Lafayette New Terminal Program Update January 9, 2019
Terminal Program Update FAA On site FAA Resident Inspector Currently managing grants LA DOTD AIP Grant 51/52 match received 100% DOTD grant received Terminal Program Update
Terminal Program Update LA FP&C Received Cooperative Agreement for FP&C contribution to QTA Provided documentation for construction award concurrence Coordinating with FP&C to confirm bid process and eligible items for terminal contribution 2019 Capital Outlay Application submitted Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application Revised EDA grant application submitted. Awaiting date for Decision Committee TSA OTA Application Submitted Grant Application, Waiting on Feedback Terminal Program Update
Terminal Program Update Airlines Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates Bids received Working with FP&C on approvals for NTP Concessions
Terminal Program Update Enabling Demo Demolition - Complete AOA fencing and gates – Complete Fill Material and Asphalt – Complete Seeding/Sod – Complete Substantially Complete Terminal Program Update
Terminal Program Update Enabling Demo – drone photo Terminal Program Update
Terminal Program Update Sod and seed at 310 Shepard Sod and seed at John Glenn
Terminal Program Update Sod and seed at demolished vaults area Sod and seed at demolished tower area
Terminal Program Update QTA Timeline: Oct. 2018: Commission Approved Updated CFC Nov. 2018: Construction Bids Due Dec. 2018: Approved Bids Jan. 2019: FP&C Construction Concurrence Feb. 2019: Award Contract and NTP Oct. 2019: Construction Complete Terminal Program Update
Terminal Program Update GMP 1: GMP 1 approved 9/25 Notice to Proceed 11/12 Schedule Starts: Nov. 2018: RTR Relocation and Enabling Parking Parking Impacts Nov. 2018: RTR Facility Construction Jan. 2019: Terminal Foundation Construction GMP 2: Structural Steel Construction/Elevations and Escalators GMP 2 Approval – Jan Commission GMP 3 100% Design is on Schedule in February April 2019 Approval Terminal Program Update
GMP1 – Project 1 New Terminal Construction Update Project 1 – RTR Cable Relocation IRMC was approved by FAA and preconstruction meeting completed Additional cable procured and ASI drawings in progress GMP1 – Project 1
GMP 1 – Project 2 RTR Facility New Terminal Construction Update Project 2 – RTR Facility Electrical service to the building trenched and concrete poured. Building pad structural fill hauled in, wet weather delayed compaction testing. GMP 1 – Project 2 RTR Facility
GMP 1 – Project 5 Enabling Parking New Terminal Construction Update Project 5 – Enabling Parking Installation of storm drainage pipe and boxes. Site stripping and electrical rough-in GMP 1 – Project 5 Enabling Parking