SNS Commissioning Mike Plum

Slides:



Advertisements
Similar presentations
ISIS Accelerator Division
Advertisements

C. Rossi – L4 Project Meeting 3 March 2011 Status and Plans of 3 MeV Test Stand.
Experience with Bunch Shape Monitors at SNS A. Aleksandrov Spallation Neutron Source, Oak Ridge, USA.
Space Charge Issues in the SNS Linac and Ring
Thomas Roser Snowmass 2001 June 30 - July 21, MW AGS proton driver (M.J. Brennan, I. Marneris, T. Roser, A.G. Ruggiero, D. Trbojevic, N. Tsoupas,
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Tuning an Accelerator for 1 MW C. Peters WAO 12 August 8 th, 2012.
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
F Project X Overview Dave McGinnis October 12, 2007.
EDM2001 Workshop May 14-15, 2001 AGS Intensity Upgrade (J.M. Brennan, I. Marneris, T. Roser, A.G. Ruggiero, D. Trbojevic, N. Tsoupas, S.Y. Zhang) Proton.
J-PARC Accelerators Masahito Tomizawa KEK Acc. Lab. Outline, Status, Schedule of J-PARC accelerator MR Beam Power Upgrade.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
Status of REX and Commissioning with Beam Dr. Jose Alberto Rodriguez, BE-OP-PSB (167538)
Managed by UT-Battelle for the Department of Energy SNS BLM System Overview Detectors, Measurements, Simulations Alexander Zhukov Saeed Assadi SNS/ORNL.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Alexander Aleksandrov Oak Ridge National Laboratory
PROTON LINAC FOR INDIAN SNS Vinod Bharadwaj, SLAC (reporting for the Indian SNS Design Team)
Managed by UT-Battelle for the Department of Energy Using Online Single Particle Model for SNS Accelerator Tuning Andrei Shishlo, Alexander Aleksandrov.
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
Project X Injector Experiment (PXIE) Sergei Nagaitsev Dec 19, 2011.
February 2010 ALBA Synchrotron Light Source Francis Perez.
ICFA-HB 2004 Commissioning Experience for the SNS Linac A. Aleksandrov, S. Assadi, I. Campisi, P. Chu, S. Cousineau, V. Danilov, G. Dodson, J. Galambos,
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
0 Plenty Energy Clean Environment Healthy Life Commissioning and Initial Operation of the KOMAC 100-MeV Proton Linac KOMAC / KAERI Kyung-Tae Seol
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
ESS Linac Modifications for ESSnuSB Dave McGinnis Chief Engineer / Accelerator Division August 27, 2014.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
A Few Pointers from the Linac4 Beam Commissioning of Warm Linac Yngve Levinsen Beam Physics Section 05/02/16.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
F A Fermilab Roadmap Dave McGinnis May 28, f Fermilab Roadmap - McGinnis Timelines  Divide the road map into three parallel paths  ILC - Energy.
Beam losses and collimation at the Oak Ridge Spallation Neutron Source by Mike Plum Beam losses and collimators in transfer lines workshop Lund May 13-14,
ORNL is managed by UT-Battelle for the US Department of Energy SNS beam loss and control By M. Plum ICFA mini-workshop on beam commissioning for high intensity.
SNS linac beam commissioning By Michael Plum Spallation Neutron Source Oak Ridge National Laboratory ESS Workshop on beam commissioning April 8-9, 2014.
ALBA RF Systems Francis Perez.
HISTORY OF SNS DESIGN AND TECHNOLOGY CHOICES PROJECT X WORKSHOP NOVEMBER 12-13, 2007 R. KUSTOM.
Brian Drendel May 21, Stacking Pbars stacked: E10 Time stacking: Hr Average stacking rate: E10/Hr Uptime Number of pulses.
Machine Protection Systems (MPS) Arden Warner, and Jim Steimel Project X Machine Advisory Committee March 18-19, 2013.
HB2008 – WG F: 27 Aug. S. Childress – Diagnostics_2MW 1 NuMI Beam Diagnostics and Control Steps to 2 MW S. Childress Fermilab.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning experience of SNS Ring By M. Plum ICFA mini-workshop on beam commissioning.
FFAG Studies at BNL Alessandro G. Ruggiero Brookhaven National Laboratory FFAG’06 - KURRI, Osaka, Japan - November 6-10, 2006.
PSI, Zurich February 29 – March Session classification : Accelerator Concepts Tuesday, March 1, 2016 Summary Vyacheslav Yakovlev Fermilab, USA.
ESS Front End diagnostic
Operation Status of the RF Systems and Taiwan Photon Source
Cost Optimization Models for SRF Linacs
UK Neutrino Factory Conceptual Design
Challenges of Dual Harmonic RF Systems
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Uppsala Commitment to ESS and FREIA Planning
Overview and System Design for ESS LLRF Systems
High Intensity Challenges
ELENA Overview and Layout Start of ELENA Commissioning Next Steps
Operating Experiences at SNS
1- Short pulse neutron source
CSNS Accelerator Control and Beam Instrumentation JIN Dapeng, XU Taoguang … June 9, 2015
SNS Timing System EPICS Workshop April 28, 2005 Coles Sibley
Revised Commissioning Strategy
CEPC RF Power Sources System
LINAC4 commissioning plans etc.
Advanced Research Electron Accelerator Laboratory
EPICS Meeting March 12 – 14, 2008, Shanghai, China
RF systems introduction
(Beam) Commissioning Plan
RF introduction Anders Sunesson RF group leader
Radiation fields During 1st stage beam commissioning
SNS-PPU upgrades the existing accelerator structure
RF system for MEIC Ion Linac: SRF and Warm Options
Presentation transcript:

