EST102: 25/10/11: Project Services Website rationalised.

Slides:



Advertisements
Similar presentations
Key components Budgeting and Planning System
Advertisements

Update to NLAG board 22 nd December Sep Jan MCE Workforce and OD Oct Nov Dec IM&T Estates Finance In hospital Model Out of hospital Model Progress.
Introduction. Service Update Property Investment Residential Care to Supported Living New Business Recruitment and Retention.
Illuminating Britelite’s Internal Services for Success Strategy for Process Improvement.
S3.1 session day 5 2 Programme management download resources from Approved by the Advisory Group: Programme management Programme and project.
CONSTRUCTING WEST MIDLANDS Question & Answer Session 22 nd March 2011 LOT 7 – CAPITAL WORKS.
Presenter: Igna Visser Date: Wednesday, 18 March 2015
Overview of Structure General Data Protection Regulation (GDPR)
Award Contract.
Industry Governance Group 28th May 2009
SIP Report – Nov 2017 Overview Headlines Workstream report
Project management for working professionals
Thinking of changing your Library Management System?
Phase 2 Tollgate Review Discussion Template
Phase 3 Tollgate Review Discussion Template
The Lean Sourcing Process
SmartMeterTM Steering Committee Update – September 2012
Phase 3 Tollgate Review Discussion Template
Eagle Programme : 4 Box Summary
Overall Project RAG Status
Sustainable Transition / Handover of malaria TB and HIV Global Fund Grants Generic 2018.
EST102: 09/10/17: Indicative Contract Award.
Update to NLAG board 24th November 2015
Week 14 – Information System Development
SmartMeterTM Steering Committee Update – March 2013
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 1st Feb to 12th Feb Feb 2018: 10 day Standstill
Student Administration and Support Programme and Project Timelines
Insert name of who presenting to
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Overall Project RAG Status
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Student Administration and Support Programme and Project Timelines
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST102: 12th Feb to 9th Mar 2018: Negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: Estates will issue new procurement schedule.
EST102: 17/11/17: Uptake of Customer References.
SmartMeterTM Steering Committee Update – July 2012
EST103: Implementation Planning Underway
EST103: Inputs for implementation planning complete. NEXT STEPS
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
SmartMeterTM Steering Committee Update – February 2013
EST102: 10/10/17: Cost Review Meeting.
Student Lifecycle Project 14th May 2008
Defining project management
Student Administration and Support Programme and Project Timelines
EST103 Estates myProject Implementation Project Report 02/11/18
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 22/02/19
Overview Headlines RSP – Progress Overview General progress report
Introduction to Project Management
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Tasks completed this period Tasks in focus next period
RSP – Progress Overview General progress report High level plan
EST103 Estates myProject Implementation Project Report 01/02/19
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
EST103 Estates myProject Implementation Project Report 09/11/18
EST103 Estates myProject Implementation Project Report 03/05/19
EST103 Estates myProject Implementation Project Report 10/05/19
EST103 Estates myProject Implementation Project Report 08/02/19
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
EST102: 30th Mar 2018: Complete negotiation of contract Ts&Cs
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Tasks completed this period Tasks in focus next period
Project Name Here Kick-off Date
G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston
Presentation transcript:

EST102: 25/10/11: Project Services Website rationalised. EST102 & EST103 Estates Capital System Procurement & Implementation Project Report 27/10/17 R A G Project Sponsor & Business Lead : Anna Stamp & Jane Johnston Business Project Manager: Jane Cameron IS Estates Programme Manager: Derrick Matheson IS Project Manager & BA: Lyn Thomson ACHIEVEMENTS EST102: 04/10/17: All scoring complete for Business & IS question sets and consensus meetings held. EST102: 10/10/17: Cost review meeting held. No further clarifications are required from the 2 lowest scoring vendors. Decision taken to carry out site visits to existing customers and invite for further clarification meetings for the 3 highest scoring vendors. EST102: 25/10/11: Project Services Website rationalised. EST103: 24/10/11: Project Implementation plan updated with feedback from Programme Manager & v0.2 issued. NEXT STEPS EST102: Estates will issue new procurement schedule. Project RAG is green (even though existing schedule is missed) because we expect to complete initial contract award Nov 2017 and final contract award Dec 2017. EST102: Customer Site Visits. EST102: Vendor Clarification Interviews. EST102: Notify Vendors of Decision. EST102: Indicative Contract Award. EST102: 31/10/17: Write up of feedback on questions sets & procurement experience. EST103: 30/10/17: Initiation of project delivery meetings with Estates. EST103: 10/11/17: Prepare Project Brief and rationalise Project Services website. MILESTONES Baseline Actual/ Predicted EST102 ITT Issued 27/07/17 EST102 Responses from Vendors Received 21/08/17 EST102 Notify Vendors of Decision 13/10/17 20/10/17 EST102 Indicative Contract Awarded 24/10/17 31/10/17 EST102 Contract Finalised 17/11/17 24/11/17 EST103 Initial Planning & Project Brief 29/09/17 10/11/17 EST103 Phase 1 DPI – Programme Management May 2018 EST103 Phase 1 DP2 – Cost Management Aug 2018 EST103 Phase 1 DP3 – Portfolio Management Nov 2018 EST103 Phase 2 DP4 – Project Management Jan 2019 RISKS & ISSUES RISK 1: Late completion of procurement will delay implementation: Begin any possible   “generic” planning and design in advance of knowing the identity of the   application that will be installed to smooth and speed the implementation. RISK 2: Too much change happening at the same time in Estates limiting the availability of Estates Resource at the right time: Good governance and stakeholder management. RISK 3: Unable to recruit new staff into Estates in time to support the new operating model which is required to successfully transition to the new application: Working on TOM, roles & responsibilities matrix leading to gap analysis to identify existing colleagues that can cover the work were possible. RISK 4: Existing data will not be of required quality to migrate to the new system: Thorough data analysis   exercise supported by 3rd party experience, early start to data cleansing, clear plan for cut-over. RISK 5: Technical Integrations may be more extensive & difficult than expected: work with identified third party supplier as early as possible to understand the number of integrations required and options. Set expectations with the business. RISK 6: 3rd party risks –   cultural, relationship, availability: Full OJEU procurement exercise (EST102) and contract, Support agreement, Hosting agreement, focus on   experience of 3rd party team during the procurement cycle.