ESS Bilbao RF Systems Overview Pedro J. González

Slides:



Advertisements
Similar presentations
ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Advertisements

DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015.
WU1 - Management S. Gammino (INFN). WU1 Management and TDR preparation: overview and criticalities 2 The WP6 aim is to define the best design of the Warm.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Anders Sunesson RF Group ESS Accelerator Division
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
ESS LLRF and Beam Interaction. ESS RF system From the wall plug to the coupler Controlled over EPICS Connected to the global Machine Protection System.
ESS RF System Design Stephen Molloy RF Group ESS Accelerator Division SLHiPP2 4-May-2012.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Alex Zaltsman Power Amplifiers and LLRF.
12 GHz Stand alone power source at CERN G.McMonagle AB/RF.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 17 th December 2013.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
H. Danared | TB12, 5 Mar 2015 | Page 1 Håkan Danared Mats Lindroos Lund, 5 March 2015 Status of In-Kind Contributions to Accelerator.
ESS Spoke Linac section RF Anders Sunesson, RF group leader Rutambhara Yogi ESS Carlos Martins ESS Roger Ruber FREIA.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
High Voltage modulators ESS developments Carlos A. Martins ESS Accelerator Division, RF electrical power systems.
H. Danared | Collaboration Board | Page 1 Status of In-Kind Contributions Håkan Danared Legnaro, 1 December 2014.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Accelerator Installation Plan: Graphical representation E. Sargsyan & L. Lari DRAFT - March March 2016.
The status of RF components G. Riddone, M. Filippova RF development meeting on
Modeling SNS Availability Using BlockSim Geoffrey Milanovich Spallation Neutron Source.
Linac Design Update Project WP6 - Monthly Report –
ESS LLRF and Beam Interaction
S1G Experiment Schedule Plan
RF cell Anders Sunesson RF group leader
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
CSP 25th November 2010 Technical agreement number 3: overview
Overview and System Design for ESS LLRF Systems
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
352MHz Klystron Control for the 3MeV Linac test stand
WP Coordinaten XFEL RF Operation
RF Power for C75 - Resources
LLRF and Beam-based Longitudinal Feedback Readiness
C75 LLRF Cost and Schedule
RF Power for C75 - Resources
Sector 0 RF System Installation of components (Master Amplifier and PEP Phase Shifter) in October down time. Testing and commissioning during October.
Strategic Planning Timeline Overview
ESS Project Status Roland Garoby – Technical Director August 2018.
RF Distribution for Warm Linac
RF Local Protection System
LO BOX and LO/CLK DISTRIBUTION Arash Kaftoosian ESS Bilbao, May 2018.
RF systems introduction
HIGH POWER AMPLIFIERS For WARM LINAC Arash Kaftoosian
Ciprian Plostinar Workshop on Testing and Commissioning
Krzysztof Czuba ESS LLRF Quarterly Meeting
Risk, Schedule, Deliveries
Introduction CDR Normal Conducting Linac LLRF
STATUS REPORT OF THE SPARC HIGH POWER RF SYSTEM Nov. 16, 2005 R
Elettra – Sincrotrone Trieste S.C.p.A.
Licensing update TAC 18 October 2018
European Spallation Source ERIC
BSM S. Grishin (installation manager),
High Level Readiness Reviews
IKCA CEA Technical ANNEXES Follow up 18th DECEMBER 2015.
Status of the ESS High Power RF Systems
Plan for early Operation
RF introduction Anders Sunesson RF group leader
CE compliance -LLRF- Anders Svensson, ESS
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Accelerator Installation Schedule
SNS-PPU upgrades the existing accelerator structure
Injector/Linac RF Status
Project Support Meeting January 9, 2019
Presentation transcript:

ESS Bilbao RF Systems Overview Pedro J. González Zamudio, 30th May 2018

Outline In-Kind Contribution in RF Systems Status of Call for Tenders Proposal of Scope Swap Detailed Project Schedule

In-Kind Contribution in RF Systems Klystron Modulators for RFQ and DTL (3370 k€) RF Power Stations for Warm Linac (RFQ and DTL) and LLRF for Spoke Linac (7334 k€) MEBT RF Power Stations (~900 k€) Modulators (3 pcs) High Power Amplifiers (6 Klystrons, 3 SSPAs) RF Distribution (6 WG, 3 Coax, Circulators, Loads… RF Local Protection System (9) Low Level RF Control (9+26)

Calls for Tenders AMPLIFIERS Klystrons SSPAs Klystron Drivers 3 klystrons were available at ESS B for reconditioning and guarantee extension: 1 failed (micro-leak)  repair and guarantee extension by CPI 2 to be reconditioned immediately (permit from CPI received) 3 new klystrons: Tendering docs under review by the State Lawyer SSPAs Procurement procedure ongoing (technical evaluation) Klystron Drivers Procurement soon (subject to scope swap?)

Calls for Tenders RF DISTRIBUTION Circulators and Loads Waveguides Open procedure launched in Feb 18 failed (low price?) New procurement procedure to be launched ASAP Estimated delay: 4 months Waveguides Tendering docs under review by the State Lawyer Mechanical Supports Procurement soon (subject to scope swap?) Coaxials Procurement soon (minor contracts)

Calls for Tenders LLRF, RF-LPS Main procurements by end of summer 2018

Steering Committee Permit Contract Notice Published Calls for Tenders Tender Procedure Estimated Value (€) Technical Doc. Ready Admin. Doc. Ready State Lawyer Report Steering Committee Permit Contract Notice Published Contract Signed SSPAs Open, harmonized regulation 395.000 ok 20 Feb. end of Feb mid July Circulators and Loads (Old) 750.000 Null 3 New Klystrons 1.850.000 pending (expected mid June) expected end of June beginning of July mid November Waveguides 1.030.000 Circulators and Loads (New) 900.000 Mechanical Supports Open, simplified 50.000 90% expected mid July - mid October Klystron Drivers 80.000 end of June end September Klystron Repair and Guarantee Extension Open/Negotiated 195.000 80% 50% expected beginning of July Coaxials Minor Contracts 2 x 15.000 98% mid June

Scope Swap To be procured by ESS ERIC ESS prices Item Qty Unit Price (€) Total (€) TDK Power Supply 18 3386 60948 Heater Power Supply 6 18625 111750 Ion pump controller 12 1174 14088 Total (€): 186786 Additional possibilities (TBD):   Mechanical Supports 1 48000 MTCA Chassis 12 slots 35 4813 168455 Cables (RF) 5000 To be procured by ESS Bilbao Spare Item Qty Unit Price (€) Total (€) Klystron Driver 2 10000 20000 SSPA Modules 25000 50000 WR2300 Components 1 30000 RFLPS LLRF 45000 90000 Total (€) (TBD): 240000 Additional possibilities (TBD):   Human Resources for Installation ? Borrowing Circulator/Load/WG

Project Schedule See updated Gantt Chart