EST102: 17/11/17: Uptake of Customer References. EST102 & EST103 Estates Capital System Procurement & Implementation Project Report 03/11/17 R A G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston Business Project Manager: Jane Cameron IS Estates Programme Manager: Derrick Matheson IS Project Manager & BA: Lyn Thomson ACHIEVEMENTS EST102: 10/10/17: Cost review meeting held. No further clarifications are required from the 2 lowest scoring vendors. Decision taken to carry out site visits to existing customers and invite for further clarification meetings for the 3 highest scoring vendors. EST102: 25/10/11: Project Services Website rationalised. EST103: 24/10/11: Project Implementation plan updated with feedback from Programme Manager & v0.2 issued. EST102: 1/11/17: New schedule agreed for completion of procurement. EST102: 30/10/17: Write up of feedback on questions sets & procurement experience complete and submitted to Dave Berry & Andy Stewart EST103: 30/10/17: Initiation of project delivery meetings with Estates. EST103: 01/11/17: First draft of Project Brief and set up of Project Services website. NEXT STEPS EST102: 17/11/17: Uptake of Customer References. EST102: 07/12/17: Vendor Clarification Interviews. EST102: 08/12/17: Notify Vendors of Decision. EST102: 19/12/17: Indicative Contract Award. EST103: 07/11/17: Meeting with Mark Ritchie to review project brief & plan, proceed to WIS for approval. EST103: 06/11/17: EqIA completion EST103: 08/11/17: Resource plan set up on ASTA EST102: Further engagement meeting with IS team leads MILESTONES Baseline Actual/ Predicted EST102 ITT Issued 27/07/17 EST102 Responses from Vendors Received 21/08/17 EST102 Notify Vendors of Decision 13/10/17 08/12/17 EST102 Indicative Contract Awarded 24/10/17 19/12/17 EST102 Contract Finalised 17/11/17 26/01/18 EST103 Initial Planning & Project Brief 29/09/17 10/11/17 EST103 Phase 1 DPI – Programme Management May 2018 EST103 Phase 1 DP2 – Cost Management Aug 2018 EST103 Phase 1 DP3 – Portfolio Management Nov 2018 EST103 Phase 2 DP4 – Project Management Jan 2019 RISKS & ISSUES RISK 1: Late completion of procurement will delay implementation: Begin any possible “generic” planning and design in advance of knowing the identity of the application that will be installed to smooth and speed the implementation. RISK 2: Too much change happening at the same time in Estates limiting the availability of Estates Resource at the right time: Good governance and stakeholder management. RISK 3: Unable to recruit new staff into Estates in time to support the new operating model which is required to successfully transition to the new application: Working on TOM, roles & responsibilities matrix leading to gap analysis to identify existing colleagues that can cover the work were possible. RISK 4: Existing data will not be of required quality to migrate to the new system: Thorough data analysis exercise supported by 3rd party experience, early start to data cleansing, clear plan for cut-over. RISK 5: Technical Integrations may be more extensive & difficult than expected: work with identified third party supplier as early as possible to understand the number of integrations required and options. Set expectations with the business. RISK 6: 3rd party risks – cultural, relationship, availability: Full OJEU procurement exercise (EST102) and contract, Support agreement, Hosting agreement, focus on experience of 3rd party team during the procurement cycle.