SA&S-Fortnightly Status Report – Overview Period Ending 18 April 2018

Slides:



Advertisements
Similar presentations
University of Glasgow Major Capital Projects Project Governance Gateway Process.
Advertisements

Program Management Office (PMO) Design
Roadmap for Sourcing Decision Review Board (DRB)
X Project Highlight Report – (Date) Achievements  Key high level outputs delivered by the project this month. Communications Key high level communications.
Information Sharing for Integrated Care A 5 Step Blueprint.
LCR Sexual Health Strategy Project Board 6 October 2016
Program Management Office (PMO) Design
Paper Switch-off Programme Initial engagement
Solihull Review of Urgent Care Programme Approach And Governance 2013
COMM02 Project Monitoring and Control Unit 8
Program Management Office (PMO) Design
SA&S-Fortnightly Status Report – Overview Period Ending 3rd May 2017
Information Sharing for Integrated care A 5 Step Blueprint
TPS Kick-Off Presentation
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
A Guide for Managers for Professional Staff
Paper Switch-off Programme Initial engagement
Program Management Office (PMO)
SIP Report – Nov 2017 Overview Headlines Workstream report
Project Steering Committee Meeting 27 May 2015 :14h00 – 16h00
SA&S-Fortnightly Status Report – Overview Period Ending 20 Sep 2017
SA&S-Fortnightly Status Report – Overview Period Ending 25 Oct 2017
Project Roles and Responsibilities
Project Initiatives Identified by the CIA Project
MOSH Leading Practices Adoption System
Guidance notes for Project Manager
End of Year Performance Review Meetings and objective setting for 2018/19 This briefing pack is designed to be used by line managers to brief their teams.
Change Assurance Dashboard
Our new quality framework and methodology:
Amendment Invoice Task Force Progress Report
IS&T Project Reviews September 9, 2004.
Program Management Office (PMO)
Program Management Office (PMO)
GENERAL SERVICES DEPARTMENT Facilities Management Division PROOF –NM (Process Reengineering & Optimization of O&M Functions for New Mexico) Phase II.
Student Administration and Support Programme and Project Timelines
Stakeholder Management Template
Launch readiness template
Amendment Invoice Task Force Progress Report
Student Administration and Support Programme and Project Timelines
Insert name of who presenting to
Amendment Invoice Task Force Progress Report
West Essex Business Planning Process
Student Administration and Support Programme and Project Timelines
Core Competencies of a World Class Customer Advisory Board
New employee induction for new staff and managers
Key Value Indicators (KVIs)
Portfolio, Programme and Project
Amendment Invoice Task Force Progress Report
SA&S-Fortnightly Status Report – Overview Period Ending 1st June 2017
Student Administration and Support Programme and Project Timelines
APT – Planning the Next Phase & Resourcing Risk 2 Nov
Amendment Invoice Task Force Progress Report
SA&S-Fortnightly Status Report – Overview Period Ending 05 Oct 2017
Launch readiness template
Overview Headlines RSP – Progress Overview General progress report
Student Administration and Support Programme and Project Timelines
SA&S-Fortnightly Status Report – Overview Period Ending 31 May 2018
ISSUE MANAGEMENT PROCESS MONTH DAY, YEAR
SA&S-Fortnightly Status Report – Overview Period Ending 21 Feb 2018
RSP – Progress Overview General progress report High level plan
Special school competitions
SA&S-Fortnightly Status Report – Overview Period Ending 11 Jan 2018
SA&S-Fortnightly Status Report – Overview Period Ending 25 Jan 2018
{Project Name} Organizational Chart, Roles and Responsibilities
DSG Governance Group Recommendations.
SA&S-Fortnightly Status Report – Overview Period Ending 2 May 2018
WORKSHOP Establish a Communication and Training Plan
World-Changing Glasgow Transformation Programme Board Summary
IT Next – Transformation Program
Project Name Here Kick-off Date
Presentation transcript:

SA&S-Fortnightly Status Report – Overview Period Ending 18 April 2018 Deliverables this period MyEd Portal: Contact Details roll out initiated. Resources booked. Immigration : HR activities with impacted staff started WSA: Communication sent to DoPS/College Registrars. Procurement project. SCEC: seeking TOM Blueprint approval with SEP Board. System build: completed iteration1 incl all backlog of bug testing. Timetabling Service: Business case and Blueprint approved by SA&S Board Exam Timetabling: Decision to Go live with Aug resit diet. PCIM: PID and planning in progress Tier 4 :  Biometric functionality post live issues deployed for user sign off. Current Status Previous Status R A Exam Timetabling ET Policy Tier 4 compliance Management and Control Engagement Delivery Planning Resource RAID Costs & Benefits Stakeholders Communications R A G -HR activities across the SA&S projects (risk raised) -WSA No project sponsor: decision point required mid May for ITT sign off. -SCEC system implementation is impacted by Blueprint non-approval, re-planning system work Phase 3 Service detailed design at risk, because of SA&S resources required to complete. Only PCIM planning work has started, but PM/BA only start end May -Change Management resources being recruited to support WSA & Timetabling -SAS Core team- implementation resources recruitment in progress -Timetabling BA not confirmed yet -New PM for PCIM, WSA & SCEC not in place yet. Risks and Issues are now reported on the project website. Benefit realisation plan and costs for phase 2 addressed in Business Cases. Benefit log to be updated. Immigration communication sent and face to face meetings held. WSA communication sent to DoPS/Registrars. Timetabling comm being drafted Further engagements with users for SCEC (yammer) and planned workshop for timetabling & SCEC. Being done through projects/workshops, programme lead 1:1 and SEP newsletter. Use of the SEP toolkit communication. -Issue: WSA communication was not cascaded consistently -Timetabling communication drafted, on hold until HR approach is clear

SAS– Fortnightly Status Report – Programme Risks -Period Ending 18 Apr 2018 Consequences Inherent Impact Residual Impact Residual Prob’ty/ Uncert’y Risk Level Risk Mvt since last mth Current & Management Processes and Mitigating Activities and Future Developments Senior Managerial Responsibility For escalation There is a risk the HR activities required for  Timetabling, SCEC and WSA projects are delayed (starting at week -5 prior to HR announcement). There is a risk that the approach may affect the expected benefit realisation. Delay to the HR announcement- The HR activities are not coordinated across SCEC, WSA & Timetabling services. This will impact the communication and the start of user engagements, who could both be at risk. Impact to Go live date. 5 4 16 p HR advisor for SEP Programme has now been appointed and is investigating potential HR approaches/ solutions. This needs approval with SEP programme lead Heather Tracey There is a risk the communication required to be sent for Timetabling, WSA, SCEC is being delayed because the HR activities are not clear (impact from above risk) and SCEC Blueprint is not approved User engagements are delayed, or users who are impacted will make noise/do not engage. Impact to the SAS programme reputation . 3 12 u Depends on HR activity being confirmed above Also depending on SCEC approval, agree common approach for all 3 projects with SEP Programme Lead. Neil McGillivray

