BLOEMFONTEIN SANDF: TEMPE MILITARY BASE: 3 MILITARY HOSPITAL: INFRASTRUCTURE REFURBISHMENT AND MAINTENANCE CHALLENGES Date: SEPTEMBER 2018 BRANCH HEAD:

Slides:



Advertisements
Similar presentations
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
Advertisements

Expenditure Outcome for 2011/12 and Spend as at 31 July for 2012/13 Select Committee of Finance 29 August 2012.
Implementation of the Government Immovable Asset Management Act, 2007 (GIAMA) National Department of Public Works Presentation to the Select Committee.
PRESENTATION TO THE PORTFOLIO COMMITTEE OF PUBLIC SERVICE AND ADMINISTRATION AS WELL AS PERFORMANCE MONITORING AND EVALUATION NDPW MPAT PERFORMANCE From.
PORTFOLIO COMMITTEE PRESENTATION: PROGRESS REPORT ON KEY CONTROLS (MOVING TOWARDS UNQUALIFIED REPORT) TO MONITOR AND EVALUATE RELIABILITY OF FINANCIAL.
IN YEAR MONITORING & BUDGET PREPARATION WORKSHOP PREPARED BY BUDGET OFFICE MAY
ANALYSIS OF THE NCERA FARMS INVESTIGATION REPORT AND RECOMMENDATIONS TO THE PORTFOLIO COMMITTEE 1.PURPOSE T O INFORM THE PORTFOLIO COMMITTEE ON THE STEPS.
Presented by Themba P Wakashe Director-General REPORT ON THE UNSPENT BUDGET 2009/10 TO STANDING COMMITTEE ON APPROPRIATIONS.
Physical Building Audit Physical Building Audit By; Engr.Dr.Attaullah Shah PhD ( Civil) Engg, MSc Engg ( Strs), BSc Engg ( Gold Medalist),), MBA, MA (
REPORTING, MONITORING AND PERFORMANCE EVALUATION PROVISIONS ON NON-FINANCIALS – 2013/14 1 MIG Quarterly Workshop 3 – 4 September 2013.
1 DPW Presentation to the Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 24 November 2010.
Limpopo - Health1 Report to the Select Committee on Finance on the Provincial Budgets and Expenditure Review 2001/ /08 and Conditional Grants and.
Briefing to the Portfolio Committee on Police, National Assembly LEASE OF ICD HEAD OFFICE BUILDING, PRETORIA S35, First Floor, NCOP Wing, Parliament Tuesday,
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
Portfolio Committee on Appropriations Quarter 1 Expenditure and Performance 24 August 2012 The Presidency Department of Performance Monitoring and Evaluation.
Presentation to Portfolio Committee on Defence and Military Veterans November 2014 Presented by the Secretary for Defence DEPARTMENT OF DEFENCE 1.
1 Department of Public Works Government Immovable Asset Management Bill [B1-2006] Portfolio Committee on Public Works 08 November
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
I Public Works I Parliament I Cape Town 1 Presentation to the Standing Committee on Appropriation 10 November 2015.
Province of the EASTERN CAPE DEPARTMENT OF PUBLIC WORKS DOH REVITALISATION PROGRAM EASTERN CAPE PROVINCE PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON RURAL DEVELOPMENT & LAND REFORM DATE: 13 APRIL THIRD QUARTER EXPENDITURE REPORT FOR THE FINANCIAL.
1 DEPARTMENT OF PUBLIC WORKS P ROGRESS REPORT ON THE LEBOMBO PORT OF ENTRY 22 FEBRUARY 2011.
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
INFRASTRUCTURE EXPANSION IN RELATION TO THE DEPARTMENT OF HOME AFFAIRS (DHA) Presentation to Portfolio Committees of Home Affairs and Public Works 19 September.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES SERVICE LEVEL AGREEMENT 02 June 2010.
PROVINCIAL INFRASTRUCTURE GRANT NCOP 06 March 2006.
FREE STATE DEPARTMENT OF HEALTH Presentation on the Status of Conditional Grants Public Hearings on Conditional Grants 03 May 2006.
Parliamentary submission on the eradication of the Bucket Toilet System 22 & 23 February 2007 Cllr. Derrick Ndlovu.
1 Hospital Revitalization Grant Performance Report: Free State.
National Department of Public Works Republic of South Africa National Department of Public Works Republic of South Africa 25 MAY 2004 JAMES MASEKO DIRECTOR-GENERAL.
Presentation to the Portfolio Committee on Energy
OVERVIEW OF DEPARTMENT OF ARTS AND CULTURE SERVICES INFRASTRUCTURE PORTFOLIO DATE: 06 SEPTEMBER 2016.
ELECTRICITY DISTRIBUTION INDUSTRY DECISION
Infrastructure Delivery Management Toolkit: 2010 Edition
BRIEF ON WORKING RELATIONS WRT DAC LEGACY PROJECTS
REPORT ON MATTERS IDENTIFIED BY THE COMMITTEE
JUSTICE AND CORRECTIONAL SERVICES PORTFOLIO COMMITTEE PRESENTATION: LEASES Portfolio Committee on Justice and Correctional Services 04/08/2015.
PORTFOLIO COMMITTE PRESENTATION
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
Report back on the review of budgetary allocation for Land Reform
South Africa Works because of Public Works
2018/19 ANNUAL PERFORMANCE PLAN FOR MISA
SELECT COMMITTEE ON APPROPRIATIONS 11 August 2010
Presentation to the Portfolio Committee OFFICE OF THE DIRECTOR-GENERAL
Economic Development Department Annual Financial Statements 2011/12
PRESENTATION ON THE FINANCIAL MANAGEMENT INFORMATION 3rd QUARTER IRO 2007/ FEBRUARY 2008.
South Africa Works because of Public Works
LIMPOPO DEPARTMENT OF PUBLIC WORKS PRESENTS
COMMITTEE ROOM M46, MARKS BUILDING CAPE TOWN
DEFENCE WORKS FORMATION
DEPARTMENT OF EDUCATION NORTH WEST MID-TERM PROVINCIAL BUDGET REPORT
Budget Vote Workshop - Safety and Security
Progress on the Bucket Eradication Programme
Progress report on the roll out of GIAMA
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS (SCOA) ON DEVOLUTION OF PROPERTY RATE FUNDS GRANT 12 OCTOBER 2010 Mr Joey Pillay.
PRESENTATION TO PORTFOLIO COMMITTEE ON DEFENCE AND MILITARY VETERANS ON THE STATUS OF THE DMV INFRASTRUCTURE 08 November 2017 Presented by Mr. M. OZINSKY.
Presented to the OPERATIONS BRANCH STRATEGIC INITIATIVES
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
National Department of Public Works Immovable Asset Management
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
HOSPITAL REVITALISATION PROJECTS REPORT TO THE SELECT COMMITTEE ON APPROPRIATIONS AUGUST 2012 Northern Cape Department of Health & Department of Roads.
PROGRESS REPORT: Infrastructure Development Function Transfer
DEPARTMENT OF HEALTH AND SOCIAL SERVICES
Presented by Magdeline Tshabalala
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Presentation to the Portfolio Committee 20 November 2018
IYM PRESENTATION UP TO 31 DECEMBER 2011 PRESENTATION 24 April 2012
Presentation transcript:

