Operations, Risks & Hazards

Slides:



Advertisements
Similar presentations
1 Second Safety Council Meeting Tucson April 2014 Name of Meeting Location Date - Change in Slide Master Dome Hazard Analysis Discussion Jacques.
Advertisements

Instrument Space Requirements Rob Connatser Chief Instrument Project Engineer November 2014.
Interfaces with the SNS Project for the ARCS Instrument Doug Abernathy ARCS Hardware Project Manager ARCS Construction Project Review DOE Germantown Aug.
1 Overview of the NPDGamma Experiment at the Fundamental Neutron Physics Beamline Geoff Greene UT/ORNL.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
A guide to… Maintenance Safety. Aim There is a legal requirement for regular and effective maintenance, inspection and testing of work equipment. This.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
K.Gadow CALICE technical review 1 Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4.
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
WEEKLY SAFETY MEETING September 22 nd, OGEC RIG RR 600 JOBI-4.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
ESS Vacuum Standardization
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
1 Interfaces, Engineering and Standards. 2 Interfaces LoKI Interface document description for deliverables Elements: PBS number, Deliverable description,
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
Slides for TAC meeting Oct/2015 Marcelo juni Ferreira Vacuum section leader October,
PERSONAL SAFETY INTERLOCKS External EHS Expert Panel Workshop
Who is Responsible for Overhead Crane and Hoist Operations
HEL – Safety aspects Christelle Gaignant
Designing Safety into a High-power Neutron Spallation Source
Pre-Contract Cost Control
Andreas Jansson, Lali Tchelidze
Welcome & Charge for the Meeting
ESS Freia Scope Setting ESS - Lund - 17/10/2016.
PSS1 overview Stuart Birch
The Bunker Project Overview Zvonko Lazic
Remote Handling Workshop Introduction
Operations Section Leader
The Common Shielding Project
Bunker Internal Review Welcome & Charge
Instruments Shielding Project Installation
Senad Kudumovic Design engineer
Imaging & Engineering STAP Meeting 12th-13th of April 2018
The Mechanical Engineering & Technology (MET)
IKON 15 Talal Osman & Iain Sutton
STUB configuration Mats Pålsson
BEER – General Update Nuclear Physics Institute CAS Přemysl Beran
Safety Analysis and Safety Functions
Preliminary Hazard Analysis of Bunker
Neutron guide Shielding Concept
Radiation Protection Handbook
Bunker -Target interfaces
Bunker Project Schedule/Budget
Bunker Wall Design Wall ESS
Safety Readiness Review (SRR) Thomas Hansson, ESH
Welcome Update on ESS Construction Project
Rack Placement Chopper Workshop
TG3 Process /Part 2 Gábor László NSS Lead Instrument Engineer
Technical Updates Gábor László NSS Lead Instrument Engineer
NSS integrated installation plan workshop Introduction
Bunker Project Operation aspects
Bunker Project Schedule/Budget
Spectroscopy STAP Meeting ESS, 8th of April 2019
The Bunker Project Overview Zvonko Lazic
TS2 PSS; update on concepts of operation and system's architecture
Bunker Project Integration/Interfaces
Test Beamline System Requirements and Charge to PDR Committee
BEER cave design and shielding
Introduction, Overview, Charge, Project Plan, Requirements
Shielding requirements for the baseline bunker shielding (current CATIA version ) Günter Muhrer
Charge and Agenda of the 18th TAC meeting
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
MRV system budget and scheduling Short overview installation
Overview of the TARGET Monolith Rough Vacuum
IS&LEBT Commissioning Review Safety and Radiation Protection
Presentation transcript:

Operations, Risks & Hazards Preliminary Design Review of the Common Shielding Project Lund, 24th of January 2019 Ken Andersen, Neutron Instruments Division, European Spallation Source ERIC

Operational aspects Guide interface Utilities routing Pre-align sections on 4m girders Alignment access only needed at ends Utilities routing Feed out of shielding as close to source as possible Pumps, control racks, etc. are all outside shielding Realignment access with single lift Provides visual and mechanical access from sides Maintenance access requires more lifts Personnel Safety Systems Allow access when proton beam is off Access with proton beam on & with shutter closed needs update to requirement #12 Interlocked doors may be possible, but needs discussion and will cost Cranes needed for access inside shielding Fixed cranes in D01/D03 Gantry cranes in E02: requires dismantling and reassembly to move

Risk Analysis Performance Risk P I Mitigation Shielding is insufficient 4 1 Install additional shielding on outside, or create unrestricted controlled areas Shielding is incompatible with guide design 2 Effective communication with instrument teams Cost Risk P I Mitigation Cost estimates are insufficient 2 3 Maximise standardisation Modular design which is well-adapted to serial production Ensure quick buy-in from instrument teams Effective competitive tendering Shielding is insufficient 4 Neutronics calculations during detailed design phase, allowing some re-design if required PSS turns out to be complex and expensive Effective communication with PSS team

Risk Analysis Schedule Risk P I Mitigation Shielding may not be installed in time 1 4 Ensure quick buy-in from instruments Apply lessons learnt from bunker procurement Operability Risk P I Mitigation Shielding is insufficient 4 2 Neutronics calculations during detailed design phase, allowing some re-design if required PSS is inconveniently slow and cumbersome 3 Effective communication with PSS team Frequent access is needed to chopper pits Allocate gantry cranes to particular chopper pits Shielding is incompatible with guide design Effective communication with instrument teams

Preliminary Hazard Analysis Event P I Mitigation Fire inside shielding H3 2 Avoid use of flammable material for shielding Personnel hit by falling blocks during transport 5 Effective design of lifting points Safe use of cranes Personnel hit by falling blocks during earthquake H4 If necessary, fix blocks to floor Personnel falling off shielding 3 Install safety barriers where necessary Personnel falling into chopper pit Use safety harness when working at height Personnel receiving dose > 3 uSv/hour outside shielding H2 Radiation survey after maintenance work Personnel receiving dose > 3 uSv/hour inside shielding Radiation survey before maintenance work Personnel contaminated by activated dust Seal all exposed concrete surfaces Internal surfaces covered by steel and/or borated cement

Thank you! ESS site 2016 5th June 2015