Recap QUANTITIES Taking out quantities
WHY do we need quantities?
3 WAYS Based on m2 price of building type Based on m2 of building component Based on detailed calculations of Materials, Manpower, Machinery
Today you will use Based on m2 price of building type Based on m2 of building component Based on detailed calculations of Materials, Manpower, Machinery
PRICE In order to CALCULATE THE PRICE of a building you need to know the quantities of: Building Materials Man Power Machinery / Equipment
TYPE OF WORK (TRADES OR PROFESSIONS) How many do you have? SOIL WORK (construction worker) SEWER (auth. construction worker) CONCRETE (concreter) BRICKWORK (bricklayer) CARPENTRY WORK (carpenter) DEKORATION (painter) INSTALLATION (plumber, electrician, etc.) How many do you have?
YOUR JOB To take out quantities for: Concrete Works Masonry Works Concrete Element works
2 WAYS To take out quantities: MARK THE AMOUNT ON DRAWING PRINTOUTS AND CALCULATE QUANTITIES EXTRACT QUANTITIES DIRECTLY FROM REVIT MODEL
WBS ”Breakdown of the total project into trades, building components or other units”
OPEN REVIT FILE: Take out quantities for your trade OPEN REVIT FILE: Take out quantities for your trade. Calculate the price an fill it in the Bidding form
BID ”An offer to the client to make a job for a certain payment”
DEADLINES FOR QUANTITIES/price: Friday AT 08:00 the 3/3 2017