SNS Commissioning Mike Plum Ring Systems manager for the Power Upgrade Project Lund, Oct. 16-17, 2018

SNS Accelerator Complex 150 kW injection dump Collimators Front-End: Produce a 1-msec long, chopped, H- beam 1 GeV LINAC Accumulator Ring: Compress 1 msec long pulse to 700 nsec Extraction Injection RF 2.5 MeV 87 MeV 186 MeV 387 MeV 1000 MeV RTBT Ion Source 7.5 kW beam dump HEBT RFQ DTL CCL SRF, b=0.61 SRF, b=0.81 Design parameters Kinetic Energy [GeV] 1.0 Beam Power [MW] 1.4 Repetition Rate [Hz] 60 Peak Linac Current [mA] 38 Linac pulse length [msec] SRF Cavities 81 7.5 kW beam dump Liquid Hg Target

SNS beam power history Beam power administratively limited by target most of this time 1.4 MW ~3 y to 1 MW Availability for last fiscal year was 94.5% Plan to operate at 1.4 MW from now until Power Upgrade Project

Commissioning Timeline 2002 2003 2004 2005 2006 Front-End DTL/CCL SCL DTL Tank 1 DTL Tanks 1-3 Ring Target Total commissioning duration was about 3 years 7 months

How we did it Each section of the accelerator complex had an assigned physicist (area manager) Responsible for the overall commissioning and performance of that section Four areas: Front end, warm linac, cold linac, HEBT/Ring/RTBT Front end later combined with warm linac to make one area Commissioning shifts were staffed 24/7, 2 physicists per 8 hour shift Technical support called in as needed Commissioned with beam in 7 stages (5 for linac, 2 for Ring and target) over ~3.5 years Front End through CCL-3 “control room” was a few computer stations in the Front End building, hard hats and safety shoes were required

How we did it (cont.) Commissioned DTL-1 (7.5 MeV output energy) with a special diagnostics beam line (D-plate) that had a high-power beam stop. We used it to demonstrate 1.0 MW equivalent power (26 mA pk, 650 us, 60 Hz) in 2003. After that did not return to 1 MW beam parameters until 2009. After initial low intensity commissioning, large fraction of accelerator physics time was spent developing low-loss tunes for the next step in beam power

Evolution of PPS enclosures Injection Dump 150kW HEBT-RTBT-Target PPS 3.0 HEBT -Ring Gate PPS 2.0 End of Linac - HEBT Gate PPS 1.0, 1.2 Extraction Dump 7.5KW DTL Tank 1 and DTL Tanks 1-3 PPS 0.4/0.5 Linac Dump 7.5 KW

How long did it take (how much time did we spend)? Section commissioned days actual* Front end 33 DTL 1 47 DTL 2-3 12 DTL 4-6 and CCL 1-3 135 (incl. ~40 days of planned shutdown) CCL 4 thru SCL 63 (incl. ~13 days of planned shutdown) *Some times could have been shorter. For example we spent a large amount of time studying the beam halo, and some of this work never bore fruit. On the other hand, this could be seen as time well spent gaining experience with the machine.

