UNC Modification 0531 Provision of Industry Testing System

Slides:



Advertisements
Similar presentations
Gemini Re-platforming Project Update April This presentation is to provide an overview of the Gemini Re-platforming Project (GRP) and provide early.
Advertisements

1 Project Smart Metering Portfolio Foundation & DCC Day 1 Updates April 2013.
Senior Stakeholder Forum 04/02/2014. Agenda UK-Link Programme Update –Including Data Cleansing Update Nexus Modification Update Faster Switching EU Reform.
1 Project Smart Metering Portfolio Foundation Updates June 2013.
Implementation of Non Effective Days Nexus Workgroup – March
ADD PRESENTATION TITLE HERE (GO TO: VIEW / MASTER / SLIDE MASTER TO AMEND) ADD PRESENTER’S NAME HERE / ADD DATE HERE © Copyright EDF Energy. All rights.
MOD506 – Gas Performance Assurance Framework and Governance Arrangements.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
February 2008 Gemini Incident Overview. Agenda Focus this part of the presentation is on the system elements of last year’s Gemini incident :-  Briefly.
UK Link Programme Dashboard Report Change Overview Board – 14/04/2015 RAG status for the full programme scope is RED Xoserve have confirmed the need to.
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
1 Mod Review Group 126 Mar 2007 slides 126 Review Group – Restriction of Invoice Billing Period  The review proposal is primarily concerned with restricting.
Cutover & Implementation Aggregated Programme RAG
Emergency Cashout Prices and Emergency Curtailment Quantity (ECQ) Adjustment Ritchard Hewitt Gas Code Development Manager.
Draft Modification Proposal: Population and Maintenance of Market Sector Code within Sites & Meters Simon Trivella –25 th February 2010 Distribution Workstream.
1 Smart Metering Foundation Stage February Agenda File Format Changes for Effective Switching Back Population Approach for Effective Switching.
Energy Balancing Credit Proposals Transmission Work Stream 7th October 2010 Loraine O'Shaughnessy.
Industry Dialogue on xoserve Services 14 th September 2007.
DSC Change Committee UK Link Future Releases Proposed Approach
Distribution Workgroup 24/11/16
Grid Code Development Forum – 6 September 2017
Code Governance Review UNC Modification Proposals
Introduction of Code Contingency Guidelines Document
UK Link Technology Refresh
Establishment of ‘Technical Sub Committee’ Action - SDG Option
UKL Future Release 2 Cutover/Implementation
An Industry-wide Approach TPG – 8th November 2016
Change Assurance Dashboard
Market Trials Working Group
Market Trials ChMC 8th August 2018.
CAP190: Workgroup Report CUSC Modifications Panel, 26th August 2011
Overall Project RAG Status
UNC Trader User – Licence obligations
UNC Modification – Non Effective Days
NTS Entry Charging Review Update
Cutover & Implementation Aggregated Programme RAG
Overall Project RAG Status
Release 3 Update November 2018.
UK Link Programme and ‘Nexus’ UNC Modifications
CSS Update for CoMC 19th September 2018
UKLP Programme Plan End Stage Assessments
Impacts of Project Nexus Implementation Date to AQ17
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
Proposer: Colette Baldwin – E.ON Panel Date: 21st August 2014
Change Proposals Capture to Delivery
Overall Project RAG Status:
XRN4534 Deployment Options December 2018
UNC0376S – Increased Choice when applying for NTS Exit Capacity
Introduction of Code Contingency Guidelines Document
Release 3 Scope & Proposed Plan
Proposed Transitional Gas Exit Arrangements
XRN4249 – Part B Data Migration Plan
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Deferral of Retrospective Updates Functionality
Overall Project RAG Status
UK Link Manual Update (UNC Modification 0613)
Modification Proposal 136
Project Nexus Workgroup
COR3007: UNC MOD 450B – Monthly revision of erroneous SSP AQs outside the User AQ Review Period Implementation UK Link Committee – May 2014.
Project Nexus Workgroup
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Customer Issue Management CoMC Update
Transmission Workstream 05 November 2009
CSS Consequential Programme Change Assurance March, 2019
DSC ChMC Switching Programme Update 10th July 2019
Gas Customer Forum 28 July 2008
DSC ChMC Switching Programme Update 10th July 2019
RAASP DSC Change Management Committee update
DSC ChMC Switching Programme Update 10th July 2019
Customer Issue Management Dashboard CoMC
Presentation transcript:

UNC Modification 0531 Provision of Industry Testing System 23rd February 2016

Background Modification 0531 has been proposed to provide a testing environment for Transporter to Shipper flows in three phases: Phase 1 – Conclusion of Market Trials (CoMT) phase to Project Nexus Implementation Date (PNID) Phase 2 – PNID to SAP Stabilisation Phase 3 – Enduring following SAP Stabilisation

Phase 1 – CoMT to PNID Xoserve are not able to provision a new environment for this Phase The testing modification was raised after environments were procured. This requirement had not been identified therefore no capability had been provisioned. Provision of a new environment is unachievable due to time and resource constraints. The data team are focussed on DMTC3 and then data Bulk Load when we commence the data transition activities to production Data load to a new environment will require 7-8 weeks to be “found” within the plan The environment that MT is conducted upon will be used for support of the Production System.

Phase 1 – CoMT to PNID Market Trials (core) was planned from 1st February 2016 to 31st May 2016. This period was recommended to PNSG following a consultation with the industry on their requirements for MT PNSG has been the vehicle to extend the MT window as challenges have been faced PNSG is monitoring progress through the MT stage. MT has gated stage criteria that have been agreed with PNSG including the exit criteria. Any extension to MT past 30th June or 31st July is the responsibility of PNSG

Phase 1 – CoMT to PNID - Conclusion The environment currently being used for MT will form part of the production stack at go live and therefore activities are required post MT to ensure the environments are ready PNSG, primarily through PwC and Xoserve, are considering the possible programme contingency scenarios and actions. This includes whether MT could be continued into August if required and any impacts this could have on downstream transition activities. Code freeze for iDR’s and transition needs to be considered. PNSG is the correct place for these decisions to be taken

Phase 2 and 3 – PNID - Enduring Xoserve recognise the requirement for an industry test environment from 1st October to test defects prior to them being deployed into the production environment Xoserve are assessing the viability of providing an environment for this purpose (not the current MT environment) We are balancing the requirement for this environment alongside the other environment needs, including those required for Release 2 and MT for RAASP Challenges with the distinct needs of the two phases. Criteria for the two stages seems relevant to assist UKLC, for example, support requirements. Data management principles need to be carefully constructed.