Overall Project RAG Status

Slides:



Advertisements
Similar presentations
XRN4361 – UK Link Release 2 - Delivery
Advertisements

XRN4572 – UK Link Release 3 - Design
Market Trials ChMC 8th August 2018.
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Plan Options Decision
Overall Project RAG Status:
Amendment Invoice Task Force Progress Report
Release 3 Update December 2018.
XRN4340 – UK Link Future Release 1.1
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
EUC Project Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
Release 3 Plan Options Analysis
XRN4361 – UK Link Release 2 - Delivery
Change Proposals Capture to Delivery
Amendment Invoice Task Force Progress Report
Amendment Invoice Task Force Progress Report
Release 3 Update 9th January 2019.
Overall Project RAG Status:
xrn4340 – UK Link Future Release 1.1
Release 3 Update 13th February 2019.
Amendment Invoice Task Force Progress Report
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
June 19 Timelines Key Upcoming Dates:
4361 – UK Link Future Release 2
Release 3 Update 07th March 2018.
Release 3 Scope & Proposed Plan
Release 3 Scope Selection and Plans
Change Management Committee – Retail & Networks Update
XRN4361 – UK Link Release 2 Project Status Update
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
4361 – UK Link Future Release 2
4340 – UK Link Future Release 2
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Overall Project RAG Status:
Overall Project RAG Status:
XRN4361 – UK Link Future Release 2
Overall Project RAG Status
XRN June 19 Release - Status Update
Change Management Committee – November 2019 Release Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
Release 3 Update 07th March 2018.
XRN4361 – UK Link Release 2 - Delivery
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
XRN November 2019 Release - Status Update
4340 – UK Link Future Release 1.1
XRN Nov 19 Release - Status Update
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
XRN June 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
XRN4361 – UK Link Release 2 - Delivery
Presentation transcript:

Overall Project RAG Status XRN4572 – UK Link Release 3 04th Oct 2018 Overall Project RAG Status A Plan/Time Risks and Issues Cost Resources RAG Status G R Status Explanation Objective Full project delivery of UK Link Future Release 3 Scope Extraordinary Change Management Committee on 23rd of July approved the split delivery of Release 3 scope into 13 CRs on 2nd of November and XRN 4454 to be delivered on 1st February 2019 The progress against each track is as below:- Track 1 (13 Changes) – MT ongoing and on track to complete latest by w/c 08th October. Regression testing tracking slightly behind plan , no impact envisaged to milestones for all changes except XRN 4534 which is RED due to issues found (see below issue section), IDR planning and preparation underway. Track 2 (XRN 4454) – System Testing is now underway with some delays within plan due to complexity of testing – revised plan now in place along with a synergised Acceptance Testing. Issue XRN 4534 : a number of observations on XRN 4534 as part of Regression suite– these issues have dependency on Production teams to understand and work up options; Issues are being worked through with Xoserve Operations team to understand root cause and solutions – This places XRN 4534 in RED status and at high risk for Go Live on 2nd November. Clear resolution plan on XRN 4534 is being prioritised and outcome of this plan will be communicated to all by 10th October ChMC meeting. The Market Trials progress update available on Xoserve website, MT on track to complete as per planned timeframes, MT Closedown w/c 08th October. Follow-on Track 1 training sessions are planned in October before Go-Live. Implementation approach and file level transition plan published to participants. Implementation plan approval received at E- ChMC on 2nd October. Cadent MT registration to open shortly, parties are requested to register interest for Cadent MT starting 19th November. MT information Inc. high level scenarios to be presented next DSG onwards. Issue against XRN 4534 places its delivery at risk for 2nd November Go Live – resolution being prioritised within Xoserve Project and Production teams for a plan of delivery on/beyond Track 1 Go Live Date Go Live date dependent on close management of parallelism in plan (this is being managed) Complete All System and Acceptance Testing on time to ensure Cadent MT entry on time Full Delivery costs approved at ChMC in April 2018. Revision expected to accommodate XRN 4454 delivery date (ongoing discussions) Greater resource needed for XRN4454 (both technical & SME) for fulfilling the need for extended track 2. Daily tracking of plan in place to ensure progressing to revised timelines and additional resource support to deliver XRN 4454 SME resource requirements for Build, ST and AT phases is being managed weekly with internal Xoserve teams.

Build Complete ST synergised with AT UK Link Release 3 - Plan Primary Scope Scoping Initiation Delivery Realisation Stage Scope Prioritisation Scope Defined Funding Analysis and HLD Detailed Design Build & System Test Acceptance Test Performance Market Trials Regression Imp. PIS Track 1 Baseline Plan 10/01/18 07/02/18 11/04/18 13/04/18 04/06/18 13/08/18 07/09/18 1910/18 08/10/18* 22/10/18 02/11/18 04/01/18 Track 1 Current Plan 10/01/8 13/12/17 04/06/18* 19/10/18 Track 2 Baseline Plan 30/06/18* 24/09/18 05/11/18 N/A 14/12/18* 18/01/18 01/02/19 08/03/19 Track 2 Current Plan Build Complete ST synergised with AT 19/11/18** Planning/Milestone date to be confirmed Milestone date forecast to be met Milestone date forecast to be at risk Milestone date forecast to be missed Milestone completed RAG Key – Milestones are end dates; *Closedown expected to finish this week ** Synergised ST and AT date