Nov. 19, 2009 prepared by H. Matsuhara, N. Takahashi, T. Nakagawa

Slides:



Advertisements
Similar presentations
Oct.10, 2007EAMA7 Japanese Space Activity on Exoplanets (JAXAs prespective) & Pathways to Habitable Planets September 16, 2009 Takao Nakagawa (ISAS/JAXA)
Advertisements

Leicester SRC, 3-5 Dec 2007 Systems engineering at detector level Tim Stevenson.
Solar Orbiter EUV Spectrometer
1 GAIA System Level Technical Reassessment Study Final Presentation ESTEC, April 23rd 2002 Part 1b Development & AIV.
1 ESAIL proof of concept mission Juha-Pekka Luntama Pekka Janhunen Petri Toivanen.
Test Cryostat, OGSE and MGSE PACS IHDR: MPE 12/13 Nov 2003 AIV1 PACS Test Cryostat, OGSE and MGSE Gerd Jakob MPE.
14/06/20151 MORE Requirements seen from ESA Pedro Pablos 1 st MORE Team Meeting 27 Febrero 2007.
W. Aalders FPU CDR 1-3 July 2003 HIFI 1 FPU CDR MCS HIFI MECHANISMS 1.Focal Plane Chopper (FPC) 2.Diplexer Rooftop Mirror Translator (DRT) 3.Pivot development.
PLATO kick-off meeting 09-Nov-2010 PLATO Payload overall architecture.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
SDW2005, juin, Taormina The Corot Space instrument.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
1 TIPS 4/18/2013 Status of JWST/ISIM Test Program Scott Friedman TIPS/JIM April 18, 2013.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
1 Mirror subsystem: telescope structure Functions: Functions: Support mirrors subsystem to S/C Support mirrors subsystem to S/C Accommodate cryostat Accommodate.
1 NASA’s Goddard Space Flight Center 2005/4/14 LRO/CRaTER Technical Interchange Meeting LRO Mechanical Systems Giulio Rosanova / /
IMPRS June Space Research, in praxis, illustrated by a ground-based example The „Ozonometer“ as a student project.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
PACS IHDR MPE 12/13 November 2003 AIV 1 PACS IHDR Integration, Qualification and Testing Reinhard Katterloher.
PACS IBDR 27/ BOLC/BOLA1 BOLC / BOLA SAp/DAPNIA/DSM/CEA C. CARA WE Design Team: A. BOUERE - N. DEVIN - G. DHENAIN - E. DOUMAYROU M. SEYRANIAN -
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
The Field Camera Unit Project definition, organization, planning S. Scuderi INAF – Catania.
Presentation EddiCam consortium, FF, Madrid 13/06/2002 Eddington programmatic status Fully approved by SPC as part of ESA’s science program as project.
PACS IHDR 12/13 Nov 2003 PACS FPU FPU Structure, Baffle and Straylight R. Graue, D. Kampf Kayser-Threde.
Current Status of SPICA Focal Plane Instruments October 19, 2009 Hideo Matsuhara (ISAS/JAXA) & FPI team.
PACS IBDR 27/28 Feb 2002 IIDR Close-out1 Close-out of IIDR Recommendations A. Poglitsch.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
FIRST/Planck 12 December 2000PT The FIRST Mission Implementation Status and Schedule T. Passvogel The Promise of FIRST.
PACS IHDR 12/13 Nov 2003 IBDR Close-out1 Close-out of IBDR Recommendations A. Poglitsch.
Science - Coronal heating - Coronal structure / dynamics - Elementary processes in Magnetic Reconnection Mission instruments - Optical Telescope / Vector.
NIRSpec Status and PDR Results Jeff Valenti & Mike Regan 2006 March 16 TIPS/JIM.
Oct.10, 2007EAMA7 The next-generation Infrared astronomy mission SPICA Outline of SPICA Scientific Research Concept (SciReC) SPICA 研究コンセプト概要 17 th May.
Herschel/Planck January 13, 2005PACS IQR - SCI-PT/ ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt.
COST 723 Training School - Cargese October 2005 OBS 3 Radiative transfer for thermal radiation. Instruments Bruno Carli.
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/ SPIRE & PACS SORPTION COOLERS.
Current Status of SPICA FPI Mechanical I/F & resources April 6 th 2010 Hideo Matsuhara (ISAS/JAXA) & FPI team.
