Can operation put the MPS in a unsafe state?

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Fabio Follin Delphine Jacquet For the LHC operation team
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Wednesday
DRY RUNS 2015 Status and program of the Dry Runs in 2015
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
SPS extraction, transfer lines, injection
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Jan Uythoven For discussion
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday 11/07: Recovery Plenty of accesses.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Monday 6th August & night
Summary of Week 11: 14 – 21 March
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Summary of Week 13 G. Arduini, B. Holzer
Interlocking of CNGS (and other high intensity beams) at the SPS
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Mike Lamont, Jorg Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Saturday 4.12 Beam in the SPS at 09:30 Beam in the LHC at 10:00
Week 35 – Technical Stop and Restart
Monday Morning – recovery from cryo.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Yesterday morning Held 1647 for a while – SPS kicker problem
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Machine Protection System Commissioning plans
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday Fill 1364 (24 bunch) dumped at 07h
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
The LHC Beam Interlock System
Interlocking strategy
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Tuesday
HI2011 Commissioning Status
Presentation transcript:

Can operation put the MPS in a unsafe state? Laurette Ponce (BE/OP) With input of all the OP team Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Preambule 2 questions in one: Can operation put the machine in an unsafe state ? Can operation put the Machine Protection System in an unsafe state? YES , we did both: The OP team has been very efficient in stressing the Machine Protection System over the 2010 run (long?) list of errors presented in OP review and Evian But we have learnt from our mistakes Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Some examples Case 1 : Loss of the beam due to procedural errors caught by MPS → beam DUMP: Sending incorrect trim values (5 units on tune instead of chroma) Sending wrong commands/settings (OFB on during collisions, mega chirp) ... Case 2 : putting the machine in an unsafe situation so that if something else goes wrong, it is not properly protected: Forgotten masked software interlocks (SIS, cryo,..) Tasks forgotten or played in the wrong order Wrong orbit Major risk Chamonix 2011 - Operation and MPS

MPS components integrity 1/2 Case 1 errors caught by MPS suppose that MPS is properly working MPS components are designed to be fail-safe: Redundancy, sanity checks, pre-ops checks Before beam injection, series of sanity checks to guarantee MPS integrity: BLM sanity checks BI checks LBDS IPOC, XPOC Collimators energy thresholds MCS checks for LBDS and injection BIC pre-ops checks ... Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Un mal pour un bien? Based on 2010 run experience, a lot of improvements were added over summer time (thanks again to OP for the appreciated contribution): Several new SIS interlocks (injection settings, RF frequency range, CODs settings,...) New tasks in the nominal sequence, to check settings during all the phases, for the incorporation (injection checks, run through the squeeze, collisions preparation...) New beam process for preparing collisions including most of the critical settings management (collimators, copying lumi scan values …) Reduced a lot the mis-manipulation and as a consequence the stress of the MPS Chamonix 2011 - Operation and MPS

Sequence and sequencer Rationalization of the nominal sequence and procedure Automatization as much as possible, espcially the tricky tasks: really few left Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS What can OP still do? Direct errors are caught by the MPS, so the major risk is combination of MPS put in an unsafe state and another error: Case 2 errors masking/forcing interlocks is the first obvious way of putting MPS unsafe: Masks in BIC, SIS Force value for cryo Some interlocks used only for injection (QPS-OK) Some examples of dangerous situation: TCDQ retraction interlock left masked after collimator set-up Wrong references used for orbit or tune feedback Movement of collimators at constant gap (interlocks only on the gap) Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Masking policy in 2010 Conditions for masking: BIC masks are conditioned by set-up beam flag Mask ignored above Cryo mask : manual procedure to force value and lock circuits SIS masks : only access rights protected QPS-OK : SIS interlock for injection only + consigne to not ramp Some examples: Cryo signal forced at the wrong level BIC interlock forgotten → beam dump during the high intensity filling or ramp SIS interlock latched → beam dump QPS-OK masked for ages Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Mask :Improvement for 2011 In SIS: Possibility to TAG a set of interlocks to unmask/mask per group Sequencer task will be added in the nominal sequence to unmask before injection/ramp... QPS-OK: (See Walter's talk) New interlock for quench heaters within the QPS sytem: if more than 2 heaters discharging for MB → dump No more visual checks Chamonix 2011 - Operation and MPS