DTL and CCL warm linac commissioning Temporary high-power (1.4 MW equivalent) beam dump for DTL-1 Temporary low-power (50 us, 1 Hz) dump for DTL 2-3 After that only internal / permanent dumps For DTL we had two methods prepared to set cavity phases and amplitudes Delta-t method Energy degrader method Later developed phase scan signature method (PASTA), and today we use a variation of the PASTA method For CCL we had one method prepared Today we use a variation of the PASTA method

SCL commissioning Initially commissioned at 4.2 and 2.1 deg. K, but cryo-plant at 2.1 K was not stable at the time Cavity amplitudes set to maximum stable gradients – much different than design gradients Determining cavity phase set points was a lot easier than expected, partly due to the large acceptance of the SCL Had two methods prepared: Beam Induced Signal (Drifting Beam method) and Phase Scan. Phase Scan method worked great, no need to further develop Drifting Beam method. Operated at 4.2 K from 2005 to 2007 to give time for cryoplant adjustments needed for stable 2.1 K operation, and also because 4.2 K met operations needs during that time

What we should have done differently During commissioning many system adjustments and modifications were needed to get everything working together. The rapid pace did not accommodate careful reviews of the modifications. Modifications to the Machine Protection System should have been more carefully reviewed. Low pass filters were added to some MPS inputs to help with false trips due to noise. This ended up slowing down the response time of the MPS, which we didn’t realize at the time, and which caused some (temporary) performance degradation due to the increased beam loss.

What worked well for us Having a physicist assigned to each section of the accelerator Thorough magnet measurement program allowed “dialing-in” magnet currents and immediately transporting beam – first shot through HEBT hit view screen in ring injection section (didn’t do as well with first shot to neutron target) Good set point reproducibility in the magnet power supplies. Physics apps were integrated with the on-line model and the control system, and well developed before start of commissioning Physics apps written by commissioning team members Commissioning the machine in 7 stages Good set of beam instrumentation (lots of beam position, beam profile, beam phase, and beam loss monitors) General philosophy of getting low intensity beam to go as far as possible as soon as possible

Some lessons learned Equipment checkout with beam takes a large fraction of the time Beam instrumentation RF & LLRF Control system Machine Protection System The pace of the commissioning is determined by equipment issues. If all the equipment worked as designed from day one it would only take a few days to commission. Need to closely involve hardware experts, thoroughly test hardware as much as practically possible before commissioning Need to prioritize equipment readiness in event of limited resources (e.g. don’t need multipole corrector magnets for initial commissioning) Low power commissioning is relatively easy. High power operations brings unexpected surprises. Be careful with modifications to critical systems (e.g. MPS system)

Power ramp up (the commissioning after the initial commissioning) Two schools of thought here: Keep the beam power low, get all the bugs worked out, don’t endanger beam availability, don’t activate beam line components until everything is working well Aggressively push beam power to identify weak components and to solve high-power problems before the users expect/demand high availability At SNS we choose the latter, and we are glad we did At 1 MW we paused to focus on beam availability. Budget and then target problems caused us to stay at 1 MW for longer than we had hoped.

Summary The pace of commissioning and beam power ramp was determined by the hardware (RF modulators, target, RFQ, ion source, beam instrumentation) Accelerator physics worked 24/7, with support from technical experts as needed. Sometimes this was not very efficient because equipment limited the rate of progress.

Commissioning: A Period of Ups and Downs Beam commissioning can be extremely frustrating and is hard work (long hours) But it is ultimately extremely rewarding Enjoy it

Thank you for your attention!

Backup slides

PPU system upgrades INJECTION DUMP Re-assess 150 kW power rating Add view screen imaging system RING EXTRACTION Add 2 more kickers to the existing 14 kickers. But there is another way: to upgrade the voltage capability of the existing 14 kickers -- prototype testing is in progress. RING INJECTION Replace 2 chicane magnets Replace inj. dump septum magnet Upgrade 8 inj. kickers Add quad magnet to inj. dump beam line WARM LINAC KLYSTRONS Upgrade DTL klystrons 3, 4, and 5 from 2.5 MW to 3.0 MW SCL Add 7 cryomodules (28 cavities) Add 28 klystrons and 3 modulators Future beam line to second target station STS STUB Build first part of beam tunnel to future second target RING UTILITIES Increase water cooling capacity TARGET Increase power capability from 1.4 to 2.0 MW

Design vs operation SCL gradients HOM HOM Turned on Conditioning Tuner problem Tuner HOM+Conditioning Design gradient (from R. Campisi, June 2006)