XRN4534 Deployment Options December 2018

Slides:



Advertisements
Similar presentations
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
Advertisements

Distribution Workgroup 24/11/16
UK Link Technology Refresh
UKL Future Release 2 Cutover/Implementation
13-block rotation schedule
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Release 3 Plan Options Decision
Overall Project RAG Status:
Amendment Invoice Task Force Progress Report
Release 3 Update December 2018.
Amendment Invoice Task Force Progress Report
R&N Timeline Release 2 Release 3 Feb-19 June-19
Release 3 Update November 2018.
EUC Project Timelines Key Upcoming Dates:
DSC Change Committee Summary – 11th July
XRN4361 – UK Link Release 2 - Delivery
Release 3 Plan Options Analysis
Overall Project RAG Status
UNC Modification 0531 Provision of Industry Testing System
Amendment Invoice Task Force Progress Report
Amendment Invoice Task Force Progress Report
South Milford Pre-School Playgroup
Release 3 Update 9th January 2019.
Overall Project RAG Status:
R&N Timeline June-19 Sept-19 (EUC) Nov-19 Minor Release D4
Release 3 Update 13th February 2019.
DSC Change Committee Summary – 9th January ‘19
Potential Minor Release Drop 4 Timeline & Scope
Amendment Invoice Task Force Progress Report
XRN Nov 19 Release - Status Update
XRN Nov 19 Release - Status Update
UKL Future Release 3 XRN4534 – Amendment to RGMA validation rules for asset install date Deployment Options – 9th January 2019 Update.
June 19 Timelines Key Upcoming Dates:
Release 3 Update 07th March 2018.
Release 3 Scope & Proposed Plan
Release 3 Scope Selection and Plans
Change Management Committee – Retail & Networks Update
GDPR Dashboard General Data Protection Regulation 06/02/2018
Amendment Invoice Task Force Progress Report
XRN4249 – Part B Data Migration Plan
Minor Release Drop 3 Timeline
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Overall Project RAG Status:
Overall Project RAG Status:
4534 RGMA Validation Update
XRN Feb 19 Minor Release - Status Update
June 19 Timelines Key Upcoming Dates:
XRN4361 – UK Link Release 2 - Delivery
XRN Nov 19 Release - Status Update
Release 3 Update 07th March 2018.
XRN4361 – UK Link Release 2 - Delivery
Retail & Networks ChMC Update
Overall Project RAG Status:
XRN November 2019 Release - Status Update
UIG Task Force Progress Report
4340 – UK Link Future Release 1.1
XRN Nov 19 Release - Status Update
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
UIG Task Force Progress Report
Potential Minor Release Drop 4 Timeline & Scope
GDPR Dashboard General Data Protection Regulation 06/02/2018
Minor Release Drop 3 Timeline
XRN Nov 19 Release - Status Update
UK Link Timeline June-19 Sept-19 (EUC) Nov-19
UK Link Change Impacts and Release Update
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
Presentation transcript:

XRN4534 Deployment Options December 2018 UKL Future Release 3 XRN4534 Deployment Options December 2018

Option Timelines w/c 3 Dec 10 Dec 17 Dec 24 Dec 31 Dec 7 Jan 14 Jan 4 Feb 11 Feb 18 Feb 25 Feb 4 Mar Option 1 Option 2 Option 3 AT RT IDR / Cutover AT Cont. RT IDR / Cutover AT Cont. RT IDR / Cutover

Current options RAID & Platform View Go Live Date RAID Platform View Negative Positive 1 1st Feb 10th December assumes best case dates for remaining BAU defect fixes - no contingency IDR planned for 23/24th January - no contingency 3 weeks is bare minimum for AT and RT - no contingency for defects Very little allowance made for Christmas holidays, assuming work can be carried out on all non-bank holidays Creates dependency between this and Cadent which creates additional risk to the Cadent deployment Deploys with rest of R3 track 2 - same governance, IDR, cutover etc. Full PIS window in line with R3 track 2 There is a high probability of finding additional existing production defects during AT so given the time constraints, this is a very high risk option 2 16th Feb Falls in line with Minor Release Drop 3 and adds dependency and risk to that deployment Allows no contingency against 3 week RT window for defect resolution. Still some potential dependency between this and Cadent deployment Falls in line with Minor Release Drop 3 so governance would be streamlined Includes additional week contingency between AT and RT for code merge into MiR track Still allows 3 weeks of PIS before end of release 3 PIS Whilst timelines are improved and more achievable, added risk and dependency on MiR drop 2 is undesirable 3 23rd Feb Requires independent deployment governance around CAB etc Only allows 2 weeks of PIS before end of Release 3 PIS Includes additional week contingency in each of AT and RT plus one full week in between for defect resolution. Removes any dependency and therefore risk on MiR drop 3 deployments Reduced dependency and therefore risk on Cadent deployment Preferred to 16th Feb option in light of RAID

Recommendation The Xoserve Project team recommend that we continue to aim for deployment on 1st February with a contingency of moving to 23rd February endorsed by ChMC. This contingency can then be used if additional production defects are identified during testing or other dependencies and risks materialise. If the impact of additional production defects uncovered are such that 23rd February is at risk then further engagement will be required at ChMC

Contingency options beyond February 19 All options for February deployment carry a degree of risk based on potential to discover further defects in testing and also because of the need to protect Cadent delivery. Alternatives beyond February are: Operationally, deployment would be possible in March but this would require project resource extensions to support deployment and PIS independent of Cadent Alignment to June 19 release is possible but this would also require project resources to be available and would create a dependency and associated risk to that release Beyond June 19 there is a Minor Release drop in July and a further major release proposed for November 19