EUC Project Timelines Key Upcoming Dates:

Slides:



Advertisements
Similar presentations
XRN4361 – UK Link Release 2 - Delivery
Advertisements

XRN4572 – UK Link Release 3 - Design
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Plan Options Decision
Overall Project RAG Status:
UIG Task Force Progress Report
Release 3 Update December 2018.
XRN4340 – UK Link Future Release 1.1
Overall Project RAG Status
UIG Task Force Progress Report
UIG Task Force Progress Report
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
XRN4361 – UK Link Release 2 - Delivery
Release 3 Plan Options Analysis
Overall Project RAG Status
XRN4361 – UK Link Release 2 - Delivery
UIG Task Force Progress Report
Release 3 Update 9th January 2019.
Overall Project RAG Status:
xrn4340 – UK Link Future Release 1.1
Release 3 Update 13th February 2019.
UIG Task Force Progress Report
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
June 19 Timelines Key Upcoming Dates:
4361 – UK Link Future Release 2
Release 3 Scope & Proposed Plan
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
UIG Task Force Progress Report
4361 – UK Link Future Release 2
4340 – UK Link Future Release 2
Overall Project RAG Status:
Overall Project RAG Status:
XRN4361 – UK Link Future Release 2
Overall Project RAG Status
XRN June 19 Release - Status Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
XRN November 2019 Release - Status Update
4340 – UK Link Future Release 1.1
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
XRN June 19 Release - Status Update
UIG Task Force Progress Report
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
UIG Task Force Progress Report
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
UIG Task Force Progress Report
UIG Task Force Progress Report
UIG Task Force Progress Report
Presentation transcript:

EUC Project Timelines Key Upcoming Dates: Design Change Packs, Extraordinary Issue Date – 21st December 10 Day Review Period Completion (Excluding Bank Holidays) – 9th January 5 Day Xoserve Response Period Completion – 16th January 5 Day Notice of ChMC Materials – 17th January Design Change Packs Approved – 24th January 2019 at Extraordinary ChMC 6 Month Notice of July 31st Implementation – 31st January BER Approved – 9th January at ChMC

Overall Project RAG Status: EUC 29th October 2018 Overall Project RAG Status: Schedule Risks and Issues Cost Resources RAG Status Status Justification Mobilisation: Mobilisation activities are underway to plan for the Design phase. Resources are being forecasted for the duration of the delivery, whilst a further detailed analysis/ impact assessment of the change is being undertaken, to help plan out the necessary Design activities Funding: As the high-level costs have been provided in the HLSOIAs, customers have been asked whether an EQR is necessary, and whether a BER, outlining the full delivery costs for EUC, would be sufficient. The BER will be provided to ChMC for approval by January 9th Design: Design preparation is underway. Design will begin w/c Nov 12th . Design Changes packs will be issued on the 21st of December A baselined plan for all subsequent lifecycle stages will be provided during the Design phase, and will be provided to the ChMC on December 12th Currently tracking green from a risk perspective given that the project has only just mobilized. All risks will be regularly monitored throughout the project lifecycle High-level, estimated, costs for the change was provided within the HLSOIAs. The BER is set to be approved by ChMC on January 9th Weekly monitoring of SME resources ongoing