Testing Plan and Status

Slides:



Advertisements
Similar presentations
BEPCII Cryogenic Control Gang Li IHEP, Beijing,China.
Advertisements

UNICOS-CPC applied to Cryogenics and specifications Benjamin Bradu EN-ICE-PLC February 2014.
-P&ID- Piping & Instrument Diagram
SCADA and Telemetry Presented By:.
A Lessons Learned Discussion of Digital Control Upgrades How to Make Sure Your Digital Upgrade is Over- Budget, Over - Schedule, and Everyone’s Vacation.
PLC introduction1 Discrete Event Control Concept Representation DEC controller design DEC controller implementation.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
LHC Cryogenics Control: INTEGRATION OF THE INDUSTRIAL CONTROLS (UNICOS) AND FRONT-END SOFTWARE ARCHITECTURE (FESA) APPLICATIONS Enrique BLANCO Controls.
Calibration PT Honeywell Chapter 7 InstrumentationELC-213Today Presentation by Clifford T. Johnson, PE, Control Systems Engineer Honeywell Primer Auxiliaries.
CISSP Common Body of Knowledge Review by Alfred Ouyang is licensed under the Creative Commons Attribution-NonCommercial-ShareAlike 3.0 Unported License.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
1. Engineering 2. Purchasing 3. Other department package assistances 4. Site supervision Instrument Department Activities:
 SOFTCON SYSTEMS PVT. LTD. (SSPL) offers unique, creative and practical automation solutions in the field of Process & Power on an LSTK / EPC basis with.
Lesson 1 PLC BASICS. PLC Definition  Programmable Logic Controllers are industrial computers that control machine and other applications.  PLC have.
Lessons Learned Implementing an IEC based Microgrid Power-Management System October 12, 2015 Presented by: Jared Mraz, P.E.
Combining safety and conventional interfaces for interlock PLCs
Cryogenic Plant Controls - Configuration
Director’s Progress Review Closeout Meeting
Cryoplant Controls Installation
Cryogenic Plant Controls – Cost and Schedule
Installation Procurement Package
Cryogenic Plant Electrical and Controls
2K Cold Box FDR Introduction
Cryomodule test stand at ESS site
Control System Instrumentation
PLC Terminology and Application
2K Cold Box PDR Introduction
LCLS-II CRYOPLANT CONTROLS HARDWARE FINAL DESIGN REVIEW
Electrical and Controls
Accelerator Operations Department Readiness (Part 2)
FRIB PLC Testing & Verification Process
Cryoplant Installation Scope
LCLS-II 2K Cold Box Controls Design Review
Current Status of ITER I&C System as Integration Begins
How SCADA Systems Work?.
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
LCLS-II Cryoplant Controls Readiness to Procure
Cryogenic C&C Scope of work
Instrumentation and Controls
2K CB FDR Overview:  Agenda, Charge, Review Process
Flow-X/C Flow Computer
SC1R Cold Box PDR Controls
Programmable Logic Controllers (PLCs) An Overview.
EPICS Controls Steve Lewis 13 December 2007
Director’s Progress Review Closeout Meeting
Cryogenic Plant Controls – Safety Switches
Cryoplant Installation Design Summary
CERN with UNICOS M. Pezzetti AT_ECR_CE 27 June 2005.
LCLS-II Cryoplant Controls FDR Status of Past Reviews and Lessons Learned Dana Arenius Sept 13, 2017.
Instrumentation and control
PLC Coding and Local HMI
Charge 2. Equipment Protection 3. Definition and Documentation
Scope, Requirements Deliverables & Schedule
Documentation Chris Scanlon and Ritendra Bhattacharya
Overarching Commissioning Plan
Operator Training Requirements
Vertical Cryostat Kick-off metting
Control Hardware & Status
SNS Cryoplant Commissioning Past Experiences
CryoPlant Commissioning
KAGRA PLC System Overview
PSS verification and validation
Automation Connections ISA EXPO 2006
DOE Review 7-9 February, 2006 Steve Lewis
Operation of Target Safety System (TSS)
Commissioning the European XFEL cryogenic system and best practice
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Vacuum Control System for Monolith Vacuum
Presentation transcript:

Testing Plan and Status Chris Scanlon LCLS-II Software Review November 14, 2018

Charge 1. GENERAL a. Is the documentation and coding maturity consistent with the schedule? b. Is the schedule compatible with the overall plan including installation and commissioning? 2. EQUIPMENT PROTECTION a. Are all equipment protection functions (in particular responses to abnormal conditions such as trips, alarms and interlocks) comprehensive, clearly identified, documented, implemented and traceable to the PLC code? 3. DEFINITION AND DOCUMENTATION a. Are all automated functions (alarms, trips, interlocks / permissive, cause and effects, control loops, and automated sequences) sufficiently documented for coding, testing, commissioning, operation and troubleshooting? 5. BENCH TESTING a. Has JLAB developed an appropriate plan for testing the CRYOPLANT control systems? b. Is the EPICS HMI testing integrated with the PLC tests? 6. COMMISSIONING c. Does JLAB’s plan for commissioning and testing of the coldboxes appropriately address commissioning and checkout of the PLC controls prior to testing the coldboxes? LCLS-II Software Review, November 14, 2018

