Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Beam expected in the afternoon PM: – Establish first-turn – Establish closed orbit – Rough correction of machine parameters Evening: – RF capture Night:
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Summary of week 11 Machine Checkout Beam Commissioning R. Giachino, M. Albert, G. Arduini, J. Wenninger.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Ion Commissioning: Thursday & Friday
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wednesday September 14th
Wednesday 21 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Monday morning 08:30 Start of rephasing MD. Dry tests in the morning.
Tue :25 Beams dumped due to RF vacuum interlock
Thursday morning – optics correction
Monday 6th August & night
Machine availability reaching well over 80%
LHC Morning Meeting - G. Arduini
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Lost at 12:05 to power converter (RTQX2.R1) problem
Wednesday 8th August & night
Friday March 4th 08h32: Access for beam dump system.
Saturday 4.12 Beam in the SPS at 09:30 Beam in the LHC at 10:00
Tuesday 20 March 2012.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday Morning – recovery from cryo.
Monday February 28th 8h00: Injection
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Friday Morning 7:30 injection for fill 2908
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Programme for Saturday 10 July
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Summary for LPC (March 7th, Ralph Assmann)
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Wednesday 26 October 2011.
Wednesday morning Waiting for PS – problem on RF cavity.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV. Successful – no PC trips. 11:0 Ramp down, leveling test with CMS. 13:00 Final test of the injection kicker MKI. Synchronization after correction of the offsets (~160 ns). BETS on kicker voltage. 90 m 2/23/2019 LHC 8:30 meeting

Wednesday 16:00 SPS ready, Preparing for beam – pre-cycle. 17:00 ATLAS magnet ramping down… 18:00 Extraction into TI2 and TI8. TI8 to downstream TED OK. No beam extracted to TI2 – extraction kicker MKE6 does not trigger, despite correct conditions (BIS, BETS). When trying to inject B2, discover that the Probe Beam Flag of the SPS SMP is always FALSE. Must be TRUE to inject into empty ring (ensure low intensity). Reception error on the SPS SMP in the CCR – since 08.03.2012. 19:30 MKE6 problem traced to an electronic card. 20:15 MKE6 pulsing again, but a problem on the pulse delay (affected by the card change). 21:30 MKE6 delay problem finally fixed. 2/23/2019 LHC 8:30 meeting

Night 22:30 SMP problem solved by SMP team + CO piquet with support from BI and CO/HT. Beam injection was blocked as the SMPC SPS could not receive information from the BCT4 / 40S in SPS. The problem was traced to a low RS485\MIL1553 transmission level in BA4, resulting in a low value of power being received in the CCR, which was unable to be decoded by the SPS SMPC. CO Piquet was called to replace transmission module, this did not rectify the issue. Finally, a set of electrical repeaters were installed in BA4 to boost the signal strength to levels which could be decoded in the CCR. Consolidation is required at next opportunity. 2/23/2019 LHC 8:30 meeting

Night – beam into the LHC 23:00 Injecting into LHC and moving from one IR to the next (collimators). Very little steering required. A few post-mortems from BLMs – seems the TCTVA thresholds in IR2 could be a bit low… 23:40 B1 circulating and partly captured. 00:30 B2 circulating and partly captured. 2/23/2019 LHC 8:30 meeting

Progress on capture and quality Working on orbit, tune, Q’ – in parallel RF team in SR4. 2/23/2019 LHC 8:30 meeting

Orbit 01:00 Closed orbit corrected to within 0.2 mm rms of the 2011 flat orbit reference. 2/23/2019 LHC 8:30 meeting

Injection oscillations 2/23/2019 LHC 8:30 meeting

Tunes Vertical Q was too low by ~ 0.06 Trimmed down by -20… final settings for B1 and B2 (|C-| about 0.01); LHCBEAM1/CMINUS_IM.IP1  0 LHCBEAM1/CMINUS_RE.IP1  0 LHCBEAM2/CMINUS_IM.IP7  -0.045 LHCBEAM2/CMINUS_RE.IP7  -0.02 LHCBEAM1/QH_TRIM        0.001 LHCBEAM1/QV_TRIM        0.06529 LHCBEAM2/QH_TRIM        -0.03 LHCBEAM2/QV_TRIM        0.07 Q’ found around +25 later in the night. Trimmed down by -20… 2/23/2019 LHC 8:30 meeting

First dumps 2/23/2019 LHC 8:30 meeting

BSRT 2/23/2019 LHC 8:30 meeting

Night 04:00 RF setup finished. Phase adjusted. Offset of 5 ns corrected. Setting up should be OK up to 1.5E11. Should check the frequency trim of -10 Hz that was applied, as it is de-centered the orbit. Some energy matching with H cods to be done.. Optics team starting their work… 2/23/2019 LHC 8:30 meeting

Today Optics measurements and correction at 450 GeV Injection and orbit with nominal bunch. FB setting up. BI shift overnight. 2 THU M 8 Beta beating measurements and correction @ 450 GeV M/A 4 Injection of nominal bunch A Flat reference orbit at injection with nominal bunch, FB setup N BI shift 3 FRI RF and Damper setup for nominal bunch Feedbacks – re-commissioning at injection (Q, orbit, radial) Ramp to 4 TeV - test QFB & OFB Aperture at injection 2/23/2019 LHC 8:30 meeting