XRN4658 – OTR UNCVR Amendment eChMC – 23rd July 2018

Slides:



Advertisements
Similar presentations
Use Case: Use case title Submitter(s) Submitting Company #1 – Submitter 1, Submitter 2 Supporters(s) Supporting Company #1 – Submitter 1, Submitter 2 Use.
Advertisements

Presenters:- Steve Nunnington xoserve & Sallyann Blackett E.on Sallyann Blackett E.on Rolling AQ – A Straw Man.
A graph, non-tree representation of the topology of a gray scale image Peter Saveliev Marshall University, USA.
David Warne Independent Manufacturing Consultant.
AQ Amendment: Relevant UNC obligations and additional Validations Applied 27 May 2010.
© British Gas Further Analysis on Meter Reading Validation Tolerances proposed by Project Nexus March 2014.
UNC Review Group 0178 National Grid Distribution “Reclassification of SSP to Domestic only” Review Group Meeting – 22 February 2008 Chris Warner.
Meter Read Validation 11 th August Background The meter read validation principles were developed under ‘The Settlement’ BRD and formed part of.
Annie Griffith & Chris Fears September 2007 UK Link Technology Refresh.
Analysis of the Xoserve Read Validation Proposal Author: Alex Cullin 27/08/2014.
PN UNC Workgroup Read Validation 4 th October 2011.
1 UNC Review Group 175 – Encouraging Participation in the Elective Daily Metered Regime 26 th June 2008.
You have 10 seconds to name…
Rolling AQ – Initial Calculation
UNC Modification Proposal 0202 National Grid Distribution
平成30年6月 November 2007 Project: IEEE P Working Group for Wireless Personal Area Networks (WPANs) Submission Title: Technical requirements for 950MHz.
XRN4361 – UK Link Release 2 - Delivery
UKL Future Release 2 Cutover/Implementation
Online Gifts Buy for wishes happy mother's day to yours choice and with happy gifts find here:

Market Trials ChMC 8th August 2018.
Background - Tolerance Rules
Nexus Meter Read Performance April 2018

Figure 1 Mast Cells per mm T-blue c-kit Rejecting Naive
Resource Planning – Process Change
Release 3 Plan Options Decision
Review Group 178 SSP as Domestic only.
Read Tolerance Scenarios - UNCVR
DSC Change Committee Summary – 13th June
Background - Tolerance Rules
UKL Future Release 2 Cutover/Implementation
R&N Timeline Release 2 Release 3 Feb-19 June-19
Future Release 3.0 – Release 3 Industry Impacts & Recommendation
Overview XRN4665 is looking to add new EUC profiles for bands 01B & 02B New EUC profiles will be split based on Market Sector Code & Pre-Payment Meter.
DSC Change Committee Summary – 11th July
Release 3 Plan Options Analysis
DSC Change Committee Summary – 10th October
R&N Timeline June-19 Sept-19 (EUC) Nov-19 Minor Release D4
xrn4340 – UK Link Future Release 1.1
XRN4790 – Introduction of winter read/consumption reports
DSC Change Committee Summary – 8th August
Release 3 Update 07th March 2018.
Changes implemented February/ March 2019
Market Differentiation Workgroup Market Sector Flag Analysis
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
PN UNC AMR Topic Workgroup
Overall Project RAG Status:
Overall Project RAG Status:
Nexus Workgroup Winter Consumption and the influence on Winter Annual Ratio (WAR) Bands 8th January 2014.
Code Modification Proposal No 0315
Proposed June 2020 UK Link Major Release Scope / Governance Timeline
Retail & Networks ChMC Update
Development Work Group 0209 Straw Man Update
XRN4658 – OTR UNCVR Amendment
Earth’s History Flip book
Meter Read Rejections ..
Meter Reads.
COR3007: UNC MOD 450B – Monthly revision of erroneous SSP AQs outside the User AQ Review Period Implementation UK Link Committee – May 2014.
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Potential Minor Release Drop 4 Timeline & Scope
Annual Quantity (AQ) 45.
Change Proposals – PARR report changes
High Level System Solution Impact Assessment
High Level System Solution Impact Assessment
doc.: IEEE <doc#>
XRN4914 MOD Retrospective Data Update Provision
UK Link Timeline June-19 Sept-19 (EUC) Nov-19
Enabling Large Scale Utilisation of Class 3
DSC Change Committee Update
Presentation transcript:

XRN4658 – OTR UNCVR Amendment eChMC – 23rd July 2018

Implementation Approach R3 changing UNCVR via XRN3656 (splitting Band 2 into 2 bands) - orange XRN4658 amends the OTR value in bands 3-11 – blue cells Lower AQ Band (kWh) Upper AQ Band (kWh) Tolerances where read will be accepted Tolerances where a Read will be Accepted if Submitted within Override Flag (Inner Tolerance) Outer Tolerance Where Read will be Rejected (Market Breaker) 1 0% - 2,000,000% of AQ/365 x no. of days 2,000,001% - 7,000,000 % of AQ/365 x no. of days > 7,000,000% of AQ/365 x no. of days 2 100 0% - 20,000% of AQ/365 x no. of days 20,001% - 45,000 % of AQ/365 x no. of days > 45,000% of AQ/365 x no. of days 101 200 0% - 10,000% of AQ/365 x no. of days 10,001% - 25,000% of AQ/365 x no. of days > 25,000% of AQ/365 x no. of days 201 500 0% - 4,000% of AQ/365 x no. of days 4,001% - 55,000 % of AQ/365 x no. of days > 55,000% of AQ/365 x no. of days 501 1,000 0% - 2,000% of AQ/365 x no. of days 2,001% - 25,000 % of AQ/365 x no. of days > 25,000 % of AQ/365 x no. of days 1,001 5,000 0% - 400% of AQ/365 x no. of days 401% - 7,000 % of AQ/365 x no. of days > 7,000% of AQ/365 x no. of days 5,001 10,000 0% - 200% of AQ/365 x no. of days 201% - 2,000 % of AQ/365 x no. of days > 2,000% of AQ/365 x no. of days 10,001 20,000 0% - 150% of AQ/365 x no. of days 151% - 1,100 % of AQ/365 x no. of days > 1,100% of AQ/365 x no. of days 20,001 73,200 0% - 300% of AQ/365 x no. of days 301% - 1,100 % of AQ/365 x no. of days 73,201 732,000 0% - 250% of AQ/365 x no. of days 251% - 1,000 % of AQ/365 x no. of days > 1,000% of AQ/365 x no. of days 732,001 2,196,000 201% - 1,000% of AQ/365 x no. of days 2,196,001 29,300,000 151% - 700% of AQ/365 x no. of days > 700% of AQ/365 x no. of days 29,300,001 58,600,000 0% - 100% of AQ/365 x no. of days 101% - 400% of AQ/365 x no. of days > 400% of AQ/365 x no. of days 58,600,001 and above 101% - 350% of AQ/365 x no. of days > 350% of AQ/365 x no. of days

Implementation Approach Implementation planned for implementation coincident with R3 (Nov UKL Release) Implementation of 4658 leverages economies of scale of 3656 testing Does not seek to duplicate test scenarios, as 3656 demonstrates that the functional processes utilise the amended value Limited unique testing to demonstrate 4658 test scenarios work Combined System Test / User Acceptance Test cycle for 4658 If 4658 encounters functional issues, 4658 will be backed out so as to preserve 3656 implementation 4658 will be available in Market Trials by virtue of the common code component for 3656