Work Breakdown Structure

Slides:



Advertisements
Similar presentations
Lecture Network Analysis
Advertisements

Precedence Diagramming
WBS: Lowest level OBS: Lowest level
Work Breakdown Structure
CP Chapter 4 Schedule Planning.
Project Management 6e..
Developing the Project Plan
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Work Breakdown Structures
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
Developing a Project Plan
Advanced Project Management - CPH
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Manjari Akella Pranava Nagpal B-Tech(CSE) 4 th Year.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
Critical Paths.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
Importance of Project Schedules
Scheduling CTC-415. Activity Network Development Network Models Activity on Node Precedence Diagram Method Activity on Arrow Network Characteristics Discrete.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Software Project Planning. Weinberg's Second Law If builders built buildings the way programmers wrote programs: Then the first woodpecker that came along.
© Pearson Education Limited 2004 OHT 8.1 Cadle and Yeates: Project Management for Information Systems, 4th edition Critical Path Method(CPM)
PROJECT MANAGEMENT Definitions WBS = Work Breakdown Structure
PROJECT MANAGEMENT Approaches
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Project Modelling The success of the whole planning and control function depends on the project planner being able to define the project’s full scope of.
Project Management MGT 30725
ECE362 Principles of Design
Critical Path Method(CPM)
UNIT II Scheduling Procedures & Techniques FLOAT
Project Scheduling KULIAH 10 Magister Sistem Informasi
Chapter 5: Project Time Management Doddy Prayogo, Ph.D.
Chapter 17 Project Management McGraw-Hill/Irwin
Activity networks – Example 1
deterministic Fixed and known in advance, representing a
Project Scheduling KULIAH 10 Magister Manajemen
Project Scheduling Lecture # 1.
Exercise 1: Escoger proyecto……….
Critical Path Analysis (CPA)
UNIT II Scheduling Procedures & Techniques CRITICAL PATH ANALYSIS
Project Time Management.
Chapter 6: Project Time Management
Project Theory and Application
Project Scheduling: networks, duration estimation, and critical path
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Critical Path Analysis
Project Scheduling Basics Activity on Node Precedence Diagrams
Project Time Management
PERT - The Program Evaluation and Review Technique
1 Total Slack A 3d Task Early Start Late Start Early Finish
Critical Path Method Farrokh Alemi, Ph.D.
Activity on Node Approach to CPM Scheduling
BEST VIEWED IN SLIDE SHOW MODE
Project Time Management
Network Logic Diagram 2/16/2019.
Software Project Management 4th Edition
Critical Path Analysis
Project Planning By Phaik San Liew.
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Project Modelling The success of the whole planning and control function depends on the project planner being able to define the project’s full scope of.
LECTURE 3.
Project Time Management
Project Time Management
Exercise – A small building.
AOA A style of project network diagram in which arrows
Project Time Management
Presentation transcript:

Work Breakdown Structure Project Management Work Breakdown Structure and the "Yellow Sticky" Process glb - 5/2003

The Work Breakdown Structure Project Management The Work Breakdown Structure What is a project? A temporary endeavor undertaken to create a unique product or service. What is a Work Breakdown Structure (WBS)? An activity oriented family-tree division of work tasks that define the entire project.

The Work Breakdown Structure WBS Terminology: Activity: A task or work package performed over a period of time. Relationships/Precedence: Dependencies that exist between activities. Duration: Length of the period of time to complete a task. Milestone: Zero time duration activity. Early Start: The earliest an activity can start based on project logic. Late Start: The latest an activity can start without delaying a project completion. Early Finish: The earliest an activity can finish based on early start and duration. Late Finish: Latest an activity can finish without delaying a project completion. Float: The amount of time an activity can be delayed without delaying the project finish date. Total Float: The amount of time that a pathway may be delayed from it's early start without delaying the project finish date. Critical Path: The longest time period from start to completion of a project; also the shortest total length of the project.