BLOEMFONTEIN SANDF: TEMPE MILITARY BASE: 3 MILITARY HOSPITAL: INFRASTRUCTURE REFURBISHMENT AND MAINTENANCE CHALLENGES Date: SEPTEMBER 2018 BRANCH HEAD: Mr BATHO MOKHOTHU

TABLE OF CONTENTS OVERVIEW SERVICE LEVEL AGREEMENT KEY CHALLENGES AND REMEDIAL ACTION CAPITAL WORKS, MAINTENANCE AND LEASING ASSET MANAGEMENT PLANS BUDGET AND SPENDING PERFORMANCE ROLLOUT OF INFRASTRUCTURE PROGRAMME OTHER MATTERS CONCLUSION AND RECOMMENDATION 2

SECTION 1 OVERVIEW

1.1 Purpose To brief SCOA on the Infrastructure Refurbishment and Challenges at Tempe Military Base – Military 3 Hospital 4

1.2 BACKGROUND The Standing Committee on Appropriation (SCOA) undertook an oversight visit to the Free State from 13 to 17 August 2018 SCOA conducted a site visit to the Bloemfontein 3 Military Hospital to assess the state of the infrastructure SCOA requested a list of priorities which need to be addressed SCOA formally invited DPW to prepare a presentation, focused on salient points including SLA, progress, asset management plan etc. 5