Risk at injection : key role of TDI Injection system is designed to handle injection failures: TDI has saved us in all cases of injection failure Importance of the TDI positions Injection procedure implies movement of the TDI in/out: Sequences to handle the movements End of filling sequences to be played in right order SIS interlock on the TDI gap added during the run to prevent injection in case of wrong settings: Avoid pulsing the kicker with TDI out But nothing prevents movements at constant gap. Improvement for 2011: TDI energy gap interlock for the SPS extraction Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Over-injection Over-injection is not a major risk in itself, except if combine with a wrong TDI settings Based on the Injection Quality Check results, injection sequencer should prevent over-injection But during 2010 run, reliability problem of the transfer line BCT Beam injected but not seen and IQC ask for repeat inejction Risk of over-injection on high intensity train When beam presence flag is OK, no extra check on injected intensity Rely only on communication with injectors OP to get intermediate intensity New for 2011: Cross-check of injection between BQM and configuration database But still manual validation from operation Chamonix 2011 - Operation and MPS

Transfer Lines trajectory Trajectory correction during injection process Effect of correction only validated by next injection Rely only on procedure, no constraints on beam current SPS extraction interlock on the converter current Limit set to 1.5 sigma (about 10 urad) Limits editable by OP, except very critical one at the end of the line New for 2011: IQC latch on injection oscillation Injection oscillation interlock to force going down to intermediate intensity after correction Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Orbit control Not discussing HW or software (feedback) failure, but only human factor Major risk in circulating beam: run with an orbit displaced w.r.t the reference orbit for collimators settings Possible human origins: Wrong reference used to correct: keep inejction orbit for collisions Create a local bump Lumi-scans: free parameters in the application in Mitigation in place in 2010: Sequencer tasks to checks references Quite tight orbit tolerance interlock in SIS at injection and STABLE BEAM, less protective in betwen because of the separation and Xing reduction For 2011: Dynamic change of the references for feedback, providing feedback controller reports state, to be translated in sequencer task Aperture-meter to monitor orbit @ TCT with lumi-scan Chamonix 2011 - Operation and MPS

Risks in circulating beam Collimators aligned around a reference orbit Problem when the orbt is not the reference one But also if the settings are not the correct ones Management of the collimators by sequences = human: Forgotten sequence : Stable beam without TCT in place Wrong settings or wrong beam process used with loading also the wrong limits For 2011: Function instead of stopping point in the squeeze Check real position versus reference settings to be implemented Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS State machine To ensure the execution of tasks in the safe order Series of checks automatically executed when moving to a new state, only certain transition permitted To be added in 2011: ALLOWED TASKS: to block execution of certain tasks in a given state (like moving out collimators...) Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Where is the danger? Non-interlocked systems, still relying on procedure: Abort gap cleaning : interlock logic to be defined Gas injection for BGI Injection cleaning with transverse dampers MDs : ab-normal operation, huge human factor Protection of the physics settings to be put in place Masking or skipped task for studies In the flexibility: Several hypercycles, Beam Processes, IP optics... Chamonix 2011 - Operation and MPS

Recovery nominal operation How to ensure the nominal settings after MDs Recovery sequence? How to protect physics settings? Reset all masks, change of thresholds, special settings Reset skipped tasks in the sequence Low intensity cycle after each period? After HW intervention, technical stops: Powering tests procedure defined by MP3 Interlocks tests Check of the PIC configuration =>To be as rigorous as during HWC Chamonix 2011 - Operation and MPS

Chamonix 2011 - Operation and MPS Summary During 2010 run, a lot of efforts to suppress the human factor: suppressing manual tasks Interlocks added in SIS Improvement for 2011: Sequence to unmask + TAG in SIS Interlock on injection oscillation TDI energy gap for injection interlock Dynamic reference for the feedbacks Reduce the number of stopping points in the cycle: Functions for the squeeze Recovery procedure from MDs, TS or piquet intervention to be clearly discussed For certain errors (collimator movements at constant gap), human factor can do it but also catch it Chamonix 2011 - Operation and MPS

Can operation put the MPS in unsafe state? Conclusion Can operation put the MPS in unsafe state? Certainly still YES, but it is harder and harder! Chamonix 2011 - Operation and MPS