IP8 aperture measurements (07:30-10:30)

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Proposal to change bunch length during physics fills to assess beam induced heating after LS1 M. Barnes, P. Baudrenghien, A. Burov, S. Claudet, S. Jakobsen,
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Summary of week 40 Machine Coordinators: G. Arduini, M. Lamont
Machine Coordinators: G. Arduini, J. Wenninger
Saturday :12 Stable beams fill 3351 Initial luminosity
Friday 15th June 01:11 Injection.
Wednesday September 14th
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary of Week 49 Machine coordination: Jorg Wenninger & Jan Uythoven
Monday fill with 1092 bunches (6 h stable beams)
LHC – Progress with Beam
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Monday – recovery from MKI flashover
Wednesday 31 October: Morning
Summary of Week 16 G. Arduini, J. Wenninger
Scrubbing progress - 09/12/2012
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Friday 31st August & night
LHC Morning Meeting - G. Arduini
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Finally.... We had to wait a long time.... We had many problems....
LHC Morning Meeting - G. Arduini
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Wednesday 10/5 Cryo recovery until 18:30
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday – Morning Fill 3265 stable beams since 1:31
Monday 24 October hours of 25ns MD
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
LHC Morning Meeting - G. Arduini
Scrubbing progress - 08/12/2012
LHC Morning Meeting - G. Arduini
Thursday – Morning Energy matching at injection with H CODs
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Monday :15 fill 3523 dumped by BPMs IP6
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Another Immortal Fill….
Monday 27th August & night
Wednesday 26 October 2011.
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Saturday 26 November 2011.
Thursday 10:00 Fill 1986 in stable beams.
HI2011 Commissioning Status
Monday 152 bunch operation summary
Presentation transcript:

IP8 aperture measurements (07:30-10:30) Aim: Measure IP8 aperture to determine possibility of having vertical external crossing angle bump from injection to allow polarity switch also for 25 ns beams. Data being analyzed. M. Giovannozzi, S. Redaelli, J. Wenninger 16/04/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Access (10:30 – 14:30) 10:30 Start access. Difficult start due to problem with the movement of the TI2 downstream TED  required strap of the corresponding interlock authorized by the DSO 11:30 – 15:20 Access in the machine and experiments: ALICE network switch (US25) 60 A PC RCBV27.L5B1/RCBH26.R3B2L, sub-converters of RQD.A12, RQD.A23, RQF.A23. Sublimation MKI2/8 in preparation of 25 ns run BLM diamond detector (point 7) ALICE, ATLAS (field off), CMS BGI TED TI2 BLM optical link in point 4 RB.A67 (QPS) 16/04/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 15:00 - 16:30. 50 ns beam checked by RF expert in PS and satellite enhancement ON 16:30 LHC ready to inject. No beam from SPS (coming out of MD) 17:40 Start injection and transfer line steering 18:40-21:40 Operational development. HOM heating studies with shorter bunches 16/04/2019 LHC Morning Meeting - G. Arduini

HOM heating vs. bunch length (B. Salvant et al.) Injected 1374 bunches with ~1.5e11 p/b on B1 and B2. Transverse emittance was blown up on purpose (screen in PS to SPS transfer line) From nominal value of 6 MV, RF voltage was increased to 14 MV, reduced to 9.5 MV, increased back to 14 MV and finally reduced to 6 MV in 0.5 MV steps Lifetime decreased with longer bunches. 16/04/2019 LHC Morning Meeting - G. Arduini

HOM heating vs. bunch length (B. Salvant et al.) Interesting observations but nothing critical detected so far when running for prolonged time at a bunch length between 1 ns and 1.1 ns. Significant difference between the beam spectrum during and after the ramp with the spectrum observed today with higher voltage at injection: Much lower second lobe (as expected). Preliminary observations on equipment (pending more detailed analysis by the experts): CRYO (F.A. Gruffaz): nothing significant on Q6.R5. Arcs: clear correlation with bunch length BSRT (E. Bravin/F. Roncarolo) Higher temperatures reached than during the flattening bunch MD yesterday. Vacuum pattern quite different. Visible change of slope observed when changing the bunch length 16/04/2019 LHC Morning Meeting - G. Arduini

HOM heating vs. bunch length (B. Salvant et al.) ALFA (S. Jakobsen) Clear correlation with bunch length. TOTEM (M. Deile/G. Bregliozzi) pressure excursions on many gauges near the pots (and sometimes on the other beam) observed when the bunch length was increased to 1.4 ns and when the beam was dumped. To be understood. Collimators (G. Bregliozzi/G.H. Hermelsoet/J. Uythoven) TDI (in parking position after injection): pressure increased slightly on TDI.4L2 at the end of the fill. Deformation rate looks quite large compared to previous fills. Nothing special on TDI.4R8 (deformation also similar to other fills). TCTVB: clear correlation with bunch length of all jaws (both 4L8 and 4R8) TCP.B6L7: steady increase without visible correlation to bunch length 16/04/2019 LHC Morning Meeting - G. Arduini

HOM heating vs. bunch length (B. Salvant et al.) Kickers (M. Barnes/G. Bregliozzi) - temporary pressure increase when bunch length decreases (VGI.161.5L2) - steady increase of tube temperature MKI8C - no clear correlation with bunch length (but heating time constants probably too large compared to bunch length steps). MKI8B magnet temperature the highest BGI (M. Sapinski) : The glowing of the Frisch wires, expected to appear during bunch length decrease, has not been observed. Beam size decrease observed during bunch length decrease. Simulations are ongoing. 16/04/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 22:48 Trip of RCBXH2.L5 while filling for physics. Access required for power converter repair 00:10 Access finished 01:30 Start ramp: 48% BLM threshold at beginning of ramp (enhanced satellites?) 02:16 STABLE BEAMS #3347. Initial luminosity ~7.3x1033 cm-2s-1. Initial ALICE luminosity still too low (5.5x1030cm-2s-1) 16/04/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Plan Dump at 12:00 Fill with mixed pattern standard/high brightness beam (compression/merging). Filling pattern: 50ns_66b_60_0_0_36bpi3inj In the mean time further enhancement of satellites in ALICE Late afternoon: Fill for physics 16/04/2019 LHC Morning Meeting - G. Arduini