Public works contract Clauses 10.5 & 11.5 Explored

Slides:



Advertisements
Similar presentations
A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
Advertisements

© 2012 McNees Wallace & Nurick LLC CONTRACT ESSENTIALS Diane M. Tokarsky Chair, Construction Law 100 Pine Street, PO Box 1166 Harrisburg, PA
CONTRACT PAYMENTS & VARIATIONS
Contracts – important issues
Possible Loopholes in the Public Sector Contracts Anthony Hussey.
Security of Payment workshop Andrew Robertson Important Disclaimer: The material contained in this publication is comment of a general nature only and.
Subcontractors بسم الله الرحمن الرحيم Islamic university in Gaza Collage of Engineering Postgraduate program Construction Management Prepared by: Eng.
COMMENCEMENT OF ARBITRATION PROFESSOR JOSEPH MBADUGHA.
Dr. Lic. Herfried Wöss, LL.M. (Exeter), MCIArb. © The relationship between Arbitration and the Dispute Adjudication Board under the FIDIC Silver Book (EPCT)
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
INTERNATIONAL FEDERATION OF CONSULTING ENGINEERS. FIDIC MEASUREMENT AND EVALUATION CHAPTER 20 SECTIONS 20.5 TO 20.8.
Time for a new standard - AS General Conditions of Contract
The Islamic University of Gaza Engineering Faculty
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Contract price & payment
About ACE Purpose of ACE ACE exists to represent its members’ interests to clients, both government and private sector, and stakeholder organisations,
Statutory Violations Identification Procedure Avoidance CCIT Presentation – July 20, 2011 (rev 3/17/14)
1 IMPLIMENTATION OF CONTRACT CLAUSES Presentation by SRI. S. SREEKUMAR GM(ENGG), NER Dt
The Building and Construction Industry Security of Payment Act 2002 (Vic) made simple Western Suburbs Law Association Tuesday 4 June 2013 Michael Heaton.
2-105(1) "Goods" means all things (including specially manufactured goods) which are movable at the time of identification to the contract for sale other.
Compensation events and claims Presented by Prof. Khem Dallakoti.
CONSTRUCTION CONTRACTS – MASTER CHART
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
1 DISPUTE SETTLEMENT THROUGH ADJUDICATION N D Sharma.
1 中央大學營管所學分班 工程契約與文件管理 CHAPTER 16 TEST AFTER COMPLETION Silver Book, 2002 Clause 12. 授課教授 : 謝定亞 博士 學員 : 陳忠正 ( 研發中心管線組 )
Why Bond Forms Matter… A Practical Guide to Better Bonding Presenters: Joanne S. Brooks, Esq., Vice President and Counsel, The Surety and Fidelity Association.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
By Khalil T. Hasan Construction Solutions ( Joint Operation/Administration of multiple FIDIC Forms – A Case Study.
Kevin Kelly Government Construction Projects & Capital Spend Conference 2016 Wednesday 11th May 2016 Royal Marine Hotel, Dun Laoghaire, Co. Dublin.
ARBITRATION ACT. Challenge of arbitrator The appointment of an arbitrator may be challenged on the issues of – (i) impartiality, – (ii) independence,
ADR UNDER LABOUR CODE 2006.
Buying and Selling Real Property CHAPTER THIRTY-ONE.
Construction Contracts Act, Adjudication & Payment Claims Conference 2016 The Right to Suspend Work Explained Lydia B. Bunni BL Wednesday 28 th September.
Contract Compliance Training
Chapter 51 Insurance Law Chapter 51: Insurance Law
Administration of a FIDIC Contract - Project Control
Content of Tender Dossier - Instructions to Tenderers - Tenders
PRE-FILING DISPUTE RESOLUTION
EPA CONTRACT TEMPLATE Overview
Administration of a FIDIC Contract - Financial Management
EPA SUBCONTRACT TEMPLATE Overview September 2017
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
First Collective Agreements
Chapter 21 Performance of Sales and Lease Contracts
Tim Ahern Consultancy Ltd. tim. Tel;
English for Lawyers 3 Lecturer: Miljen Matijašević
What is Commercial law? Commercial law, also known as business law, is the body of law that applies to the rights, relations, and conduct of persons.
SIMAD UNIVERSITY Keyd abdirahman salaad.
Deferred Compensation in M&A Transactions ABA Business Law Section Spring Meeting 2015 Hermann J. Knott Partner, Luther, Köln, Germany Diane Holt Frankle.
Presented by Peter Barnes
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
بسم الله الرحمن الرحيم Tests on Completion Dr. Kamaleen Sha’ath
NEC 3 Engineering and Construction Contract (ECC) & Principles of Law
Find the Problems with the Provisions May 11, 2016 Presented By:
Dennis Li - HKCIC Lecturer
Insurance, Liability and Indemnity issues for Assigned Certifiers
Construction Contracts Act – Experience to Date
EMPLOYER’S RIGHTS – COMMON LAW AND CONTRACTUAL DETERMINATION PROCEDURE
Construction Contract Administration
About ACE Purpose of ACE Values
BUILDING DEFECTS: a legal perspective
RIGHTS, DUTIES AND LIABILITIES OF AUDITOR
What is a Dispute Board? A Dispute Board is composed of 1 or 3 neutral individuals who help the Parties avoid disputes or resolve disputes. If necessary,
5626 BESG Construction Contracts
DIRECTORS’ LIABILITIES FOR DECLARATION OF SOLVENCY
Presentation transcript:

