Scott McFarlane & Richard Merifield

Slides:



Advertisements
Similar presentations
Christchurch Town Hall for Performing Arts
Advertisements

Failure Case Study of Construction at a Solid Waste Site K. Madhavan, Ph.D., P.E., Dept. of Civil & Env. Engineering Christian Brothers University Memphis,
1 Application and Analysis of Helical Piers in Frozen Ground He Liu, Ph.D., P.E. Daniel Schubert, P.E. Hannele Zubeck, Ph.D., P.E. Sean Baginski.
Investigation of Consolidation Promoting Effect by Field and Model Test for Vacuum Consolidation Method Nagasaki University H.Mihara Y.Tanabasi Y.Jiang.
FIXED MARINE STRUCTURES
4.3 STONE OR SAND COLUMNS IN SOFT CLAYEY MATERIALS :
SOFT SOIL (PROBLEMS & STABILISATION METHOD) Session 2 - 7
INTRODUCTION Session 1 – 2
Design Parameters.
Project details • New headquarters for HKSB
  AN-najah National University Faculty of Engineering Civil engineering Department Prepared by: Eng. Imad A. F. Jarara’h. Submitted.
1 Asia Managing Geotechnical Risk Learning from the Failures “Issues related to the use of Numerical Modelling in Design of Deep Excavations in Soft Clay”
Session 17 – 18 PILE FOUNDATIONS
SEMBODAI RUKMANI VARATHARAJAN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING FOUNDATION ENGINEERING BY KARTHIVELU.
TOPIC 2: TYPES OF FOUNDATION
Foundation Engineering CE 483
Chapter 2b Foundations Shallow & Deep Foundations.
Mata kuliah: S0892 – Ground Improvement Method Tahun: 2010 Case Study Session
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Thomas F. Joos, P.E. Civil/Structural Engineer BNL Plant Engineering Division May 8, 2007 NSLS-II Conventional.
Reference Manual Chapter 9
Investigation of the causes of movement and damage to an office building in the UK founded on Carboniferous Coal Measures mudstone. William J Marshall.
Team Central Winter Presentationslide 1 of 65 Winter Presentation AEC Global Team Class 2002 Winter presentation Team Central.
Role of Foundation Consultants in optimizing time and cost in large projects – Case Studies Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and.
BCM 210 Foundation Issues- Fall 2000 refer to Allen Text
OMAE 2009 Honolulu, HI - May 31 to June
4.4 SOIL NAILING SOIL NAILING IS A REINFORCEMENT METHOD TO REINFORCE THE GROUND WITH STEEL BARS OR STEEL BARS IN GROUT FILLED HOLES. IT IS MAINLY USED.
LONG TERM GEODETIC MONITORING OF THE DEFORMATION OF A LIQUID STORAGE TANK FOUNDED ON PILES P. Savvaidis Laboratory of Geodesy Dept. of Civil Engineering.
David Faux Student ID: September 2015
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
Modern GROUND IMPROVEMENT TECHNIQUES FOR HIGHWAYS
Foundation Loads Dead Load Live Load Wind Load
SITE INVESTIGATION.
DESIGN AND ANALYSIS OF DEEP FOUNDATION WEEK 10 DESIGN OF BORED PILE DESIGN OF GROUP AND RAKE PILE PILE SETTLEMENT.
BUILDING CONSTRUCTION
Engineering Presentation. Basic Soil Mechanics Soil type classification Gravel, sand, silt, clay Soil strength classification Granular soils (sand and.
PILE FOUNDATIONS UNIT IV.
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
SOIL MECHANICS AND FOUNDATION ENGINEERING-II (CE 311)
GLE/CEE 330: Soil Mechanics Settlement of Shallow Footings
SOIL MECHANICS AND FOUNDATION ENGINEERING-III (CE 434)
Deep Replacement Presented by: M. Taromi
Soil mechanics and foundation engineering-III (CE-434)
Direct Shear Test.
Soil wetting patterns under porous clay pipe subsurface irrigation A. A. Siyal 1 and T. H. Skaggs 2 1 Sindh Agriculture University, Tandojam, Sindh, Pakistan.
Settlement prediction for deep foundation piles using artificial neural networks Arshiya ABADKON1*, Muhammed Ernur AKINER1 1Bogazici University, Civil.
GROUND IMPROVEMENT BY P. VENKATESH REDDY. WHY GROUND IMPROVEMENT IS NECESSARY? Subsurface conditions can vary greatly within a single job site and the.
Site Investigation and Field Tests
Use of Modern Retrofitting Techniques in Udaipur Station Building
Soil Improvement.
Jet grouting underpinning of a building on a marl embankment platform
Fall 2016 ASSE 4311: Learning Outcome Assessment III/Civil Engineering 18/1/2017 Final Presentation Structural & Geotechnical Design of a Hotel in the.
GROUND IMPROVEMENT TECHNIQUES
GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE 12 TOPIC : 4
Bridge Pile Foundation Evaluation for a Soil Remediation Project
Ground improvement techniques
CFAC Review NSLS-II Conventional Facilities Update
Aspek Geoteknik.
Soil & Site Investigation
Aspek Geoteknik.
MATERIALS AND CONSTRUCTION I
Arch205 Materials and building construction 1 foundation
Christopher R. McGann, Ph.D. Student University of Washington
Arch205 building construction foundation
GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE 10 TOPIC : 3
Foundations Four Basic Types Footings Piers Pilings Slabs
REVISION 1 1. Foundations.
Pavement materials: Soil
PAT GEOTECHNIC INTRODUCTION TO GEOTECHNICAL ENGINEERING.
Graduation Project Bracing system for deep excavation.
BUILDING CONSTRUCTION Foundation
Presentation transcript:

Scott McFarlane & Richard Merifield Ground Improvement Project – Large water storage tanks Carrington NSW Douglas Partners’ Technical Seminar 2019 Scott McFarlane & Richard Merifield

Background Douglas Partners are a trusted consultant to PWCS; PWCS needed to upgrade their stormwater management system; PWCS engaged GHD as the design consultant (civil, hydraulic, mechanical, electrical & geotechnical); PWCS provided GHD previous nearby geotechnical data (by DP) to assist GHD with conceptual geotechnical ground improvement options for tank; PWCS provided DP the concept geotechnical design options by GHD to develop scope of works (i.e. data report).

