EST102: Estates will issue new procurement schedule.

Slides:



Advertisements
Similar presentations
Tendering Yuck!.
Advertisements

Integrated Baseline Review What is it? Why should I want one? Joseph A. Jankoviak, PMP, PMI-RMP.
1 ISA&D7‏/8‏/ ISA&D7‏/8‏/ ISA&D7‏/8‏/2013 IS Projects: Success and Failure Role of the Project Manager Project Management Tasks in SDLC.
©2010 asapm asapm Project Management Communities of Practice - PMCoP Program.
Key components Budgeting and Planning System
Code Governance Review: follow up. 2 Background CGR implementation PID included the following deliverable –“achieve a demonstrable cultural shift within.
Introduction. Service Update Property Investment Residential Care to Supported Living New Business Recruitment and Retention.
CONSTRUCTING WEST MIDLANDS Question & Answer Session 22 nd March 2011 LOT 7 – CAPITAL WORKS.
Presenter: Igna Visser Date: Wednesday, 18 March 2015
Risk Management DIA Working Group 22 May 2017.
Project Management Processes
Presenter Name | Company Name
SIP Report – Nov 2017 Overview Headlines Workstream report
Thinking of changing your Library Management System?
Phase 2 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
MOSH Leading Practices Adoption System
The Lean Sourcing Process
Phase 3 Tollgate Review Discussion Template
Eagle Programme : 4 Box Summary
Sustainable Transition / Handover of malaria TB and HIV Global Fund Grants Generic 2018.
Presenter Name | Company Name
Stan Whitcomb LSC meeting Livingston 21 March 2005
EST102: 09/10/17: Indicative Contract Award.
Presenter Name | Company Name
Project Management Process Groups
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 1st Feb to 12th Feb Feb 2018: 10 day Standstill
Phase 2 Tollgate Review Discussion Template
Student Administration and Support Programme and Project Timelines
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Student Administration and Support Programme and Project Timelines
Project Management Processes
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Presenter Name | Company Name
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST102: 12th Feb to 9th Mar 2018: Negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 17/11/17: Uptake of Customer References.
EST103: Implementation Planning Underway
EST103: Inputs for implementation planning complete. NEXT STEPS
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
The emphasis of Construction Management and Preconstruction Services in the AEC industry Preconstruction Services Construction Management.
Reasons for Change Modernisation long overdue!
EST102: 10/10/17: Cost Review Meeting.
EST102: 25/10/11: Project Services Website rationalised.
Student Lifecycle Project 14th May 2008
Student Administration and Support Programme and Project Timelines
EST103 Estates myProject Implementation Project Report 02/11/18
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 22/02/19
Presenter Name | Company Name
Overview Headlines RSP – Progress Overview General progress report
Introduction to Project Management
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Executive Project Kickoff
EST103 Estates myProject Implementation Project Report 01/02/19
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 09/11/18
EST103 Estates myProject Implementation Project Report 03/05/19
EST103 Estates myProject Implementation Project Report 10/05/19
EST103 Estates myProject Implementation Project Report 08/02/19
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 30th Mar 2018: Complete negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Presentation transcript:

EST102: Estates will issue new procurement schedule. EST102 & EST103 Estates Capital System Procurement & Implementation Project Report 13/10/17 R A G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston Business Project Manager: Jane Cameron IS Estates Programme Manager: Derrick Matheson IS Project Manager & BA: Lyn Thomson ACHIEVEMENTS EST102: 12/09/17: Vendor demonstrations completed and scored. EST102: 29/10/17: All scoring complete for IS question sets and consensus meetings held. EST102: 04/11/17: All scoring complete for Business question sets and consensus meetings held. EST102: 10/10/17: Cost review meeting held. No further clarifications are required from the 2 lowest scoring vendors. Decision taken to carry out site visits to existing customers and invite for further clarification meetings for the 3 highest scoring vendors. EST103: Steady progress on planning, governance arrangements and TOM for the future EPPM service. NEXT STEPS EST102: Estates will issue new procurement schedule. EST102: Customer Site Visits. EST102: Vendor Clarification Interviews. EST102: 20/10/17: Notify Vendors of Decision. EST102: 31/10/17: Indicative Contract Award. EST103: 27/10/17: Prepare Implementation Plan. EST103: 27/10/17: Prepare Project Brief. MILESTONES Baseline Actual/ Predicted EST102 ITT Issued 27/07/17 EST102 Responses from Vendors Received 21/08/17 EST102 Notify Vendors of Decision 13/10/17 20/10/17 EST102 Indicative Contract Awarded 24/10/17 31/10/17 EST102 Contract Finalised 17/11/17 24/11/17 EST103 Initial Planning & Project Brief 29/09/17 27/10/17 EST103 Phase 1 DPI – Programme Management May 2018 EST103 Phase 1 DP2 – Cost Management Aug 2018 EST103 Phase 1 DP3 – Portfolio Management Nov 2018 EST103 Phase 2 DP4 – Project Management Jan 2019 RISKS & ISSUES RISK 1: Late completion of procurement will delay implementation: Begin any possible   “generic” planning and design in advance of knowing the identity of the   application that will be installed to smooth and speed the implementation. RISK 2: Too much change happening at the same time in Estates limiting the availability of Estates Resource at the right time: Good governance and stakeholder management. RISK 3: Unable to recruit new staff into Estates in time to support the new operating model which is required to successfully transition to the new application: Working on TOM, roles & responsibilities matrix leading to gap analysis to identify existing colleagues that can cover the work were possible. RISK 4: Existing data will not be of required quality to migrate to the new system: Thorough data analysis   exercise supported by 3rd party experience, early start to data cleansing, clear plan for cut-over. RISK 5: Technical Integrations may be more extensive & difficult than expected: work with identified third party supplier as early as possible to understand the number of integrations required and options. Set expectations with the business. RISK 6: 3rd party risks –   cultural, relationship, availability: Full OJEU procurement exercise (EST102) and contract, Support agreement, Hosting agreement, focus on   experience of 3rd party team during the procurement cycle.