Exit Capacity – Managing Incremental Signals

Slides:



Advertisements
Similar presentations
Exit Reform Review Transmission Workstream 07 January 2010.
Advertisements

The Treatment of “Spare / Sterilised” Capacity – follow up Draft for discussion purposes only.
SO Incentives from April 2010 John Perkins. 2 Gas System Operator (SO) Incentives National Grid operates the high pressure Gas Transmission System in.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Mod 214 – Reservation of firm NTS Exit Capacity at new NTS Exit Points in the transitional period Steve Rose.
Third Workstream meeting re Baseline Re-consultation and Substitution 12 September 2007.
Modification proposal 0073 ‘Revision to the Notice Period regarding the implementation of changes to Transportation charges’ Transmission Workstream, 2.
Mod 166 Review Group Incremental Exit Capacity at New and Existing Exit Points.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
15 February 2006 TPCR second consultation: gas offtake Offtake Arrangements Workstream 15 February 2006.
Fundamental review of entry charging principles UNC Transmission Workstream - 6 th August 2009.
The calculation of the NTS Optional Commodity tariff (NTS Shorthaul) in the Enduring Exit Period Richard Hounslea/Debra Hawkin National Grid NTS, Gas Charging.
Supply Assumptions for Investment Planning Transmission Planning Code Workshop 1 3rd April 2008.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Entry Capacity Substitution: Discussion Document Transmission Workstream 7 th August 2008 Initial Analysis of Responses.
Demand Side Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review Group -140 Thoughts on additional information requirements.
National Grid - Key Challenges Beijing 24 October 2005 Alan Smart Optimisation & Risk Manager UK Transmission.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Estimation of Long Run Capacity Costs Gas TCMF 26 th April 2006.
Transitional Exit Capacity Proposals -Update Offtake Agreement Workstream, 30 Nov 05 Dave Adlam.
Mod 376: Increased Choice when Applying for Enduring NTS Exit Capacity Jeff Chandler - 5 th May 2011 Transmission Workgroup - Elexon 1.
Transitional Exit Capacity Proposals -Update Transmission Workstream, 1 Dec Nov 05.
Stuart Forrest, Network Planning Manager, Scotia Gas Networks 19 th October 2010 MOD Review of Industry Charging & Contractual Arrangements in Relation.
Transitional offtake arrangements – Ofgem Initial Proposals on transitional incentives 6 October 2005.
Accompanying Narrative
Interactions with the implementation of RIIO-T1
Transitional Exit Capacity Proposals -Update
SGN Modification Proposal Amendments to UNC TPD OCS Process Long Term Allocation of Capacity for the Transitional Period.
Exit Capacity Release Methodology Statement
An alternative approach…..
Modification Proposal 0283 Update
Transmission Workgroup 7th July 2011
Exit Capacity User Commitment – Transmission Workstream update
Transmission Workgroup 4th October 2012
Transmission Workstream, 2nd March 06
Transmission Workstream, 6 August
SO Incentives from April 2010
Capacity Methodology Statements: Impact of Mod 452
Capacity Methodology Statements
Danishtah Parker 0621 Workgroup 26 April 2018
Background Exit Reform Modification expected to be implemented 01 April 2009 But, decision has not yet been received Number of procedures/documents need.
Mod 0452 (PARCA) – Further thoughts
Transmission Workgroup June 7th 2012
COR1360 NTS Exit Reform (Mod 0195AV) UK-Link Committee 11th June 2009
Background to National Grid’s Baseline analysis
Update on Exit Capacity Substitution and Revision
Enduring NTS Exit Capacity Arrangements - Update
EU/GB Charging Project – Delivery Timescales
Development of Entry Capacity Substitution
QSEC auction timetable
Mod 0621 Amendments to Gas Transmission Charging Regime
Jeff Chandler - 3rd October 2013 UNC Tx Workgroup
Flow Swap Scenarios – Agreed Logic
Long Term Non Firm Capacity Update
Interruptible to Firm – NTS Supply Point Transition
Transmission Workstream – Partial Assignment
Review Group /09/2007.
UNC Transmission Workstream 7th December 2006
Proposed Transitional Gas Exit Arrangements
Entry Overrun Calculation
Reinstatement of NTS Interruption
Information Provision for Transitional Exit Capacity
Review Group 221: Review of Questions from Session 2
195AV “Future work” – system flexibility
What happened in Portugal’s recent record-breaking solar auctions?
Presentation transcript:

Exit Capacity – Managing Incremental Signals 7 May 2009

Potential Incremental Signals Initialisation will pare all capacity back to baselines* But based on User responses, transitional DC bookings and OCS data, we could see up to 3123 GWh/day of above baseline capacity signalled at 82 sites in the July 09 annual application window. This broadly breaks down as follows: *Except where ARCAs have been signed

Potential increase in obligations Key issue is how we manage this increase Highest demand day = 4862 GWh Funded as part of 2007 PCR Note: we would expect obligations to be significantly higher than demand as demand is diversified, whereas the obligations include previous interruptible loads, storage and interconnectors.

National Grid’s view (1) Increases in obligations above the enduring baselines represent an increase in risk - funding for which was not provided in the last PCR. However, it would not be economic and efficient to invest for all of these incremental increases nor pragmatic to request towards 100 revenue drivers. We also do not believe that it is beneficial that baselines move further and further away from the physical reality of the system and demand.

National Grid’s view (2) Also the nature of the increases are not necessarily the same: DCs – some power stations will require specific reinforcement, others will just tighten the existing system Storage – where operation mirrors historical behaviour, we would not expect to invest for exit, but storage is becoming more price rather than demand led, so some sites could inject on high demand days DNs – generally demand is not increasing, however the location is not always where it was envisaged to be at the 2007 PCR Therefore we believe we need to use a full range of tools, including baseline setting, to address the different characteristics described above

National Grid’s Suggested Approach (1) Request specific project revenue drivers for: Tonna / Abernedd Power Station Barking Power Station Coryton 2 Power Station ……….further evaluation after July window closes Undertake a baseline “re-jig” for DN sites based on the 2008 OCS for 2011/12, before 1 July 2009. Would reduce the need for further specific revenue drivers This would be limited to each DN Baselines that were not fully utilised in 2011/12, would be reduced to accommodate incremental requests above baselines Aggregate level of baselines for each DN would be unchanged This would reduce the potential incremental increase in DN obligations by 76%

National Grid’s Suggested Approach (2) Provide non-specific funding to manage the risk associated with the remaining incremental signals (storage, DCs and DNs), in one of the following forms: National generic revenue driver for load growth Zonal revenue driver(s) National long term contracting incentive Specific long term contracting incentive Review buy back scheme As can be seen there are a number of potential options in terms of funding for capacity increases, these need further evaluation and analysis, as they are not designed to be automatically applied to incremental capacity except for pre-defined exit points. The risk associated with these increases materialises in October 2012, although the treatment of them, in order to allow contracting solutions to be developed, would need to be agreed earlier. Therefore we have suggested an agreement in principle to revisit this issue as part of the next PCR and to provide appropriate funding to manage the increased risks.

Next Steps Any immediate feedback on this approach would be welcome to National Grid NTS (Martin Watson): martin.watson@uk.ngrid.com Assuming no significant issues are raised, intention would be to complete baseline “re-jig” by 1 July 2009.