Background The electrification programme was started by Eskom during the late 1980’s It was further refined by the National Electrification Forum.

Slides:



Advertisements
Similar presentations
1 Presentation to the Portfolio Committee on Water Affairs and Forestry and Select Committee on Land and Environmental Affairs 2005 Department of Water.
Advertisements

SIP 18 WATER AND SANITATION MASTER PLAN Water and Sanitation Master Plan NDHS and DWA Water & Sanitation Master Plan.
Presentation to Select Committee on Public Services Briefing on Unproclaimed Roads and Road Maintenance Budgets 14 th August
1 The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure.
Experiences and Lessons Learned Electrification Indaba by Wolsey Barnard Executive Manager: INEP 15 March 2012.
INITIATIVES IMPLEMENTED ON NATIONAL AND INTERNATIONAL LEVELS FOR ENERGY EFFICIENCY AND ENERGY- SAVING IMPROVEMENT VI Eurasian Energy Forum 4-6 October.
Date 08 October 2013 SC Economic Development: Electrification Programme Ms Ayanda Noah Group Executive Distribution.
National Electrification Indaba 16 March 2012 Electrification Technical Aspects Nomvula Kungwane.
1 ALLOCATIONS for the Integrated National Electrification Programme 2009/10 Presentation to the Select Committee on Finance 25 February 2009.
Department of Arts and Culture Presentation to the Select Committee on Appropriations: 08 May 2013 Community Library Services Grant Mr Sibusiso Xaba Director.
1 DEPARTMENT OF ENERGY PRESENTATION ON THE INTEGRATED NATIONAL ELECTRFICATION PROGRAM (INEP) 10 September 2013.
Click to edit Master subtitle style 3/10/11 DEPARTMENT OF ENERGY Integrated National Electrification Programme (INEP) Select Committee on Economic Development.
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
Technical Secondary Schools Recapitalisation Grant Framework – 2011/12 Interim Report - 31 March 2012 Conditional Grant, Division of Revenue Act, 2011,
The Association of Municipal Electricity Undertakings (Southern Africa) 1 AMEU History and Structure The AMEU was founded in 1915 and for over 90 years.
1 Electrification: An Integrated Implementation Approach [Eskom’s Overview] Presentation to the Parliamentary Select Committee on Finance 22 nd August.
Programme 4: Housing Development Finance Purpose: Fund national housing and human settlement development programmes in terms of the Housing Act (1997),
Themba Wakashe Director - General Department of Arts and Culture 2009 / 10 DIVISION OF REVENUE BILL PRESENTATION TO SELECT COMMITTEE ON FINANCE NCOP 3.
SOUTH AFRICAN POLICE SERVICE HUMAN RESOURCE PLAN 2003 TO 2005 ALLOCATION OF HUMAN RESOURCES.
Integrated National Electrification Programme (INEP): Overall Performance (End of January 2012) Dr Wolsey Barnard.
Presentation to the Select Committee on Finance 26 FEBRUARY 2006.
1 Local Government Budgets and Expenditure Review 2001/02 – 2007/08.
1. PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATIONS Public Hearing on Division of Revenue Bill March
Electricity Sector April Electricity sector in perspective Electrification of households is one of Government’s priority programmes The country.
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
Performance of the Integrated National Electrification Programme as at 30 June 2008 (4 rd Quarter) Presentation to the Select Committee on Finance 14 August.