Public works contract Clauses 10.5 & 11.5 Explored Hugh Cummins, Partner – Projects & Construction 7 February 2019

PWC Clauses 10.5 & 11.5 Explored Public Works Contracts: Clause 10.5 (Employer’s Representative’s Determination): Consequences of an Employer’s Representative’s determination Clause 11.5 (Final Statement): The Final Statement – the finality of the contractor’s last application for payment Public Works Contracts: PW-CF1, PW-CF2, PW-CF3, PW-CF4, PW-CF5      

Clause 10.5: Employer’s Representative’s Determination 10.5.1 If the Contractor has made a claim or proposal under sub-clauses 10.3 or 10.4, the Employer’s Representative shall, within 20 working days of receiving it, do one of the following: direct the Contractor to give additional information or revised proposals […] notify the Contractor and the Employer that the Contractor’s proposals are agreed […] make a determination of any adjustments to the Contract Sum, use of the programme contingency referred to in sub-clause 9.4 or extension to the Date for Substantial Completion of the Works and any affected Section, and notify the Contractor and the Employer in response to a proposal under sub-clause 10.4, notify the Contractor that the proposed instruction will not be given.      

Clause 10.5: Employer’s Representative’s Determination 10.5.2 The Employer’s Representative may [but is not bound to] determine an extension of time for a Compensation Event that is a breach of the Contract by the Employer on its own initiative even if the Contractor has not made a claim or proposal under sub-clauses 10.3 or 10.4. Note – invitation to use initiative – added responsibility on ER? 10.5.3 If the Employer’s Representative fails to take any of the actions in sub- clause 10.5.1 within the time stated, the Employer’s Representative will be taken to have made a determination under sub-clause 10.5.1(3) that there be no adjustment to the Contract Sum, no use of programme contingency referred to in sub-clause 9.4, and no extension to any Date for Substantial Completion. The determination will be taken to have been made on the last day of the time provided for in sub-clause 10.5.1.      

ER Determination – Final and Binding? 10.5.4 A determination of the Employer’s Representative notified to the Contractor and the Employer under sub-clause 10.5.1(3) or 10.5.2 shall be final and binding on the Parties unless, within 28 days after receiving notice of the determination (or, if sub- clause 10.5.3 applies, within 28 days after the determination is taken to have been made), the Contractor or the Employer gives notice to the other under sub-clause 13.1.1 or under sub-clause 13.2.1 disputing the determination and referring the dispute to either; the dispute management procedure under sub-clause 13.1; or conciliation under sub-clause 13.2

Disputing ER’s Determination Construction Contracts Act, 2013 S. 6 confers a statutory right to refer “payment disputes” to adjudication Clause 13.3 of PWC: Parties have recourse to adjudication under the CCA 2013 If adjudicated under the CCA 2013, cannot refer to dispute management or conciliation under PWC

ER’s Determination – Conclusive? Clause 4.3.4 “Any opinion, certificate, determination, assessment or objection of the Employer’s Representative under the Contract may be revised in accordance with clause 13, except for decisions stated in the Contract to be conclusive [such as rejection of a value engineering proposal under sub-clause 4.8 or rejection of a Defect under sub- clause 8.5.4].” The word “conclusive” appears in this context in clauses: 4.8.3 (Value Engineering) 8.5.4 (Defects) 8.6.2 (Defects Period) 10.6.4 (Adjustments to the Contract Sum) Does not appear in the context of Clause 10.5 (or 11.5)