Outline Testing Steps Testing Plan Testing Status LCLS-II Software Review, November 14, 2018

Testing Plan – Bench Testing Using the software and testing specifications, test every I/O and functionality: I/O scaling Alarms Trips Interlocks PID loops Calculations Correct representation in the HMI This speeds commissioning by reducing potential software bugs and increasing trust in the software. Put dates for expected testing completion. LCLS-II Software Review, November 14, 2018

Testing Steps – Bench Testing Tests software functionality Alarms, trips, interlocks, correct I/O ranges, sequences, PID loops, etc HMI testing is included in this. Outlined in 79120-C6004 LCLS-II Cryoplant Software Testing Specification: LCLS-II Software Review, November 14, 2018

Testing Plan – Bench Testing Due to the graphic nature of ladder logic, used to program most of the LCLS-II cryoplant PLC functionality, troubleshooting is relatively simple. Any errors found during bench testing will be corrected as part of the testing process. Errors found in the documentation will be corrected at the conclusion of testing. LCLS-II Software Review, November 14, 2018

Testing Steps – Precommissioning Precommissioning plant check out Tests installed hardware, instruments and cabling Turn on PLC and determine which inputs are not functioning properly, lift wire to inputs to verify correct input assignment. To troubleshoot: Verify wiring between PLC and field box Resistance test to verify not open Disconnect wire to verify correct terminals Verify wiring between field box and instrument Verify functionality of the instrument (if possible) Source loop power or command with process meter Valves need to be calibrated individually after installation. Pressure transducers will be calibrated in the field in lieu of lifting a wire. Determine safety of actuating outputs before testing. LCLS-II Software Review, November 14, 2018

Testing Steps – Precommissioning An example from the Software Testing Specification 79120- C6004 LCLS-II Software Review, November 14, 2018

Testing Steps – Precommissioning An example from the Software Testing Form 79120-C6005 LCLS-II Software Review, November 14, 2018

Testing Plan – Precommissioning Using the cryoplant wiring diagrams, verify all I/O and wiring. This reduces commissioning time by reducing the number of holds for troubleshooting a problem and increasing trust in the wiring and instrumentation. LCLS-II Software Review, November 14, 2018

Testing Status – Controls Enclosures Controls Enclosure Inspection Each control enclosure that will be installed by the GC was inspected by at least three people from the LCLS-II project. Spot checks were performed for point to point wiring, resistance check, pull test and instrument functionality LCLS-II Software Review, November 14, 2018

Testing Status – Bench Testing Bench testing has started for the 2K cold compressor drive communication. This is the big difference between the way the cold compressor are controlled at Jlab versus LCLS-II. JLab asked for assistance with cold compressor communication from the FRIB project, which use the same cold compressor drives, but FRIB refused. After successful cold compressor drive communication, full bench testing will start with the utility system PLC software and then the gas management system PLC software. LCLS-II Software Review, November 14, 2018

Testing Status – Bench Testing Air Liquide developed the control philosophy (software specification) and agreed to back and forth software development. We had a meeting in September to discuss the differences between LCLS-II’s operational ideas and Air Liquide’s Air Liquide has responded with a revised control philsophy Air Liquide will visit JLab and witness the final testing of the 4K cold box PLC software. Air Liquide will review JLab’s PLC code before commissioning. LCLS-II Software Review, November 14, 2018

Testing Status – Bench Testing PLC racks Cold compressor drive The current state of bench testing at JLab. At least one of each instrument and I/O card is available. LCLS-II Software Review, November 14, 2018

Charge 1. GENERAL a. Is the documentation and coding maturity consistent with the schedule? Yes. b. Is the schedule compatible with the overall plan including installation and commissioning? Yes. 2. EQUIPMENT PROTECTION a. Are all equipment protection functions (in particular responses to abnormal conditions such as trips, alarms and interlocks) comprehensive, clearly identified, documented, implemented and traceable to the PLC code? Yes. 3. DEFINITION AND DOCUMENTATION a. Are all automated functions (alarms, trips, interlocks / permissive, cause and effects, control loops, and automated sequences) sufficiently documented for coding, testing, commissioning, operation and troubleshooting? Yes. 5. BENCH TESTING a. Has JLAB developed an appropriate plan for testing the CRYOPLANT control systems? Yes. b. Is the EPICS HMI testing integrated with the PLC tests? Yes. 6. COMMISSIONING c. Does JLAB’s plan for commissioning and testing of the coldboxes appropriately address commissioning and checkout of the PLC controls prior to testing the coldboxes? Yes. LCLS-II Software Review, November 14, 2018

THANK YOU FOR KIND ATTENTION LCLS-II Software Review, November 14, 2018