The Work Breakdown Structure Task Relationships: Finish to Start: Activity 1 must be totally finished before activity 2 can start. Activity 1 Activity 2 Start to Start: Activity 2 can not start before activity 1 starts. Activity 1 Activity 2

The Work Breakdown Structure Task Relationships: Finish to Finish: Activity 2 can not finish until activity 1 finishes. Activity 1 Activity 2

The Work Breakdown Structure "Yellow Sticky" Exercise: Early Start Early Finish Task Name / Brief Description: Late Start Duration: Resource: Late Finish Uses 3 X 5 Yellow Stickum Note Pads

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Activities/Tasks To Make: Toast, Eggs, and Coffee Toast Eggs Coffee Setup Get Bread Get Pan Put Water In Get Dishes Toast It Melt Butter Put Coffee In Set Table Turn on Maker Butter Toast Cook Egg Pour Coffee

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Set Precedence Get Bread Toast It Butter Toast Start: Alarm Clock Get Pan Melt Butter Cook Egg Finish: Eat Break- fast Put Water In Put Coffee In Turn on Pour Coffee Get Dishes Set Table

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Add Durations Get Bread Toast It Butter Toast 1 1 3 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 2 5 Put Water In Put Coffee In Turn on Pour Coffee 1 1 4 1 Get Dishes Set Table 2 3

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Perform Forward Pass 1 2 2 5 5 6 Get Bread Toast It Butter Toast 3 1 1 1 2 2 4 4 9 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 9 1 2 5 1 2 2 3 3 7 7 8 Put Water In Put Coffee In Turn on Pour Coffee 1 1 4 1 1 3 3 6 Get Dishes Set Table 2 3 Determine Early Start and Early Finish

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Perform Backward Pass 5 6 1 2 2 5 Get Bread Toast It Butter Toast 5 3 8 8 1 9 4 1 5 1 2 2 4 4 9 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 9 1 1 2 2 2 4 4 5 9 1 1 2 2 3 3 7 7 8 9 Put Water In Put Coffee In Turn on Pour Coffee 2 1 3 3 1 4 4 4 8 8 1 9 1 3 3 6 Get Dishes Set Table 4 2 6 6 3 9 Determine Late Start and Late Finish

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Critical Path 5 6 1 2 2 5 Get Bread Toast It Butter Toast 5 3 8 8 1 9 4 1 5 1 2 2 4 4 9 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 9 1 1 2 2 2 4 4 5 9 1 1 2 2 3 3 7 7 8 9 Put Water In Put Coffee In Turn on Pour Coffee 2 1 3 3 1 4 4 4 8 8 1 9 1 3 3 6 Get Dishes Set Table 4 2 6 6 3 9 Key: Any actions to shorten the overall project plan must be done to the critical path.

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Total Float 5 6 1 2 2 5 Get Bread Toast It Butter Toast 5 3 8 8 1 9 4 1 5 3 1 2 2 4 4 9 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 9 1 1 2 2 2 4 4 5 9 1 1 1 2 2 3 3 7 7 8 9 Put Water In Put Coffee In Turn on Pour Coffee 2 1 3 3 1 4 4 4 8 8 1 9 3 1 3 3 6 Get Dishes Set Table 4 2 6 6 3 9

The Work Breakdown Structure Yellow Sticky Exercise: Make Breakfast - Determine Activity/Task Float 3 3 3 5 6 1 2 2 5 Get Bread Toast It Butter Toast 4 1 5 5 3 8 8 1 9 1 2 2 4 4 9 Get Pan Start: Alarm Clock Melt Butter Cook Egg Finish: Eat Break- fast 1 9 1 1 2 2 2 4 4 5 9 1 1 1 1 1 1 2 2 3 3 7 7 8 9 Put Water In Put Coffee In Turn on Pour Coffee 2 1 3 3 1 4 4 4 8 8 1 9 3 3 1 3 3 6 Get Dishes Set Table 4 2 6 6 3 9 Activity/Task Float (Exclusive / Or) - Any one task on a pathway can use the total float, or the total float can be shared among all of the tasks on the pathway. However, the total float can not be exceeded without affecting the project end date.

The Work Breakdown Structure WBS Terminology: Activity: A task or work package performed over a period of time. Relationships/Precedence: Dependencies that exist between activities. Duration: Length of the period of time to complete a task. Milestone: Zero time duration activity. Early Start: The earliest an activity can start based on project logic. Late Start: The latest an activity can start without delaying a project completion. Early Finish: The earliest an activity can finish based on early start and duration. Late Finish: Latest an activity can finish without delaying a project completion. Float: The amount of time an activity can be delayed without delaying the project finish date. Total Float: The amount of time that a pathway may be delayed from it's early start without delaying the project finish date. Critical Path: The longest time period from start to completion of a project; also the shortest total length of the project.

Work Breakdown Structure Project Management Work Breakdown Structure and the "Yellow Sticky" Process glb - 5/2003