SECTION 2 SERVICE LEVEL AGREEMENT

2. SERVICE LEVEL AGREEMENT The Service Level Agreement is aimed at clarifying the relationship between the Department of Defence and DPW with regards to the provision and management of immovable assets. The SLA between the Departments were signed in September 2016 by both parties. According to the SLA (Item 10.1.8) DPW will be responsible to appoint service providers to operate the specialised facilities, installed equipment and systems and other such equipment associated with immovable infrastructure. 7

SECTION 3 CHALLENGES

3.1 KEY CHALLENGES AND REMEDIAL ACTION SOLUTIONS Turnaround time on Projects Task Teams establish to ensure governance, reporting and monitoring Project support (professionals, project management) based on needs assessment from Region Currently busy with the business processes re-engineering to eliminate long lead and delays in planning process Maintenance Backlog 3 Military Hospital (Hot water storage, security system etc) Bloemfontein Army support Base (Living Quarters, Married Quarters, Fencing, security system etc) Bloemfontein Air force (Boundary wall, security, fire detection etc) Hanger Aircraft Facilities (Refurb of Aircraft wash bays) Condition Assessment of facilities Quantification of the scope and cost Prioritisation of services Registration of a project(s) 9

3.2 HISTORICAL CHALLENGES ON ACCOMODATION CHARGES Accommodation Charges is a devolved budget from National Treasury. Annually the DPW is being given up to R1bn. DPW must use this budget to fund the Day-to-Day Maintenance, Planned Maintenance and Rates and Taxes for the DOD. DPW has annually underperformed on the Planned Maintenance Programme notwithstanding the budget was prepaid quarterly. The strategy from the Defence Works Formation (DW Fmn) is to ensure the following related to Accommodation Charges: DPW to make visible what Planned Maintenance Programme they are going to undertake for the MTEF in order to allow DW Fmn to monitor progress. RESTRICTED

3.3 FINANCIAL SUSTAINABILITY FUNDING CONSTRAINTS (MAINTENANCE FEEDBACK) IMPLICATIONS OF FUNDING GAP ON CONDITION OF PROPERTY PORTFOLIO AND PMTE BASELINE Upkeep of entire portfolio is not adequately funded in User Departments’ baselines which resulted in significant repair and refurbishment backlog which led to deterioration of the condition of portfolio The financial impact of addressing the condition of our portfolio to an acceptable level to operate a sustainable business will be significant to the PMTE EXAMPLE Based on 13 pilot properties in Pretoria, estimated accommodation charges required to implement a desired / sustainable FM strategy far exceeds funding currently available 17/18 ENE accommodation charges allocation for total portfolio is only R4.5 billion If the desired FM strategy for the piloted 13 properties is implemented, a capital injection of R650m would be required immediately – this excludes operating costs (rates / maintenance etc.) Per extrapolated ARV analysis an estimated that significant amount of money is required to uplift the condition of the entire portfolio through implementation of a Maintenance solution.

GROWING ACCOMMODATION CHARGES FUNDING GAP 3.4 FINANCIAL SUSTAINABILITY FUNDING CONSTRAINTS GROWING ACCOMMODATION CHARGES FUNDING GAP Investment required for capital backlog Operational requirement deficit Current user charges based on properties occupied before 2006 and does not take into account any new facilities built or upgraded in the last 10 years (these are funded from the PMTE baseline) Ideal

SECTION 4 CAPITAL WORKS, MAINTENANCE AND LEASING

4.1 CAPITAL WORKS, MAINTENANCE AND LEASING There are two projects registered for 3 Military Hospital facility namely the repair to storm damaged roof and facility management contract The contract for Bloemspruit complex comprises repairs and renovation of the sewer works There are no Leasing matters for 3 Military Hospital

