythoven, AB /BT MAC, 15th June 2007

SPS extraction BIS information - PFN voltage - BIC permit - BETS window - Beam Timing of kicker, BIC permit and BETS: Extr. 1 Extr. 2 Signals as seen on an oscilloscope for testing the interlock system Beam Energy Tracking System considers dipole DCCT and HV of extraction kicker: Same hardware as for the LHC Beam Dumping System (but reverse logic) Jan Uythoven, AB /BT MAC, 15th June 2007

SPS extraction BIS information Bar graph summarising the status of the interlock system Time offset wrt start of cycle Depth in seconds wrt Time offset Extraction permit switching to TRUE for extraction (3 ms wide) Check this box to hold selected time range values Check this box to freeze display Jan Uythoven, AB /BT MAC, 15th June 2007

Fast Magnet Current Change Monitor: MBG 4101M – Interlock Triggers at 10-4 change of I nominal FMCM triggers @ 3984.4 =10E-4 3 FMCMs were operational last year and tested following well defined procedures. Modified CERN types (better adapted for pulsed magnets and additional controls interface) will be installed later this year M. Zerlauth, Adapted DESY design Jan Uythoven, AB /BT MAC, 15th June 2007

LHC Hardware Commissioning D2.L8 presently under test Quench event at 17018 ms Presently being commissioned: Quench Protection System & PIC system Obtain experience with: Tools for Post Mortem and Logging Sequencer Current ramp Current starts to change 17.027 ms Quench heaters efficient 17.026 ms Quench loop reading PIC 17021 ms Signal to BIC Quench detected 17018 ms Jan Uythoven, AB /BT MAC, 15th June 2007

Plans for (further) Commissioning and follow-up Thorough commissioning of the Machine Protection System: Individual System Tests Part of the LHC Hardware Commissioning LHC Cold Check-Out period (machine closed, ready for beam) System commissioning with beam Different phases depending on beam intensity and beam energy Special attention to the links between the different systems Most hours of MPS testing before first beam, Some systems completely tested before beam  Jan Uythoven, AB /BT MAC, 15th June 2007

100 % Tested before First Beam LHC Devices Movable Detectors Beam Loss Monitors BCM Experimental Magnets Collimator Positions Environmental parameters Safe Beam Parameter Distribution LHC Devices LHC Devices SpecialBLMs Safe LHC Parameter Software Interlocks Sequencer Operator Buttons CCC LHC Experiments Transverse Feedback Beam Aperture Kickers Collimation System Beam Dumping System Beam Interlock System Safe Beam Flag Injection Interlock Powering Interlocks sc magnets Powering Interlocks nc magnets Magnet Current Monitor RF System Beam loss monitors BLM Beam LifetimeFBCM Access System Vacuum System Screens / Mirrors BTV Timing System (Post Mortem Trigger) Magnets Power Converters Monitors aperture limits (some 100) Monitors in arcs (several 1000) QPS (several 1000) Power Converters ~1500 AUG UPS Cryo OK Doors EIS Vacuum valves Access Safety Blocks RF Stoppers Jan Uythoven, AB /BT MAC, 15th June 2007

MPS Commissioning Working Group Sub working group of the LHC Commissioning Working Group Six meetings since November 2006, 20 Members: Two people per main system Engineers in charge + a few others Webpage: http://lhccwg.web.cern.ch/lhccwg/MPS/mps.htm Mandate of Sub-Working Group on the Commissioning of the Machine Protection System   " Produce the detailed (=step by step) description of the commissioning of the LHC Machine Protection System and record the test results. " The aim is to have a first version available by June / July 2007.  ...but was defined with circulating beam in mind for November 2007… That is going to be tight…. Jan Uythoven, AB /BT MAC, 15th June 2007

Detailed Procedure for Each System Follow standard format for tests to be performed at the different phases Identical to LHC HC strategy To be published and approved by MPS comm. wg members Specific tests are listed and tabulated Jan Uythoven, AB /BT MAC, 15th June 2007

