March 14, 2019
Updates Phase 1.1 Phase 1.2 Phases 1.3 and 2 Remaining items Construction activities Partner coordination Additional Funding Phases 1.3 and 2 Design Activities
Phase 1.1 Remaining Items Additional railing at Travis Gatehouse Installation underway Inlet lighting Trash screen at inlet pump station Work postponed until late 2019 Santa Rosa Pedestrian Crossing Work to begin next week
Phase 1.2 Construction Houston to Commerce Commerce to Dolorosa Concrete pours for channel bottom and walls 8-inch waterline installation under Commerce Street bridge Concrete pours for bridge rail curb and terminal ends Commerce to Dolorosa Concrete pours for building underpinning Drilled shaft installation Dolorosa to Nueva Commerce Street Bridge
Phases 1.3 and 2 Design
Phase 1.3 and Phase 2 Design Coordination with Mario Schjetnan underway Design team developing strategy to address direction from Bexar County Desired design completion October 2019
Partner Coordination SAISD administration building SARA/SAISD coordination Camaron Street construction Travis to Houston block to be completed in May Remainder to begin in late winter 2019 Alameda Theater Project team coordination Texas Public Radio Demolition started Coordination ongoing
Partner Coordination Commerce Street UTSA downtown campus expansion Construction Proposals under review Construction to begin May/June UTSA downtown campus expansion SPC design files shared Coordination meeting to scheduled Federal Courthouse (GSA) Coordination ongoing
Partner Coordination Executive Committee Next Meeting – March 15, 2019 David Smith, County Manager, Bexar County Lori Houston, Assistant City Manager, City of San Antonio Razi Hosseini, Interim Director, Transportation and Capital Improvements, City of San Antonio Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – March 15, 2019