Stormwater Management System Manage stormwater to minimise off-site uncontrolled discharge; Above ground steel tanks; Supported on concrete slab; Tank 1 – 20 m dia, 11 m high, 5Ml; Tank 2 – 32 m dia, 11 m high, 8 Ml; Tank 3 – 32 m dia, 11 m high, 8 Ml; Pipeline to connect into existing pond. Trench to be excavated adjacent to rail line.

Previous Data Fill Soft Clay VL Sand Clay / Silt and Sand Dense Sand -0 Soft Clay VL Sand Clay / Silt and Sand -10 Dense Sand Stiff Clay -20 Very Stiff to Hard Clay -30 Rock -40

GHD Concept Ground Improvement Options Do nothing Preload CFA piles Driven Piles Cutter Soil Mixing (CSM) Design Details - 8 m high preload (3 month wait) 600 mm dia; Installed to >35 m, 3 m c/c 400 mm sq; 2.5 m c/c CSM to 35 m 15% area replacement ratio Estimated Post Construction Settlement (mm) 700 250 to 300 5 to 10 With preload: 20 mm Without: 100 mm Constraints Settlement Space, time Depth of piles, ASS Depth of Piles PWCS – very risk adverse with any ground improvement (past experience)

DP Difference

DP Revised Scope Investigation – Provide data to GHD to undertake Design; Parallel modelling to compare with GHD design; Review technical specification; Review tenders methodology; Review preferred tenderers design, QA and alternate design.

Investigation Geotechnical Risks Soft clay layer? Sand stratum? Deeper clay? Ground water? Rock strength?

Subsurface Profile Tank 1 – 20 m dia Tank 2 – 32 m dia

Design & Analysis

Tank Design Loads Design Life = 50 years

Serviceability Criteria Max settlement at centre ≤ 100 mm; Max settlement around perimeter ≤ 100 mm; Max settlement between centre and edge ≤ 40 mm; Max edge to edge tilt ≤ 30 mm; Differential settlement ≤ 1 in 500.

Conceptual Time-Settlement Behaviour

Initial Ground Improvement Options No Ground Improvement; Piles with Pile Transfer Layer (PTL); Deep Soil Mixing (GHD preference); Tank Interaction (3D analysis). Max Total Settlement: Case 1 – 71 mm Case 2 – 53 mm Max Total Settlement: Case 1 – 80 mm Case 2 – 60 mm Max Total Settlement: Case 1 – 300 mm Case 2 – 225 mm Max Total Settlement: Case 1 – 76 mm

Initial Tender Review – Mix Soil Option Large QA component in design spec by GHD: Sampling and lab mix design to determine strength properties; Additional CPTs; Trial sites (curing time); Core sampling of mixed soil; Lab testing during mixing; Column Penetration Test or Pull-out resistance test. 1 m preload.

Alternative Tender – Rigid Inclusions Concrete Injected Columns (CIC); Controlled Modulus Columns (CMC); Controlled Stiffness Columns (CSC).

Using the result from b), a larger model was generated. A “unit cell” axisymmetric model consisting of the CSC and its surrounding soils was analysed; Based on the results from a), an equivalent set of soil properties was generated; Using the result from b), a larger model was generated. The analysis of the CSC ground improvement option was undertaken using 2D axisymmetric finite element analyses in Plaxis 2D. More specifically, the following analyses steps were undertaken as part of the CSC assessment: A “unit cell” axisymmetric Plaxis 2D model composed of the CSC and its surrounding soils was created and the settlements versus time estimated. The unit cell model includes the CSC (diameter, spacing) and the load transfer platform (including thickness) as shown in Figure a. Based on the unit cell results from (a) for each tank location and the adopted CSC/Load Transfer Platform properties, an equivalent set of soil properties (stiffness, permeability) for the composite soil/CSC matrix is established that match the consolidation response observed in (a) (Figure b). Using the parameters established in (b) for the composite soil/CSC matrix, a larger 2D axisymmetric Plaxis 2D model composed of the composite soil/CSC zone and the surrounding soils at each tank location was created and the settlements versus time estimated. A sample Plaxis 2D model is shown in Figure 6.   Plaxis 2D Unit Cell Model of CSC

Plaxis 2D axisymmetric model (half model) with equivalent composite CSC/Soil Zone

Sustained Constant Load – 120 kPa Tank Total Settlement mm Sustained Constant Load – 120 kPa Keller Prediction DP Prediction Tank 1 (20 m dia) 74 62 Tank 2 (32 m dia) 86 71

QA During Construction Proof rolling & Plate Load Testing rather than density testing of working platform; Additional CPTs; Concrete testing (by others); Review of concrete takes & penetration depths; Plate load testing of installed columns (similar to pile test)

Plate Load Testing – Working Platform

Installation of Trial Columns

Installation of Trial Columns

Production Rate of Columns Stats No. Metres per day No. of Piles per Day Range 72 – 400 8 – 53 Average 264 35

Column Load Testing (10 MPa – 7 days)

Typical Column Load Test Result Column Diameter – 0.4 m Column Depth – 7.5 m Total No. of Column Tests – 9 Range of Max Deflection – 2.1 to 28 mm

Thanks to All Involved with this Project