Public Hearings on Division of Revenue Bill, 25 February 2009 Presentation by Department of Water Affairs and Forestry 1.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
FREE BASIC ALTERNATIVE ENERGY/ FREE BASIC ELECTRICITY 6/14/20161.
1 DEPARTMENT OF MINERALS AND ENERGY Presentation to Parliamentary Portfolio Committee Presentation to Parliamentary Portfolio Committee 9 June 2004 PRESENTATION.
Date : 20 October 2010 Electrification of Schools and Clinics Programme.
Financial and Fiscal Commission
Presentation to the Portfolio Committee on Energy
RESTRUCTURING OF THE ELECTRICITY DISTRIBUTION INDUSTRY
Transformation Integrated Strategy
DEPARTMENT OF ENERGY PPC MINISTERIAL BRIEFING ON THE OUTCOMES OF THE SERVICE DELIVERY AGREEMENT Ms Dipuo Peters, MP Minister of Energy 09 October 2012.
Legislation Constitution of the Republic of South Africa, 1996 (Act No. 108 of 1996) Housing Act No.107 of 1997 The Housing Consumers Protection Measures.
FREE BASIC ELECTRICITY/FREE BASIC ALTERNATIVE ENERGY
Trevor Balzer: Acting CFO Helgard Muller : CD Water Services
PRESENTATION TO SELECT COMMITTEE ON FINANCE
INTEGRATED NATIONAL ELECTRFICATION PROGRAM (INEP)
National Department of Health Presentation to the Standing Committee on Appropriations Public Hearings on the Adjustments Appropriation Bill 05 November.
Early Childhood Development Delivery – one year later
Select Committee on Cooperative Governance and Traditional Affairs Operational Response Plan Audit Outcome of Municipalities 16 August
SA Fakie Auditor-General
Collaboration with other government entities
Eskom’s Electrification Programme
Overview of the Electricity Regulation Bill
NATIONAL DEPARTMENT OF HEALTH
PRESENTATION OF THE 2008/9 MTEF STRATEGIC PLAN.
Parliamentary Portfolio Committee on Energy
GREEN FUND PROJECT PROTFOLIO
PRESENTATION TO THE SELECT COMMITTEE ON FINANCE 18 OCTOBER 2005
DEPARTMENT OF ENERGY PPC MINISTERIAL BRIEFING ON THE OUTCOMES OF THE SERVICE DELIVERY AGREEMENT Ms Dipuo Peters, MP Minister of Energy 09 October 2012.
DEPARTMENT OF ENERGY PPC MINISTERIAL BRIEFING ON THE OUTCOMES OF THE SERVICE DELIVERY AGREEMENT Ms Dipuo Peters, MP Minister of Energy 09 October 2012.
Select Committee on Finance Water Services Operating and Transfer Subsidy 10 May 2006 Department of Water Affairs and Forestry Jabulani Sindane : DG Trevor.
Division of Revenue Bill 2004/05
BUCKET ERADICATION : KWAZULU-NATAL
Select Committee on Economic Development INEP and SWH 14 June 2011
Monitoring Structures & Processes to ensure that the pothole reparation project across the 9 Provinces has the necessary delivery impact" 02 August.
Sport and Recreation Infrastructure Programme
mSCOA Readiness for 31 March Budget Data Strings Upload
Progress on the Renewable Energy IPP Procurement Programme
PRESENTATION TO THE SELECT COMMITTEE ON EDUCATION & RECREATION
ANNUAL PERFORMANCE PLAN
Presentation to the Standing Committee on Appropriations DEVOLUTION OF PROPERTY RATE FUNDS GRANT 12 OCTOBER
DEPARTMENT OF ENERGY Select Committee on Appropriations on the Division of Revenue Bill 2011/12 EDSM and INEP Grants Dr Wolsey Barnard and Mr Mohau Nketsi.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON SPORT & RECREATION
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Annual Financial Statements for the year ended 31 March 2017
Presentation transcript:

