Xoserve IX Refresh Customer Update 04/04/2019.

Slides:



Advertisements
Similar presentations
Gemini Re-platforming Project Update April This presentation is to provide an overview of the Gemini Re-platforming Project (GRP) and provide early.
Advertisements

Services Flexible Workstyle and People-Centric IT Windows Accelerate: Deployment Windows 8.1 Proof of Concept (Window 8.1 PoC) will demonstrate how the.
A Review ISO 9001:2015 Draft What’s Important to Know Now
Performance Management Open Information Session Spring 2009.
COR1000 Telecoms Project UK Link Committee Update September 2012.
Network Rationalization Mail Moves, Labeling Lists and Mail Direction File Industry Webinar July 1, 2013 To listen to a recording of this presentation.
How to do business guide. Fixed, Data and Hosted Solutions by Mandy Fazelynia Latest update – 11/11/2013 Operations Director.
Supporting Industry Change Planning: Risk, Issue & Milestone Assessment Process Clarifications 04/08/2014.
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details.
August 2013 Performance Report RM Education Stoke BSF and Stoke CIS.
COR1000 Telecoms Project UK Link Committee Update May 2013.
1 June 2012 COR1000 Telecoms Project UK Link Committee.
Digital Campus: Foundation Projects
Career Ready and Programme updates
The ACT with Writing and ACT WorkKeys - Alabama
Sarah Leng Quality and Patient Safety Collaborative, KSS AHSN
Primary Care Support England
IGG Agenda 17th December 2009 Minutes from Previous IGG Meeting
TN: TEACH AACTE Grant TN TEACH: The TN EPP Assistive and Collaborative Help Network.
xoserve relocation to 31 Homer Road Solihull
UK Link Technology Refresh
360o Feedback Report Post-Training After-Session Actions
Cost of Service Analysis & Rate Design
Gemini Re-platforming Project; External User Participation July 2012
Employcoder - An offshore custom software developer to solve complex business problems!
Customer Overview Pack – September 2018
Title Date NEW OFFERING: ATTENDEES VIEWING IN A GROUP SETTING CAN NOW QUALIFY FOR CPE!! HAVE A GROUP VIEWING ADMIN DOWNLOAD, COMPLETE AND RETURN THE GROUP.
Customer Overview Pack – August 2018
End of Year Performance Review Meetings and objective setting for 2018/19 This briefing pack is designed to be used by line managers to brief their teams.
HRA User Satisfaction Report
Discussion group meeting
Updated Implementation Timeline
PRESENTATION TO THE PORTFOLIO COMMITTEE ON HOME AFFAIRS
Sarah Leng Quality and Patient Safety Collaborative, KSS AHSN
TransformUs Programme
Xoserve IX Refresh Update
Customer Overview Pack – September 2018
Xoserve IX Refresh Customer Update 12/02/2019.
Customs Declaration Service
Customer Overview Pack – July 2018
Xoserve IX Refresh Customer Update 30/10/2018.
DSC ChMC CSS update 11th December 2018
Customer Overview Pack – July 2018
Xoserve IX Refresh Customer Update 03/01/2019.
Enduring NTS Exit Capacity Arrangements - Update
Key Value Indicators (KVIs)
Course Preparation Check List
Teacher name August phone: Enter text here.
TransformUs programme
Plymouth Connect is an exciting new e-mentoring service, connecting students with Plymouth alumni around the world.
NDIA PMSC Guides Working Group
TransformUs Programme
Sarah Leng Quality and Patient Safety Collaborative, KSS AHSN
COR1000 Telecoms Project UK Link Committee Update
COR1000 Telecoms Project UK Link Committee
Xoserve IX Refresh Customer Update 05/03/2019.
WordPress Unit Web Coordinators
Xoserve IX Refresh Customer Update 04/04/2019.
KVI Analysis for period 1st May 2018 to 31st March 2019
Xoserve IX Refresh Customer Update 01/05/2019.
WordPress Unit Web Coordinators
Data Office POAP July/August 2019
Xoserve IX Refresh Customer Update 30/07/2019.
Xoserve IX Refresh Customer Update 30/07/2019.
KVI Analysis for period 1st May 2018 to 31st March 2019
Habitat Changes and Fish Migration
2015 January February March April May June July August September
Habitat Changes and Fish Migration
Xoserve IX Refresh Customer Update 09/10/2019.
Presentation transcript:

Xoserve IX Refresh Customer Update 04/04/2019

IX Refresh Customer Update (Raj Draft) Welcome to the March update of the IX Refresh Project Our focus during March has been to work on improvements identified from the learnings from the pilot which will incorporate into the rollout and most importantly enhancing the customer experience. Following on from this we have been busy planning the next pilot which we are anticipating by the end of April 2019. This will allow us to test and assure ourselves of the improvements that we have identified as well as identifying further improvements. In the meantime line installation continues as well as ongoing work with our suppliers. Whilst we appreciate that the improvements outlined will have an impact on the timelines we will look to identify efficiencies during the delivery phases of the program where possible and we will provide further information in future updates. Again I would like to reiterate our overriding aim is to make this process as seamless as possible ensuring the installation experience meets your expectations. If you’d like more detailed information about dates relevant to your migration, please email box.xoserve.IXEnquiries@xoserve.com Thank you for your ongoing support and I look forward to updating you again in April. Michelle Callaghan People Platform Director

Look Forward: IX Program Quarterly Activity Three Month Timeline April IX Server image to be amended based on findings from the Pilot V1 Updated server to be tested with a Proof of Concept (PoC) V2 Pilot V2 site migration Ongoing initial line installations to continue across all phases Router installations to take place at some phase one sites Prepare May migrations Continue to engage customers with Disaster Recovery equipment about testing approach Continue to engage relevant customers requesting additional IP range / addresses for IX End User equipment May Rollout begins with Phase One Relevant sites contacted to have servers installed Prepare June migrations Phone line installations to continue June Rollout continues for line, router and server installations Customers contacted to have servers installed Prepare July migrations Please be assured that you will be contacted by Gamma before either your Network survey or phone line installation takes place (dependant on the complexity and IX option required). If you have any queries answers to the most commonly asked questions can be found on our website in the Q&A section here.

(Where surveys are outstanding) High level migration plan – Current & future view April May June July August September March Network and Router Installation Server Installation PoC V2 Pilot V2 Phase One Phase Two Phase Three Phase Four Phase Five Remaining Sites (Where surveys are outstanding)