EST103: Implementation Planning Underway

Slides:



Advertisements
Similar presentations
Business Project Plan Presenter Name | Company Name.
Advertisements

Update to NLAG board 22 nd December Sep Jan MCE Workforce and OD Oct Nov Dec IM&T Estates Finance In hospital Model Out of hospital Model Progress.
Overview of Structure General Data Protection Regulation (GDPR)
Presenter Name | Company Name
Presenter Name | Company Name
Presenter Name | Company Name
SIP Report – Nov 2017 Overview Headlines Workstream report
Thinking of changing your Library Management System?
Phase 2 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
SmartMeterTM Steering Committee Update – September 2012
Phase 3 Tollgate Review Discussion Template
“ You’re hired” Apprenticeships and the RDS - a WSFRS approach.
Presenter Name | Company Name
Eagle Programme : 4 Box Summary
Presenter Name | Company Name
EST102: 09/10/17: Indicative Contract Award.
Update to NLAG board 24th November 2015
SmartMeterTM Steering Committee Update – March 2013
Student Administration and Support Programme and Project Timelines
Presenter Name | Company Name
Iowa College Aid Processing System (ICAPS)
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 1st Feb to 12th Feb Feb 2018: 10 day Standstill
Student Administration and Support Programme and Project Timelines
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Overall Project RAG Status
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Student Administration and Support Programme and Project Timelines
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Presenter Name | Company Name
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
Ongoing consultation, engagement and awareness raising
EST102: 12th Feb to 9th Mar 2018: Negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: Estates will issue new procurement schedule.
EST102: 17/11/17: Uptake of Customer References.
SmartMeterTM Steering Committee Update – July 2012
EST103: Inputs for implementation planning complete. NEXT STEPS
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
SmartMeterTM Steering Committee Update – February 2013
EST102: 10/10/17: Cost Review Meeting.
EST102: 25/10/11: Project Services Website rationalised.
Student Administration and Support Programme and Project Timelines
EST103 Estates myProject Implementation Project Report 02/11/18
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 22/02/19
Overall Project RAG Status
Presenter Name | Company Name
Overview Headlines RSP – Progress Overview General progress report
XRN Nov 19 Release - Status Update
Introduction to Project Management
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
RSP – Progress Overview General progress report High level plan
EST103 Estates myProject Implementation Project Report 01/02/19
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 09/11/18
EST103 Estates myProject Implementation Project Report 03/05/19
EST103 Estates myProject Implementation Project Report 10/05/19
EST103 Estates myProject Implementation Project Report 08/02/19
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
XRN 4927 – MiR Drop 4 - Status Update
EST102: 30th Mar 2018: Complete negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Proposed core price & service spec L1 product milestone 31 Dec 2019
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Presentation transcript:

EST103: Implementation Planning Underway EST102 & EST103 Estates Capital System Procurement & Implementation Project Report 15/09/17 R A G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston Business Project Manager: Jane Cameron IS Estates Programme Manager: Derrick Matheson IS Project Manager & BA: Lyn Thomson ACHIEVEMENTS EST102: ITT Issued 27th July EST102: Technical question sets feedback to Dave Berry for continuous improvement of the standard question sets. EST103: WIS approval received 25/08/17 EST103: Implementation Planning Underway EST102: Vendor Demonstrations completed 11th & 12th September and scoring completed after moderation meeting. EST102: Scoring of written vendor responses underway. NEXT STEPS EST102: Scoring of written vendor responses to ITT 23rd Aug – 27th Sept EST102: Consensus Meetings 28th Sept – 4th Oct EST103: Prepare Implementation Plan. EST103: Prepare Project Brief. MILESTONES Baseline Actual/ Predicted ITT Issued 27/07/17 Responses from Vendors Received 21/08/17 Indicative Contract Awarded 09/10/17 Contract Finalised 17/11/17 Initial Planning & Project Brief 29/09/17 Phase 1 DPI – Programme Management May 2018 Phase 1 DP2 – Cost Management Aug 2018 Phase 1 DP3 – Portfolio Management Nov 2018 Phase 2 DP4 – Project Management Jan 2019 RISKS & ISSUES RISK 1: Late completion of procurement will delay implementation: Begin any possible   “generic” planning and design in advance of knowing the identity of the   application that will be installed to smooth and speed the implementation. RISK 2: Too much change happening at the same time in Estates limiting the availability of Estates Resource at the right time: Good governance and stakeholder management. RISK 3: Unable to recruit new staff into Estates in time to support the new operating model which is required to successfully transition to the new application: Working on TOM, roles & responsibilities matrix leading to gap analysis to identify existing colleagues that can cover the work were possible. RISK 4: Existing data will not be of required quality to migrate to the new system: Thorough data analysis   exercise supported by 3rd party experience, early start to data cleansing, clear plan for cut-over. RISK 5: Technical Integrations may be more extensive & difficult than expected: work with identified third party supplier as early as possible to understand the number of integrations required and options. Set expectations with the business. RISK 6: 3rd party risks –   cultural, relationship, availability: Full OJEU procurement exercise (EST102) and contract, Support agreement, Hosting agreement, focus on   experience of 3rd party team during the procurement cycle.