Coordinating with Project Managers

Slides:



Advertisements
Similar presentations
Why Do People Join Groups?
Advertisements

Coordinating with Project Manager Cindy Kowalski, PMP Utility Coordinator, Parsons December 2013.
Teamwork C.Eng 491 Fall 2009.
Coordinating with Project Manager Cindy Kowalski, PMP Utility Coordinator, Parsons November 19, 2013.
Troop 1600 Junior Leader Training
10 Aug 2010 ECE/BENG-492 SENIOR ADVANCED DESIGN PROJECT Meeting #2.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT August 21, 2014.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Contract Training Class I
STEP 4 Manage Delivery. Role of Project Manager At this stage, you as a project manager should clearly understand why you are doing this project. Also.
Construction Review LaVon M Marshall Greenfield District Utility/RR Engineer, INDOT June 11, 2015.
n Taking Notes and Keeping a Journal n Listening Skills n Working Together n Managing Your Time.
Coordinating with Project Managers Cassie Reiter, P.E., ENV SP Utility Coordinator/Project Manager CMT Engineers and Consultants June 2016.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
IDM Chapter 104 Utility Coordination Gail Lee Highway Utility Engineer, INDOT June 21, 2016.
A New Paradigm for Utility Coordination Kenny Franklin VP of SUE Development Blood Hound.
Chapter 1 My Role on the Team. Chapter 1 My Role on the Team.
Preparing and Delivering Effective Performance Reviews
Managing Time, Tasks and Yourself
Project Management Business Management.
Continuous Improvement Project (A Guideline For Sponsors)
Pick Ups & Job Management
Study Tips For A Great Education In Math.
The Service Challenge – xxxxx Team
ICE Innovation, Collaboration and Execution
Quiz: How Are Your Meetings
Managing the Bowl for Kids’ Sake Committee
Chapter 16 Participating in Groups and Teams.
ENTERPRISE FACULTY What is Enterprise?.
Building the foundations for innovation
“Plan the work. Work the plan.” ~ Old Saying
Multi Rater Feedback Surveys FAQs for Participants
Multi Rater Feedback Surveys FAQs for Participants
ENGM92 Communication Unit 3
Case Study: The Accounting Software Installation Project
ITPD ISSUE MANAGEMENT PROCESS SEPTEMBER 5, 2008
Advanced Invitations.
Organizations, Constraints & Projects
Top Ten Soft Skills Employers Seek In Candidates
Responsible, Accountable, Consulted, Informed
IS&T Project Reviews September 9, 2004.
Stakeholder Communication
Troubleshooting a Task
General comments: These projects are locally owned and the LPA should be involved and informed throughout the project. The project agreement is between.
BUS 1040 Project Management Wk 13, April 5-9, 2004 Final Exam review
Engineering Project Project Management Project Management.
How to keep your Enterprise GIS Project on Track
Research Phase, Indiana 811, Initial Notice, Verification
SUPER SUCCESS SERIES TIME MANAGEMENT VOL. 1
Killer Project Management Best Practices
M253 Team working in distributed environments
Roles and Responsibilities of a Project Manager
Project Management How to access the power of projects!
Bulloch Information Session
Interpersonal/Social Skills
A Paradigm for Utility Coordination
Managing Customer Expectations
105 Indiana Administrative Code Article 13
Utility Coordination OBJECT FOR THIS MODULE: Learning how soft sills contributes to a successful Utility Coordinator.
BUS 4017 Project Management Wk 13, April 5-9, 2004 exam review
Quarterly Business Review Template
Drawing of Sufficient Detail (DOSD)
Contents Fundraising Responsibilities Fundraising Facts and Figures
Project Management.
Project Overview.
(Project) SIGN OFF PROCESS MONTH DAY, YEAR
Project management Initiative & Self Learning Confidence in leadership
How to Conduct Effectively
Project Manager / Utility Liaison
Presentation transcript:

Coordinating with Project Managers

Coordination The organization of the different elements of a complex body or activity so as to enable them to work together effectively Different Elements Work Together Effectively Construction plans and design project have so many different elements to them – grading, drainage, paving, subsurface elements, utilities, lighting signals, and much more. In order to have a successful project, every element must work together effectively. To have that, we need coordination Everyone knows where everything goes!!