Role of the Employer’s Representative – Beyond the Contract To whom does the Employer’s Representative owe a duty? Employer – as agent Employer and Contractor – certification, making decisions/determinations etc. Sutcliffe v Thackrah [[1974] AC 727] – House of Lords: “The building owner and the contractor make their contract on the understanding that in all such matters the architect will act in a fair and unbiased manner and it must therefore be implicit in the owner’s contract with the architect that he shall not only exercise due care and skill but also reach such decisions fairly, holding the balance between his client and the contractor.”

Role of the Employer’s Representative – Beyond the Contract Hudson’s Building and Engineering Contracts: “It should be borne in mind by Certifiers that their primary duty to their client requires them to protect that client’s interest. That duty is in no way inconsistent with a duty to act impartially when called upon by the contract to do so, but this does not mean (as some Architects and Engineers, whether acting as Certifiers or arbitrators, seem to think) that they are free to give way to their own ideas of what is fair in defiance of the strict letter of the contract. The contract confers no personal discretion whatever upon the Certifier, unless it expressly so states…”

Challenging ER’s Determination Referral to ADR through Clause 13 Breach of duty of care Support claim under ADR Separate cause of action?

Clause 11.5 – Final Statement Finality of contractor’s last application – when does the contractor make its last application? 11.5.1 Within 2 months after Substantial Completion of the Works is certified, the Contractor shall give to the Employer’s Representative a final statement. The Contractor shall include in that statement all money that the Contractor considers to be due from the Employer to the Contractor under or in connection with the Contract. The Employer shall have no liability to the Contractor under or in connection with the Contract for any matter not detailed in the final statement, except under the indemnities in the Contract or Compensation Events occurring after Substantial Completion of the Works was certified. If no final statement is given within the time required, the Employer shall be released from all liability to the Contractor under or in connection with the Contract. 11.5.2 Within 3 months after receipt of the Contractor’s final statement, the Employer’s Representative shall issue to the Contractor and to the Employer a penultimate payment certificate certifying the amount that, in the Employer’s Representative’s opinion, will be due from the Employer to the Contractor, less any final retention to be paid after the Defects Certificate is issued, or from the Contractor to the Employer.

Clause 11.5.1 – breakdown Contractor’s Final Statement: When? Contractor to deliver 2 months after Substantial Completion Contents? All money the Contractor considers due from the Employer under or in connection with the contract Incentive on Contractor to put onus on Employer’s Representative?

Clause 11.5.1 – breakdown Employer’s Liability/Finality: Employer not liable for matters not included in final statement, save for: Indemnities (Clause 3.5, Clause 6.2.2) Compensation Events occurring after Substantial Completion No final statement, Employer released from all liability

Clause 11.5.2 – Penultimate Payment Certificate Employer’s Representative: Issue penultimate certificate within 3 months of final statement Amount that in ER’s opinion is due from Employer to Contractor (vice-versa) Reminder! – Clause 4.3.4 “Any opinion, certificate, determination, assessment or objection of the Employer’s Representative under the Contract may be revised in accordance with clause 13, except for decisions stated in the Contract to be conclusive [such as rejection of a value engineering proposal under sub-clause 4.8 or rejection of a Defect under sub- clause 8.5.4].”

Clause 11.5.3 – Final Payment Certificate Employer’s Representative: Issue final payment certificate 3 months after Defects Certificate Amount that in ER’s opinion is due from Employer to Contractor (vice-versa) Reminder! – Clause 4.3.4

Finality of contractor’s final application/final statement Clause 11.5.1: “Kitchen sink” in the “last chance saloon”? Put onus on Employer’s Representative Duty of care to both employer and contractor Ability to challenge ER’s opinion under Clause 13

Thank you for listening philiplee.ie info@philiplee.ie DUBLIN 7/8 Wilton Terrace Dublin 2 Ireland T: +353 (0)1 237 3700 F: +353 (0)1 678 7794 BRUSSELS 39 Rue des Deux Eglises 1000 Brussels, Belgium T: +353 (0)1 237 3700 F: +353 (0)1 678 7794 SAN FRANCISCO 201 Spear Street, Suite 1100 CA 94105, United States T: +353 (0)1 237 3700 F: +353 (0)1 678 7794