Thursday 26th July 13:21 Fill 2880 beam dumped

Slides:



Advertisements
Similar presentations
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Advertisements

06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
LHC Status Fri Morning 3-June
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
LHC Status Tue Morning 22-Aug
Wednesday 3rd October - morning
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Friday 15th June 01:11 Injection.
Wednesday September 14th
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
LHC progress Week 30 summary 30th July 2012
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday fill with 1092 bunches (6 h stable beams)
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
LHC Morning Meeting - G. Arduini
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Wednesday 31 October: Morning
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Mike Lamont, Jorg Wenninger
Wednesday 8th August & night
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Summary week 29 VdM scans Luminosity production
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Chromaticity can make a difference…
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
Saturday – Morning 7:36 beams dumped
Friday Morning 7:30 injection for fill 2908
Wednesday 03/11 – The Plan Finish electron-cloud program:
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
LHC Morning Meeting - G. Arduini
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
LHC Morning Meeting - G. Arduini
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday 3rd November - morning
Thursday – Morning Energy matching at injection with H CODs
LHC Status Tue Morning 22-Aug
Thursday 22 September 2011.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Thursday
Saturday 24 September 2011.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday 15th February - morning
Tuesday – Morning and Evening
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday morning / afternoon
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Monday 152 bunch operation summary
Tuesday
Presentation transcript:

Thursday 26th July 13:21 Fill 2880 beam dumped triggering of heaters on inner triplet R1, closing vacuum valves 118 pb-1 in 9h17m 13pb-1 for LHCb Initial lumi: 5.5 cm-2s-1 From A.Verweij's analysis it looks like RQTX1.R1 tripped and that caused the increase of Ures on the triplet. We contacted H.Thiesen who will check the PC-PM signals… QPS SEU suspect – Reiner Denz 27-07-12 LHC status

Thursday afternoon: access Cryogenics informed as about a problem with a valve at D4L5 on the DSL line for the main circuits of S45. This valves closes slowly (5%/day) leading to a temperature increase. An intervention needs to be done before tomorrow PM. Access while triplet investigations ongoing Given the current situation we decided to prepare access to the tunnel now (close to triplet L5). RP has been informed and will meet cryogenics in about 20min. at PM56. 27-07-12 LHC status

Thursday evening 17:40 Injection physics beam Injection optimization by Chiara and Wolfgang 20:20 injecting for physics Cooling problem effecting MSE – SPS Ring 1 – booster problems 800 bunches in beam 1, we stop beam2 and finish beam 1 as requested by ALICE Emittances not brilliant – LHC takes what it can get 21:15 Stable beams #2882 Initial luminosity: Smooth – lifetime dips to around 1 hour on beam 2 going into collisions 27-07-12 LHC status

Thursday evening 21:41 Trip of LHCb dipole power converter BRIDGE B COOLING :FAULT 22:50 ramping up LHCB DIPOLE 23:15 re-injecting 00:40 Flat top Trimmed B2H tune by 0.002 01:01 end squeeze Beam 1 horizontal goes unstable shortly after Trimmed tune B1H by 0.001 Settings issues…. Bad lifetime both beams – beam blown up 01:40 Stable beams . Beams dumped by temperature of TCP_B6L7_B1 27-07-12 LHC status

Friday morning COLLs temperature. Thresholds have been increased by 15 degrees (set to 95). To allow next fill to progress with problems – thanks Stefano 03:00 re-injecting 03:45 OFSU crash on flat-top – thanks Laurette for helping to sort things out 04:30 Stable beams Initial luminosity 5.4e33 cm-2s-1 Moderate bunch currents 27-07-12 LHC status

BBQ amplitude 27-07-12 LHC status

B1H 27-07-12 LHC status

B2H 27-07-12 LHC status

Beam size Federico Roncarolo 27-07-12 LHC status

Beam sizes before/after TS Federico Roncarolo You see that indeed B2 H and V seems to have changed, even though the BSRT meas. are biased by a larger noise (not optimized settings that I think don't introduce systematics on the average, but to be checked further). 27-07-12 LHC status

Temperature calibration BPMS - WIP A temperature calibration was attempted in point 6 on the interlocked BPMS channels Temperature compensation in interlocked channels showed a big excursion w.r.t the reference orbit. The temperature factors have been manually reverted to 0 (so temperature compensation disabled). Note: The temperature compensation only affects to the orbit published (not to the interlock process). E. Calvo. 27-07-12 LHC status

Incoming – low emittance test 2 fills (but only if first fill looks OK) 50ns_38b_32_0_0_32bpi2inj 50ns_262_256_0_128_128bpi3inj We'd plan for stable beams if things look OK (not guaranteed) - wouldn't keep them in for longer than 1 hour. Note nominal intensity: ~1.1e11 - putting in reasonable numbers gives pile-up comparable with normal. 27-07-12 LHC status

Gianluigi, Elias, Mike, Jorg, Bernhard BS Gianluigi, Elias, Mike, Jorg, Bernhard Step 0: Check that we have the sign of the octupoles we think (ABP) Reproduce the tune footprints with both polarity of the octupoles during the squeeze (ABP) Step 1: 1) Measure chromaticity through the whole cycle (up to collision with pilot beams – non colliding with chirp, collimators at injection settings, momentum modulation of ~2x10-4) 2) Correct chromaticity to 1-2 unit accordingly Step 2: 3) Reduce the gain of the damper (at least during end of ramp and squeeze initially) by factor 2/4/10) In parallel to verify the feasibility of running with opposite polarity of the octupoles a few end-of fill tests will have to be done to optimize the strength of the octupoles and possibly the working point that might have to be changed Based on the above results we will have a more solid background to see next steps (octupole strength and polarity and operation with larger chromaticity at high damper gain) 27-07-12 LHC status