Objective Understand soft skills needed for utility coordination 2. Discuss the Utility Risk Report and Project Funding to give an understanding of how these tools are used by the Utility Coordinator (UC) and PM to ensure project success. Soft skills for coordinating with PM: recognize there are more than several soft skills and ask the audience to name a few. Writing, effective communication, creative thinking, flexibility, collaboration, listening, leadership/taking initiative 2) Utility risk report and project funding is more technical; so if the soft skills are not your thing, just hang in there. This is not a utility status report; it’s a summary of current risk to the project arising with utility coordination Notice the objective of the PM is project success! Your success as a utility coordinator, contributes to the project success

Soft Skills Writing Effective Communication Creative Thinking Flexibility Collaboration Listening Leadership – Taking Initiative

Effective Communication Who is your customer? Is it the Project Manager within your company? Is it the project manager for the prime designer? Is it the INDOT project manager? What is important to them? How can you as a utility coordinator help them succeed? Where do they need to get the information to do their job?

Effective Communication Methods for staying in contact depend on the situation; e-mail is a good form of communication, but at times picking up the phone and talking can resolve an issue best. Can anyone give me an example/reason of when e-mail is better or when a phone call is best? E-mail when giving facts Phone when needing to explain a situation and have dialogue back / forth Meetings can be best way to communicate when needing to share a lot of information and/or with other people. (examples: 1) Kickoff meeting; 2) Coordination between multiple affected utilities professionalism in meetings – determine who takes the leadership role, build the relationship, find common goals You will need to actually call people, on the phone, and talk with them. Not texting, not just e-mail, but actual verbal conversation! Stay in contact Many ways to do so – email, meetings, and yes, even by phone!

Effective Communication Ask questions…the more information you have, the better the project will be. You will be able to coordinate better if you understand what is happening with the project, with each utility, with ROW, etc. What is scenarios…ask about that too Ask questions – make sure you understand the project specifics. If unsure, ask; chances are others are wondering the same thing.

Effective Communication Clarify – “You need utilities moved by x date” “You will talk to the DM to see if the drainage can be adjusted to avoid the water main” You need to know where the gas company is relocating to before you can determine your relocation plan

Effective Communication Be responsive – aggravating if PM tries to contact you and you are not available and do not respond in a timely manner. Try to return calls same day. Reply to e-mails (do not ignore). Even state “I received this, but I need some time to look into it and will get back with you soon” Remember the PM is your customer. You want the project to succeed….to do this you must be responsive!

Organization A multi-tasking requirement Different utility companies Project schedule Project design elements Files Documentation To-do Lists Status reports Utility schedules Utility Coordinators are multi-taskers…you must juggle multiple utility companies for every project; communicating with different representatives regarding various stages of coordination. Organize e-mails in Archive folders like you would hard copy files; a separate folder for each project and separate sub-folders for each utility. So that it is easy to go back and find an e-mail. Keep hard copy documents organized and filed away in easy to access file cabinets located nearby. Create to-do lists or use the Task feature in Outlook so you keep track of the many activities and ensure nothing gets overlooked. Create status reports that help you track the process and report back to the PM. Can also be used to measure the process. Agreement tracking Work Plan process from time it is submitted by the utility to the time the work plan approval letter is sent to the utility company

Attitude is everything Be the go-to person, available, ready to respond, use your skills and abilities to respond to both office and field situations. Includes: Treat your PM as your customer Have a positive attitude Be willing to think there could be solutions to a given problem. Be open-minded. No idea is wrong…so think outside the box. Responsiveness, follow through and timely are all connected; one implies the other. Be ready to respond. Customer Focused Positive Solutions Minded Responsiveness Follow Through Timely Ready to resolve office or field situations

Coordinating with Others Not Just the Project Manager… Utility company representatives INDOT Utility Oversight Agent Consultants Contractor Designers “Everyone knows where everyone goes”

Coordinating with Others Understanding Manhole vs. vault A checklist is just a checklist – you need to know how to use it Do you need to get depths and when? A line on a drawing or ductbank What can we do to mitigate risk? “Know what you can know when you need to know it”

Utility Risk Report Project Information Goals Risk Evaluation UC is responsible to develop a Utility Risk Report on every project. Initially in the early stages; then updated as needed. Responsibility in the IDM – Joe This is a reporting tool to enlist the support of the PM. Does not include a list of utility companies Project Information is self explanatory; everything from the DES No., dates, Project manager name, Utility Coordinator name and date project assigned to UC (good for tracking) Goals – we will talk about this in more detail Risk Evaluation includes 1) identifying the risk and 2) developing a strategy to mitigate (eliminate or minimize) the risk. We will discuss this process and 3) how you can implement the strategy (action items / tasks) Critical R/W parcels – YES! Finally, the engineers are giving consideration to r/w parcels needed for utility relocations. Kenny discussed this in “new paradigm”. We need to do our part and help list the most critical parcels. Recent change to the parcel number column to include LA Code. Funding by FY – we will talk more about this in an upcoming slide, but it’s important to see how the utility estimate effects overall project budget. Project Information Goals Risk Evaluation Critical Right-of-Way Parcels Funding by FY