SAS– Fortnightly Status Report – Programme Risks -Period Ending 18 Apr 2018 Consequences Inherent Impact Residual Impact Residual Prob’ty/ Uncert’y Risk Level Risk Mvt since last mth Current & Management Processes and Mitigating Activities and Future Developments Senior Managerial Responsibility For information SCEC- There is a risk that proposed changes to the Target Operating Model (TOM) decision processes for special circumstances and extensions would require system changes  May lead to an increase in the cost of the development effort and impact the timescales for delivery. Options: Stop next iteration until there is clarity from the business Plan other work 4 5 20 u Replanning system design with users around new proposed decision point-On Hold Update: Next iteration(#2) has stated and is planned with work not impacted by the non approval of the blueprint- Workshops re decision process and framework have been delayed once TOM is approved. Franck Bergeret There is a risk that future projects may not have access to student systems BA or Implementation expertise. The risk is higher as the business cases for WSA is articulating the significant effort required from both BA & Implementation to complete the standard operating procedures. This will impact on the start of the WSA implementation Analysis of data and process is not completed for PGR and Programme and Course Information and publishing 3 12 q SAS resource demand has been fed into the overall Student Systems resource planning for approval by Programme Sponsor. Recruitment is planned for. In the meantime short term staff for SCEC project have been recruited and in place. Engaging with SRA and IS (end of life of degree finder) for the Programme/Course PCIM work. Lisa Dawson SCEC- Risks have been raised in the business case re 1) implementation mid year, 2) academic buy in , 3) CSPC does not support TOM proposal 1- inconsistent treatment of student cases, additional work for staff and reputational damage for SEP 2-resistance during implementation 3--impact to timeline Review risks ‘mitigations articulated in the business case post Board decision Update- waiting for SEP Board outcome

SA&S Fortnightly Status Report - Programme Issues-Period Ending 18 Apr 2018 Green - Low Not currently impacting the project A Amber - Medium Resolution in hand and is being managed within the Programme R Red – High Immediate escalation is required Issue Description. There is an issue that… Severity Score (RAG) Issue resolution Senior Managerial Responsibility For escalation issue 1, for information issues 2 WSA Project has no named Project Sponsor. Impact: no-one identified early enough to sign-off initial key deliverables of procurement work (ITT delayed): 1. Planning-status completed 2. Evaluation group –status confirmed (needs organisational buy-in) and 3. Requirements ITT requires validation by sponsor- Decision point mid May. High Outstanding: being raised at next SAS Board. Decision point is mid May so that the sponsor signs off the ITT. In the absence of project sponsor, the programme sponsor will be asked to sign off the ITT. Barry Neilson Student Finance- There are overlaps of work between SA&S and Finance programme. The student finance process workshops held in November 2017 identified a number of points in which the SA&S finance-related functions interact with the Finance Office.  Ideally, we need to dovetail into the Finance Transformation and Core Systems work, with SA&S influencing finance-related processes bringing the voice of the student and how they interact with the University’s financial processes.  Therefore it is the SAS programme lead's view that attempting to design new processes for an SA&S blueprint in isolation to and apart from the financial processes would be counter-productive.   Medium submit a list of requirements to the Finance Transformation and Core Systems team to request developments around the identified common themes. Ensure output takes the student focus into account Meeting scheduled to manage the overlaps and the ownership Workshops planned end April for Finance to be attended by SAS team member Neil McGillivray

RAG Guidance Criteria Red Amber Green Delivery Key deliverables at risk Some risks around delivery On track for delivery Planning No detailed plan Detailed plan in place. Gaps around benefit/key deliverables. Not fully up to date. Covers less than 6 weeks. Detailed, current plan in place covering the next 6 weeks. Resource Significant skills or resource gaps Some gaps All resource in place and trained. RAID No documented risks and issues. Defined process and roles. Clearly defined escalation routes. Risks and issues log actively maintained and reviewed by project team. Costs & benefits Very limited benefit identification/ limited understanding of costs Some gaps in information. Costs fully broken down and information accessible. Benefits documented and logged in register. Stakeholder engagement Very limited identification. No documented plan. Some ad hoc identification of stakeholders. Incomplete plan. Not approved by sponsor. Stakeholder, interest and needs systematically identified. Plan for engaging in place and approved by sponsor. Communications Little current information on website; stakeholders not informed of status Some ad hoc communication. Some information on website Website updated for last completed stage. Stakeholders informed and aware of nest stage plans. Key messages available for last stage. A programme will be assumed to be green initially. It may be red/amber status if 2/8 elements are red or amber. A project is likely to be red/amber if 3 or more elements are that colour. A project is red/amber if 4 or more elements are that colour.