Thursday Fill 1364 (24 bunch) dumped at 07h

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
LHC Status Tue Morning 22-Aug
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday fill with 1092 bunches (6 h stable beams)
LHC Morning Meeting - G. Arduini
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
LHC Operation Week 38 Coordination G.Arduini, R.Bailey
Lost at 12:05 to power converter (RTQX2.R1) problem
LHC Morning Meeting - G. Arduini
Friday 31st August & night
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Chromaticity can make a difference…
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
Yesterday’s morning’s controls issues
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Ramp single nominal bunches for loss maps
Aims for the week Recover from technical stop and precycle at 10A/s
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Saturday Nov Stop proton operation. Switch back to ions
Tue/Wed 12/ :00 Probe beam back again
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
LHC Status Tue Morning 22-Aug
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary Tuesday h23: Machine closed. Precycle started.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Saturday 24 September 2011.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Thursday 20th July - morning
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Saturday 6th October 05:38 STABLE BEAMS # :06 OP dump
Friday :47 stable beams fill 3273
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Wednesday 6.10 Morning: Quench test at 450 GeV
Saturday 26 November 2011.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Monday 152 bunch operation summary
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

Thursday Fill 1364 (24 bunch) dumped at 07h Access needed for quench heater power supply sector 45 Adjust longitudinal blow-up to better track fast bunch reaction... Reduced time constant and increased gain Beam injected 11.30 Trip of RSF2.A56B1 Dump test on BPMSB.B4L6.B2 PM analysis shows that in fact the dump was triggered some 1000 turns or so after the beam position stabilized. Next time (!) we will trim such the final target position is well beyond the interlock limit to be able to judge the reaction time of the interlock 13.30 Start physics fill 1365 (Scheme 150ns_56b_47_16_47_8bpi) Tune feedback switched OFF at 800 GeV for beam 2 Beams dumped at end of ramp. TCDQ B1 interlock ALICE dipole tripped due to electrical perturbation at point 2 (20 minutes later) 2/25/2019 LHC status

Injection (DC BCT looks OK) wirescan before ramp B2H 2.0 B2V 2.25 B1H 1.67 B1V 1.68 2/25/2019 LHC status

Injection and ramp (long blowup now OK) 2/25/2019 LHC status

Ramp (no B2 tune signal) Most likely the tune spectra went flat because with the high intensity in the machine the diodes in the BBQ detectors go into Zener regime. To cure it, the parallel resistors in the "BBQ-Front-end Gain Settings" should be on. Fixed by the experts. 2/25/2019 LHC status

Ramp (TCDQ position monitoring) TCDQ B1 position and limits during the ramp We see a glitch in the position readings at the moment of the beam dump, which correspond exactly to the end of the ramp function. 2/25/2019 LHC status

TCDQ position monitoring TCDQ internal protection against displacement overshoot at a start of a displacement (force positioning reading at first point of the ramp for limited duration) has been triggered at the beginning of the ramp. Good positioning condition have been reached (damping of the overshoot oscillation) and protection stopped before the end limit of the protection duration. Remaining part of the interlock duration has been played after the transition from MOTION_EXECUTION to IDLE at the end of the ramp (to be investigated) resulting in a dump request through the positioning and energy interlocking logics. 2/25/2019 LHC status

Thursday 16.00 Start physics fill 1366 (Scheme 150ns_56b_47_16_47_8bpi) No beam from LINAC for a while 17.30 Fill for physics Many latches of IQC 19.00 Collisions and stable beams Initial luminosities ~ 2 1031 cm-2 s-1 For these intensities ε ~ 2.2 µm.rad Congratulations .... this is wonderful !! ALICE reports they see "parasitic collisions" which force them to stop taking data Polarity issue ? Integrated luminosity in ~ 13 hours ~ 650 nb-1 End of fill emittance studies wirescan @ start ramp B2 H 2.14 B2 V 2.33 B1 H 1.88 B1 V 1.86 2/25/2019 LHC status

Start of fill 1366 2/25/2019 LHC status

losses in the beta-cleaning insertion 2/25/2019 LHC status

Lifetimes 2/25/2019 LHC status

Currents and losses fill 1366 (56_47_16_47) IPs: 1 5 2 8 - 1 5 8 - 1 5 2 - 1 5 - 2 8 - 8 2/25/2019 LHC status

Friday Some time needed to tune up transfer lines (injection oscillations) ALICE Next steps Scheme 150ns_56b_47_16_47_8bpi Scheme 150ns_104b_93_8_93_8bpi 2/25/2019 LHC status

To fit in later Transverse damper firmware update (to prevent glitches positions very close to 0) – W. Höfle Test of luminosity optimization software - S. White Gas Ionization Profile Monitor tests - M. Sapinski Abort gap cleaning – M. Meddahi Test of new beam presence flag system – M. Gasior DC BCT – P. Odier Q kicker – R. Barlow CO security intervention to be scheduled - A.Bland 2/25/2019 LHC status