Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
07:30 – 10:30 Asynchronous dump test with Beam 2. No issue found. FIDEL update. Now chromaticity decay corrected. 12:13 Beam dump due to problem in the.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Saturday :12 Stable beams fill 3351 Initial luminosity
-9:00: Test IP transverse adjustment (CMS) and optics verification.
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
LHC Progress Week 6 Coordination: G. Arduini, E.B. Holzer
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 11: 14 – 21 March
LHC Morning Meeting - G. Arduini
Summary of week 22 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Mike Lamont, Jorg Wenninger
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Saturday – Morning 7:36 beams dumped
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Sunday
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday – Morning Fill 3265 stable beams since 1:31
Thursday 26th July 13:21 Fill 2880 beam dumped
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
LHC Morning Meeting - G. Arduini
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 23/2 Thanks CRYO!!!.
LHC Status Fro Morning 9-Sep
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Monday 27th August & night
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
31/3/2010 Difficult day… but at the end stable beams.
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM. Problems with the following injection due to intermittent loss of communication with the FGC. Traced back to an issue with a client of the FGC acquisition (Luminosity scan application). 15:27 STABLE BEAMS #2471 (47 on 47 bunches). Initial luminosity: 8.7x1031cm-2s-1 17:47 End of Fill #2471. 0.5 nb-1 in ~2:15 hours (OP dump) 19:54 Stable beam #2472. (84 on 84 bunches): Initial luminosity: 2.9x1032cm-2s-1 00:18 End of fill #2472. 3.5 pb-1 in 4:24 hours (OP dump) 01:00 – 01:50 no beam form LINAC2 01:50 – 07:30 Damper setting-up

Beam Lifetime Fill 2471 (47 bunches) Fill 2472 (84 bunches) Injection Ramp Squeeze Collision Injection Ramp Squeeze Collision

Fill 2470 - Pile-up (29 events) Average pile-up at beginning of fill should be ~20

Vacuum Some vacuum activity during injection and ramp (84 bunches)

Damper setting-up (D. Valuch, G. Hagmann) ADT setting up for high intensity summary: - We started setting up only after 2am due to a linac problem. - we prepared optimized settings for 1.1, 1.3, 1.5, 1.7e11 ppb (average intensity per bunch) - ADT is left with 1.5e11 settings for the Easter (front-ends will saturate around 1.7-2e11) - if significant increase of per bunch intensity is expected the ADT experts should be contacted to load proper settings - new settings validated with single bunches, should be fine also for the trains The transverse blow-up for loss maps is disabled by writing 'safe' settings. In case the application is needed please contact D. Valuch to re-enable it. The rbac protection was already prepared but the front-ends were not restarted yet. There is another update in the same package related to the post mortem buffer. After restarting the unit (HB1) the fixed display does not update anymore and status displayed in the ADT control application behaves strangely. It will be followed up.

Issues During Fill 2471: while injecting B2, losses on B1; as soon as the event of injection of B2 came, the losses stopped. Large emittance on 1st batch of 12.  Not understood Application for luminosity optimization crashing and slowing down communication with FGC (acquisition of the PC currents)  CO+OP follow-up. For the moment minimize the number of applications open VdM scan application: cannot enter integration time  CO+OP follow-up Fidel correction for decay and snap-back: chromaticity drifting at flat-bottom  Mike+Marek Page 1 data: Lint ALICE= Lint ATLAS Damper post-mortem (update required). Fixed display for injection oscillations (HB1)

MPS tests – asynchronous dumps Comparison 2011 to 2012 losses at IP5 – asynchronous dump in ‘collision’. Analysis done by collimation team  We looked in the details of the losses and noticed that losses in Q4/Q5 occur also with squeezed and separated beams, when the TCLs are still out. They could be caused by losses from the incoming beam 2 (the beta functions at the Q4/Q5 are now higher than in 2011) or by debris from the TCT of the other beam (TCTs are now ~3 sigma tighter than in 2011). The latter seems less likely but we cannot easily distinguish between the two cases looking at losses with the 2 beams. We therefore propose to repeat the synch bump tests at the end of the squeeze with beams separated, with B2 only.

Plan Asynchronous dump test ongoing Morning: Stable beams 84 on 84: LHCb field OFF Afternoon: Stable beams 268 on 268: levelling test (if OK from rMPP) Night: Stable beams 268 on 268: levelling test

Intensity ramp-up Bunches Max number of bunches injected Alice 3 1 2-3 fills and 4-6 hours with 48b, 84b, 264b and 624b (cycle validation) 3 fills and 20 hours with 840b, 1092b, 1380b (intensity/lumi related problems) MP checklists after 84b, 624b, 840b, 1092 bunches Regular MP checklists every two weeks when operating with 1380b Bunches Max number of bunches injected Alice 3 1 Main-main 48 12 Main-satellite 84 36 264 624 72 840 108 1092 1380 144