Background The electrification programme was started by Eskom during the late 1980’s It was further refined by the National Electrification Forum (NELF) during the early 1990’s. Access to electricity for households in RSA was approximately 30%. During this period the electrification programme was funded through the National Electricity Regulator (NER)

Background Cont. After 1994 and through the government’s initiative of RDP (Reconstruction and Development Programme), electrification programme was endorsed. During 2001 the government took responsibility for funding electrification programme. The funds are made available from the fiscas President’s State of Nation Address (universal access in RSA by 2012)

MANDATE OF INEP To manage the electrification planning, funding and implementation process, with the aim of addressing electrification backlog so as to reach universal access by 2012. Our Focus areas Managing the electrification planning process Managing the electrification funding allocation process Managing the electrification implementation process Monitor the INEP in line with the Energy white paper, the Division of Revenue Act (DoRA, Public Finance Management Act (PFMA),ER Act, OHS Act etc.

SITUATIONAL ANALYSIS

National backlog (Households) Province Eskom Area Municipal Area Total Backlog Eastern Cape 625,760 103,721 729,481 Free State 156,805 44,507 201,312 Gauteng 256,750 415,969 672,719 Kwazulu-Natal 657,642 156,890 814,532 Limpopo 345,725 36,460 382,185 Mpumalanga 155,137 60,343 215,480 North West 150,142 27,859 178,001 Northern Cape 45,302 11,326 56,628 Western Cape 75,759 90,436 166,195 Total 2,469,022 947,511 3,416,533

National backlog cont.(H/H)

National backlog (Schools and Clinics) Province Schools Clinics Eastern Cape 1924 Free State 157 Gauteng Kwa Zulu-Natal 2230 Limpopo 263 Mpumalanga 400 North West 151 Northern Cape 6 Western Cape Total 5131

TRANSMISSION SUBSTATIONS Electricity value chain GENERATION Electricity is Generated by burning of fossil fuels (coal, oil, or natural gas), use of nuclear technology and hydro capability 2 TRANSMISSION SUBSTATIONS MUNICIPALITIES 1 TRANSMISSION LINES 3 TRANSMISSION (400/275 kV) POWER STATIONS High Voltage electricity is carried between Generation and required Distribution through Transmission networks (or Transmission grids) DISTRIBUTION LINES DISTRIBUTION (132/33 kV) The distribution networks collect ‘stepped down’ electricity from the transmission networks and deliver it to Redistributors /End Users DISTRIBUTION SUBSTATIONS The voltage levels of electricity are further transformed to meet Distribution requirements SERVICE CONNECTION RETICULATION HV LINE (11 & 22kV) Customer consumption is measured at the point of supply in KWh. This information is used to measure and bill consumption levels utilised/sold RETICULATION LV LINE (380/220V)

Electrification Plan (Actual data)

Electrification Projected Trend

CHALLENGES Challenges in the Electricity industry in South Africa Ageing electricity infrastructure Minimum or no investment by respective distributors (municipalities) in the operation and maintenance of the electricity infrastructure to date, hence lack of maintenance. Increased blackouts and brownouts in the country, concern for quality and security of supply for the 2010 FIFA World cup Limited or lack of adequate skills at local government level for operation and maintenance electricity infrastructure.

Electrification outputs Project life cycle Pre-Engineering and Detailed design Household connection 80 % Construction for backbone infrastructure Poles Cables MV and LV 15% 5% Start Finish

Electrification outputs Project life cycle Pre-Engineering and Detailed design Household connection 80 % Construction for backbone infrastructure Poles Cables MV and LV 15% 5% Start Finish

Projected outputs for MTEF

DoRA FRAMEWORK

Comments (current) Current framework support the projected outputs Connections for households, schools and clinics Building of bulk infrastructure Assist in monitoring performance Reallocate funding were is required (if necessary)

Comments (future) Have a schedule that allows funding of DSM and Energy Efficiency initiatives for municipalities Framework outputs MW shifted through the programme Assist in monitoring performance Process to be initiated with National Treasury

INSTITUTIONAL AND LEGISLATIVE FRAMEWORK Electricity Regulation Act (Act. No 4 of 2006) completed, will be used to: Monitor compliance to the quality of supply regulations (to be completed by the end of October 2006. Enforce penalties to distributors for non-compliance Improve integration during planning process with municipal IDP. Eskom progress report to municipalities as per DoRa requirement

THANK YOU Questions….?