Minuteman Vocational Technical Regional High School Progress November 19th 2018 – December 17th 2018
December 17th View of Area A & B – Upper Level Taping/Sanding activities in progress.
December 17th View of Area G – Low Roof Level Green roof membrane substantially complete. Lower level window installation in progress. Out building foundation complete. December 17th View of Area G – Upper Level Sheetrocking & Taping activities in progress
December 17th View of Area E – East Elevation Media Center Curtain Wall Glazed. Metal Panel Installation in Progress.
December 17th View of Area E – East Elevation Rigging and setting of equipment curbs on E Roof.
December 17th View of Area D – Upper Level Sheetrocking activities have commenced and are in progress.
December 17th View of Area D – Gymnasium Slab on Grade was placed 12/10. Rough-in of overhead MEP’s in progress.
December 17th View of Area E+F – Lower Level Final placement of monumental stairs occurred week of 12/10. December 17th View of Area E+F – Lower Level Interior CMU construction nearing completion. Rough-in of overhead MEP’s in progress.
December 17th View of Area F – East Elevation Storefront installation complete. Architectural stone veneer complete. Metal panel installation in progress. December 17th View of Area F – Lower Level Interior CMU wall construction in progress.
December 17th View of Area C – West Elevation Masonry Veneer complete on West elevation. Remaining elevations concurrently in progress. December 17th View of Area C – Mezzanine Level Misc Metal stairs and railings in progress. Temp staging to support overhead rough-in being constructed.
December Construction Schedule Look Ahead: Area A+B Complete Metal Panel Installation Activities Complete Taping on Upper Level B Continue Prime Painting CMU Walls on Lower Level Commence Prime Painting on Upper Level B Area G Complete Window system installation on Lower Level Continue Sheetrocking activities on Upper Level Commence Taping on Upper Level Commence Sheetrocking activities on Lower Level Area E Continue Curtain Wall & Window System installation Continue Rough-In of OH MEP’s on all levels Continue Wall Framing activities on lower level Area D Complete Masonry Veneer activities. Continue Rough-In of OH MEP’s in Mechanical Room & Gymnasium. Continue Window system installation. Area F Complete Window installation. Complete Interior CMU wall construction. Commence Rough-In of OH Duct work. Area C Complete exterior masonry veneer on remaining elevations. Commence Rough-In of OH MEP’s over the theater space. Exterior/Sitework Complete Foundations for exterior out buildings. Continue setting equipment curbs and equipment on all roof levels.