Injector / Linac Installation Current Status

Slides:



Advertisements
Similar presentations
Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Advertisements

FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Jose Chan FAC - BC2/Linac Installation Status & 4/16/07 1 BC2/Linac Installation Status & Schedule Jose Chan.
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Hamid Shoaee LCLS Facility Advisory Committee 20 April Plans for 2006 Installation April 20, 2006 Injector commissioning.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Shielding Design for LCLS Injector Operation – Phase one
PHIL: A TEST BEAMLINE AT LAL Specifications of PHIL
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
CLEX* Status and Plans CTF3 complex CLEX
Thermal emittance measurement Gun Spectrometer
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
Electron Source Configuration
LCLS Injector Commissioning Dates ( )
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
e-Beams Systems Update
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
LCLS Commissioning P. Emma, et al
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
Linac LLP Outline LINAC Long Lead Procurements
Maximum Credible Beam Event Paul Emma et al
Undulator Cavity BPM System Status
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
LCLS Undulator System Production Management
Diagnostics RF and Feedback
Linac Diagnostics Commissioning Experience
Operational Experience with LCLS RF systems
LCLS Injector Commissioning P
E-Beams Systems Manager
E. Michael Saleski PPS and BCS Systems Manager
LCLS Injector System Overview D. H
Control System Overview Hamid Shoaee LCLS Control System Manager
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
Overview of RF Gun Specifications and Technical Issues
LCLS e- Beams System Overview
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
e-Beams Systems Update
BC2 / Linac Installation Coordination Kathleen Ratcliffe
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
Injector Physics C.Limborg-Deprey Feb.8th 2006
LCLS e- Beams Systems Manager
Injector/Linac RF Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Injector / Linac Installation Current Status Manager-Kathleen Ratcliffe Project Schedule R.M. Boyce Major Partner-Mechanical Fabrication Department Installation Underway!

2006 Installation Sector 21 Sector 20 Laser BC1 Out Bunch Compressor 1 Vault X-Band Compressor L1 Insertion/SAB Wall

Linac Status Downtime Installation 8/~20 Weeks of Linac Access Prep and Removal Complete Installation Priority Linac Housing / Return to A-Line Operation January 07 Vacuum Envelope & All Safety Systems Injection Vault / Laser Schedule and Controls SLAC Resources / MFD and Others Hardware Ready System Schedule / Commissioning Good Design, Teamwork, Control

Linac Housing E-

BC 1 Out TD11 (Stopper) BL11/12 Future EO/BL Wire Scanner / PMT

Bunch Compressor 1 Chambers & Supports BC1 Diagnostics 4 Dipoles 2 Tweeker Quads

Bunch Compressor 1 Sub-Assembly

X-Band Compressor WC 293 Removable 60cm X-Band

The X-band accelerator section Klystron, modulator being power tested prior to installation.

L 1 2ea 9 ½ Ft DLWG

Linac Accelerator Section Removal Before Making room for the Insertion, L-1 and L-X regions After

Insertion / SAB BX 02 Dipole SDMP / Stopper OTRS1 / ANL SAB Dipole

Injection Vault E-

The Injector Vault Cable plant, vault ready for beamline components.

Wall 3 Wire Scanners BX 01 Dipole BBS Radiation Stopper

Heater Phase 1 Heater Table

L0A / L0B L0A L0B

L0A on the MMF CMM

Gun / GTL Laser Table SAB Dipole Gun

Gun-to-Linac area Laser table uv Gun L0a Spectrometer GTL

The LCLS photocathode electron gun The new-design LCLS gun, with dual RF feeds. The dual RF feeds have been added to symmetrize the RF entering the gun, eliminating a source of beam emittance growth.

Linac Downtime Issues BPM feed-through 10-9 He leak Old problem / New again (~3/23 BPMs On Temporary Hold) BC 1 Diagnostics 2/3 Assemblies close with Fab. SLA BPM is probably late for January. Late components: BLM 11 (BLM 12 will be in) Toroids (All Locations / Vendor Failure) Vacuum chambers in insertion region. (next slide) Spool pieces are being fabricated to not prevent Commissioning Start. Scheduled Downtime will be needed to install these components January : March to support current Commissioning schedule.

LCLS Insertion region Vac Chambers late for January LCLS Injection LCLS Insertion region Linac beam Vac Chambers late for January Linac integrity needed for ESA program in Jan.

Injector Installation Status Injector installation has taken second priority to Linac installation. Injector vault: Floor and cable plant installed Injector beamline: Accelerator structures, L0a ready, L0b in final bake RF waveguide needs to go through bake Gun in hot test at Klystron Mfg 2nd gun is in pre-braze cold-test. Vault Supports & Tables waiting DB start. except for the GTL supports & table

Injector Installation Issues Water system under pressure to make schedule! 1 BPM in GTL waiting feedthrough resolution. Late: Torroids are not delivered from Vendor The GTL stand is out for quote Estimate it will be here 11/16 for installation 11/20. Laser table installation begins 11/27 The Gun will be ready by Laser Table install. GTL is late, released for machining. Working all issues with MFD to expedite schedule. Improve on 2/15/07 Date.

Good Design with Solid Documentation. Active Data Base Some Good Stuff Good Design with Solid Documentation. Active Data Base Interconnect Control Component Histories Non-Compliance Effective Teamwork MFD/MD/KLY/AD Downstream Linac under design!