Heidelberg Module Production Straw Production: Modification of straw confectioning machine successfully finished: reliable crimping of wire locators optimization of hole production process Significant speed-up: 4 min / straw for cutting etc. 2 min / straw for soldering Production runs full swing (i.e. ~200 straws / week)
Heidelberg Module Production Module-0 finished last week: currently being tested Production of Module-1 has started and is already 60% completed Serial Production has started !! Our goal of 1 module / 7 days seems feasible Biggest worry now: material flow ! Technology: Panel gluing: using glue strips at every at 5 cm from glue thickened with silica power gives excellent results
Heidelberg Module Production