Format of the Procedures Jan Uythoven, AB /BT MAC, 15th June 2007

Manufacturing and Test Folder (MTF) Each Described Test is to be found back in the MTF system The Status of the Test (passed, not passed, pending) and possible test reports are kept in this system Identical system to what is being used for the LHC Hardware Commissioning Many of the MPS tests will be done during the LHC Hardware Commissioning Need to have compatible systems: MPS commissioning procedures can refer to LHC HC procedures Jan Uythoven, AB /BT MAC, 15th June 2007

The Hardware Commissioning Manufacturing & Test Folder B. Perea Solano SECTOR HC REGION EQUIPMENT & EQUIPMENT GROUPS Organization of the stored information within arborescence Jan Uythoven, AB /BT MAC, 15th June 2007

Validation of the tests performed to the equipment External Properties (LDB) + Property Values (test variables) + Parameters (historical tracking) Report documents, journals, EDMS, etc. Jan Uythoven, AB /BT MAC, 15th June 2007

Within MTF specific reports (=views) can be created to show the progress of the commissioning as an example by region for all the systems Jan Uythoven, AB /BT MAC, 15th June 2007

Status of Written Procedures Some of the procedures exist and are well advanced, (almost) ready for distribution within edms PIC, FMCM, Vacuum System Advanced (already presented) BIS system, BLM system Next presentations Injection System, WIC System Outstanding main systems (but already worked upon) Beam Dumping System, Collimation System Other systems – need to be assigned to people to write procedures: Experiments, RF & Feedback, Aperture Kickers & AC dipole, Safe Beam Flag etc. After comments and approval to be described in MTF Results of tests to be entered in MTF Custom reports to be created to follow progress Jan Uythoven, AB /BT MAC, 15th June 2007

Different Procedures & Work in other Groups LHC Hardware Commissioning WG: Procedures per System – create for MPS if it does not exist LHC Commissioning Working Group ‘Procedures’ are given per phase of LHC Commissioning First Injection (pilot), energy ramp, increasing the intensity etc. MPS commissioning Procedures are per System, over all phases Etc. Cold Check-out Hardware Commissioning Injection Ramp Increasing Intensity Beam Dumping System RF System Injection System Collimation System MPS Commissioning LHCCWG & LTC Jan Uythoven, AB /BT MAC, 15th June 2007

Besides Procedures MPS Commissioning Working Group is a forum to discuss different items related to the MPS commissioning and operation Establishes a team of experts who can be called in during LHC operation when required Training for Engineers In Charge Jan Uythoven, AB /BT MAC, 15th June 2007

Topics concerning the MPS under discussion in the different working groups BLM operation Which thresholds to set? Proposed 30 % of quench level, for the arcs, this concerns operational efficiency and not machine protection When and How to change BLM settings? Are remote changes via ‘Management of Critical Settings’ more risky than a local change? Procedure for disabling single BLMs when required Protection settings (collimators) during the different phases of LHC commissioning Relation with limits on beam parameters (beta beta, orbit etc.) during the different commissioning phases Interlocking Strategy of the Aperture kicker and Ac Dipole Based on keys and LHC Safe Beam Flag Jan Uythoven, AB /BT MAC, 15th June 2007

Conclusions The Commissioning of the LHC Machine Protection System has already started LHC Hardware Commissioning SPS extraction and ring Beam Interlock System, FMCM Proof of the hardware design choices that have been made Experience concerning commissioning and operations of systems similar to those that will be used in the LHC To guarantee a ‘Safe’ LHC operation, the commissioning procedures of the different MPS components Are being described in detail following a fixed format, distributed and agreed upon Will be followed up in the Manufacturing and Test Folder A lot of work still to be done On paper (procedures, MTF, reports) In reality, following the paper work The fruits of the work should be: Limited confusion during LHC commissioning, with and without beam Never see the destructive potential of the LHC being confirmed Jan Uythoven, AB /BT MAC, 15th June 2007