4.2 (DETAILS) CAPITAL WORKS AND MAINTENANCE NO. REGION DESCRIPTION HISTORICAL CHALLENGES PROGRESS 1 BLOEMFONTEIN 3 Military Hospital: Repair to Storm Damaged Roof. WCS 054805 A project was registered in March 2016 after the Client reported that a storm damaged almost all the roofs in the hospital complex. This is registered against a Suspense Account / Damages and Losses.   Consultants were appointed and briefed. Consultant team busy with the design process, and quotations were invited to appoint a Consultant for OHS. Other details: Structural engineer, quantity surveyor have been appointed already. Appointment for the OHS is sent for adjudication at RBAC. Mid October 2018 sketch plans approval is planned Contractor award is planned 2 3 Miliary Hospital: Facilities Management Contract. WCS 050804 DPW identified the need for this contract when the project was in the final phase before completion of the construction of the new hospital.. The project was registered in May 2012 under the Planned Maintenance Implementation Programme. The final phase 4 of construction of the hospital was completed in October 2014.  The Facilities Management Contract is still in status 3 (Pre-design stage). The Procurement Instruction to be issued. The project will alleviate the challenges experienced in maintenance by having an appointed Contractor available at all times, in case of emergencies.

4.3 (DETAILS) CAPITAL WORKS AND MAINTENANCE NO. REGION DESCRIPTION HISTORICAL CHALLENGES PROGRESS 3 BLOEMFONTEIN Bloemspruit Complex: Repair and Renovation of Sewer WCS 047318 A project was registered and project in implementation   Site Handed over at 10 August 2016. Value of Contract =R 20 093 921.27 (Incl. 15% VAT from 01 April 2018). Practical Completion was taken on 10 July 2018, works completion planned to be taken 19 September 2018. Other details: Contractor busy with snagging before final completion 4 Air Force Base Bloemspruit: Refurbishment programme. WCS 049921 BLOEMSPRUIT AIR FORCE BASE, REPAIR & RENOVATION TO BUILDINGS 70, 81, 82, 83, 95, 104, 105, 107 AND 318: GROUP 5 The 1st Contractor was stopped due to poor workmanship. 2 x contractors were terminated due to non-performance. Tenders for the third replacement contractor closed on 12 June 2018. Bid Evaluation Committee members have appointed and evaluation process planned to take four weeks. Planned site hand over date: 20 Sept. 2018 Contract period: 12 months

SECTION 5 ASSET MANAGEMENT PLANS

5. ASSET MANAGEMENT PLANS Constant engagements with client to ensure UAMPS are completed CAMP submitted annually to National Treasury as per GIAMA DOD has submitted their User Asset Management Plan this year on 01 August 2018. DPW to meet user departments' accommodation requirements as per the approved Infrastructure Programme Implementation Plan (IPIP) (Annually) and Infrastructure Programme Management Plans (IPMP)

SECTION 6 BUDGET AND SPENDING FOR MAINTENANCE ACTIVITIES

6. BUDGET AND SPENDING PERFORMANCE No major maintenance is being done at 3 Military Hospital. All maintenance is done re-actively at this point in time. Term contract to replace the re-active maintenance

SECTION 7 ROLL OUT OF INFRUSTRUCTURE PROGRAMMES

7. ROLL OUT OF INFRASTRUCTURE PROGRAMME The availability of funding and clear direction on the implementation of the Facilities Management Contract This has created a challenge in the Region by not providing a maintenance plan for this facility to the Client. Lengthy response time when calls are logged. Current process are manual and unintegrated. Introduction of an enterprise resource planning (ERP) system (Archibus) will ensure the digitisation of the complete workflow from logging of calls to processing payments. Length of Contracts – Intermediate We are in process of implementing 24 month scheduled maintenance contracts for all critical components this financial year. Current Boiler operating contracts are also being revised for longer periods. Repairs and Refurbishments – Long term It is noted that capital is required to refurbish the facility critical component. The constraint on the capital reserve resulting from the devolution has created a significant maintenance backlog. Within the task team priorities have been identified and funding secured for immediate action.

8. OTHER ISSUES The implementation of the Facilities Management Contract will definitely assist with the NDPW’s mandate in providing a service to its Client. At the moment NDPW is not meeting that mandate. There is no maintenance plan in place currently, which is imperative at any Health Facility

9. CONCLUSION AND RECOMMENDATIONS It is recommended that SCOA notes the report 24

END National Department of Public Works (NDPW) Head Office: Public Works CGO Building Cnr Bosman and Madiba Pretoria Central Private Bag X65 Pretoria 0001 Website: http://www.publicworks.gov.za