PM Goals for Utility Coordination Meet with PM Design Manager Project Team Example Goals: Have all utilities relocated ahead of construction Transmission Poles ordered by x date Use SUE data to avoid relocation of fiber optics Other Every project is different. Once you have an understanding of the project scope and potential conflicts, you can identify one or two goals that, if met, will lead to a success for the project staying on schedule and within budget. Talk to PM and Design Manager / Project Team DM is critical to opportunities to design around utilities UC has the responsibility but a good idea for the PM and UC brainstorm the goals and concur. Examples Have Type 1 utilities relocated by April 2013 Purchase easement for utilities where know in advance

PM Goals for Utility Coordination What does the PM need from the UC? NOT surprised The risks identified so that project decisions can be made appropriately Utility needs for construction Utility needs for Right of Way Understand utility needs for working area, tolerances, and easements Be able to convey this information to the designers and other project team members

Risk Evaluation Step 1: Risk Identification List factors that could adversely impact the project schedule or budget Be Specific – What could go wrong? Name the utility and the problem Examples: Duke Material Acquisition/Delay (i.e. steel poles) AT&T Work Plans not approved Time Warner representative unresponsive Communicate with the PM. Brainstorm what could happen to jeopardize the project schedule or budget. Be specific, this is the time to talk about what could go wrong.

Risk Evaluation Step 2: Risk Mitigation Strategy For each risk identified, develop one or two strategies to eliminate or minimize the risk Examples Let the project with a Utility Impact Note re: Duke Keep reminding AT&T that the Work Plan is due Send letter to Time Warner Accelerate a parcel for right-of-way acquisition Develop design exception Change MOT Ignoring the risk will not make it go away! You need to have a plan. If your plan is documented, that’s half the work! Think creatively. What have you done in the past that worked well? Be Solutions-Minded

Risk Evaluation Step 3: Tactics For each strategy, list specific action items (tactics) that can implement the strategy Examples (i.e. who, what, when): UC will obtain schedule from Duke, Lee Nicholson by x date. UC will submit impact note to PM by x date UC will send a letter to ATT Craig Adams, and then follow up weekly by e-mail or phone call UC will draft letter to Forrest & Time Warner by x date – INDOT Utility Oversight Agent to sign Escalate to Director if not resolved by x date Get specific. What will you do to make the strategy happen? Who, what, when? Review slide: examples- This may include bringing the Utility Oversight Agent or the State Director of Utilities and Rails in to help resolve. They own this project as much as the PM. Don’t overlook the opportunity to gain their support. If you are having a problem with a company, then chances are other UC’s across the state are too. So, Joe, Gail or INDOT may have already been involved with finding solutions on other projects that could help you.

Risk Evaluation Summary Step 1: Identify Risk Step 2: Develop 1 or 2 Strategies to eliminate or mitigate the risk Step 3: Assign Action Items to implement strategies Step 4: Communicate this to all parties To summarize the three steps Don’t be overwhelmed; this is not as difficult; practice the principle and it will make sense. Everyone knows where everyone and everything goes!

Risk Evaluation Summary As the Utility Coordinator: You cannot just document everything… You must communicate the results The utility coordinator must dig deeper. What have you told the designers? Do they understand what that means. For instance, did you say Vectren has a 16” main? Or did you say Vectren has a 16” main and they have clearance requirements of x’ in every direction? Sometimes you must be technical, and sometimes you may need to drill deeper into the details. A utility log sheet is only as good as the information it conveys…so communicate that. I don’t care that you have talked with AT&T 18 times…I want to know what it means if we have to move their pole.

Funding by Fiscal Year INDOT Fiscal Year: July - June FHWA Fiscal Year: October - September Utility relocation work typically overlaps one or more calendar years Coordinate with utility representatives Estimate reimbursements Calculate the funds needed by FY Communicate with PM Follow up as needed Need help? Contact the Utility Oversight Agent Finally, the money. Not sure why INDOT decided to put the money at the bottom of the Risk report; but….here it is. Basically, this requires the UC to break out the utility adjustment estimated expenses by fiscal year spending. Properly allocating the funds is another PM responsibility. Your job is to help the PM make the project a success. If you have problems with this, contact the INDOT Utility Oversight Agent

Conclusion Project Success Effective Communication Organization On-Point Attitude Utility Risk Evaluation Funding by FY Project Success Solves Problems Utility Adjustments On time and Within Budget Coordinating with PM If you practice effective communication and organization, in your coordination with the PM, you will be a success. If you do all that, properly evaluate utility risk and align the utility funds by FY, you have gone a long way to help ensure utility adjustments are on-time and within budge; a success for the project.