Strategic Road Projects May 2018
Cherno More Motorway Corridor VIII Length of the alignment – 95 km Indicative value – EUR 723 million This year is forthcoming launch of public procurement procedure for elaboration of expanded conceptual design.
Kalotina – Sofia Motorway Corridor X Kalotina – Sofia Motorway Sections: Kalotina BCCP – Dragoman – 14.5 km In September 2017 tender procedures for engineering were launched. Indicative value – EUR 72.5 million, VAT excluded. Funding – Connecting Europe Facility and state budget. Dragoman – Hrabarsko road junction – 17 km In September 2017 public procurement procedure for engineering was launched Indicative value – EUR 59.8 million, VAT excluded. Funding – state budget Hrabarsko road junction – Sofia Ring Road Length of the alignment – 16.5 km At present the project is at a stage of preparation of technical design and Detailed Development Plan
Vidin – Botevgrad direction Corridor IV Vidin – Botevgrad direction Total length – 167 km In March 2018 public procurement procedures were launched for engineering of the following sections: Mezdra – Botevgrad , Lot 1 – 19.3 km Mezdra – Botevgrad, Lot 2 – 13.4 km This year will be launched public procurement procedures for engineering of the following sections: Vidin – Rujintsi, from km 3 to km 33 – 30 km Vidin – Rujintsi, from km 33 to km 47 – 13.6 km Vidin – Rujintsi, from km 47 to km 58 – 11 km
Struma Motorway Lot 3 Corridor IV Length of the alignment – 61,6 km Lot 3.1 Blagoevgrad – Krupnik – 12,6 km Lot 3.1 Zheleznitsa tunnel – 4,4 km (2 km tunnel and 2,4 km road before and after the facility) Lot 3.2 Krupnik – Kresna – 21 km Lot 3.3 Kresna – Sandanski – 23,6 km
THANK YOU FOR YOUR ATTENTION! http://www.mrrb.government.bg/