PACS IBDR 27/28 Feb 2002 PACS PI Summary1 Where we are and where to go… A. Poglitsch MPE.
SPICA / AIV&T issues Spacecraft test program & model philosophy
Advanced Studies and Technology Preparation Division 1 SPICA Mission profile M class presentation Paris, 1 December 2009.
PACS IIDR ESTEC 01/02 March 2001 System Engineering 1 PACS Instrument Intermediate Design Review (IIDR) Reinhard Katterloher System Engineering DDVP, Model.
Réunion de présentation des besoins 10 Nov Joël MICHAUD French expertise in SiC for large telescopes.
PACS IHDR MPE 12/13 November 2003 System Engineering 1 PACS IHDR Model Philosophy, Budgets, Interfaces and IID-B Reinhard Katterloher.
Optical & Mechanical I/F between SAFARI and IOB Rev. A Mar. 12 th 2010 Hideo Matsuhara.
PACS IHDR MPE, 12/13 Nov 2003 Overall Schedule1 Otto H. Bauer MPE Garching.
Instrument Status GLM Science Team Meeting 9 September 2016 Marc Rafal/GSFC GLM Instrument Manager.
FPI related schedule & Model Philosophy Based on spica_AIVT_revC, FPI_review_by_SDR_E Mar. 15 th, 2010 by H. Matsuhara, N. Takahashi, T. Nakagawa.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
1 System Architecture Mark Herring (Stephen Merkowitz Presenting)
Goddard Space Flight Center Cryogenics and Fluids Branch Status of the AMS-02 Cryocooler January 2007 TIM.
1DSM/DAPNIA/SAp – J. MartignacPACS - IHDR - MPE – Nov. 12 – 13, 2003 PACS – IHDR PhFPU Design J. Martignac CEA/DSM/DAPNIA Service d’Astrophysique.
PACS IBDR MPE 27/28 Feb 2002 System Engineering 1 PACS IBDR Model Philosophy / Development Plan Reinhard Katterloher.
JWST Mission CDR Northrop Grumman Space Systems Redondo Beach (CA) April 10-16, 2010.
SPICA FPI envelopes – current status 16 th April, 2010 Hideo Matsuhara On behalf of FPI team.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
BSMIan Pain, UK ATC SPIRE Instrument Intermediate Design Review April 23, RAL 1 Beam Steering Mirror Sub-System IIDR Overview Ian Pain UK ATC Colin.
Date of download: 5/29/2016 Copyright © 2016 SPIE. All rights reserved. Drawing of the Space Infrared Telescope for Cosmology and Astrophysics (SPICA)
Dr.F. Arteche EMC DEPFET Project: A general overview.
Lunar Reconnaissance Orbiter (LRO) SRR/Mechanical System August 16-18, 2005
Spacecraft Technology Structure
Incorporating Hubble Servicing with NASA’s Long-Term Vision
TEMPO Instrument Update
Integrated Thermal Analysis of the Iodine Satellite (iSAT) from Preliminary to Critical Design Review October 20th 2016 Stephanie Mauro NASA Marshall Space.
30-Nov-2006 Jean-Marc Defise - CSL
A.M.Villavan Sai Lalith Rohit K.Anudeep
Integration and Test Organization Chart
SPICA / FPI Mechanical /Optical Issues
Instrument Overview Larry Springer HMI Program Manager
THERMAL CONTROL SYSTEM
CHEOPS - CHaracterizing ExOPlanet Satellite
Presentation transcript:

Nov. 19, 2009 prepared by H. Matsuhara, N. Takahashi, T. Nakagawa SPICA / AIV&T issues Spacecraft test program & model philosophy (tentative plan) Nov. 19, 2009 prepared by H. Matsuhara, N. Takahashi, T. Nakagawa

Key issues for FPI AIV&T FPI’s system-level test plan should take account of the critical issues as below: (a) FPI is cooled to <5K with J-T coolers under extremely careful Spacecraft thermal design. (b) disturbance and interference from J-T coolers and AOCS (such as RW, gyro) To assure high-sensitivity (low-noise) in orbit (c) Co-operation with FPC-G to establish the pointing stability Interferences? Alignment? (d) Co-focus among FPIs (especially MIR’s) Since STA 2ry cannot be adjusted so frequently in orbit

FPI Model philosophy Minimum number of Models required for the system level test (in the previous page) is: FM (Flight Model) (& its spare) STM : structure thermal model CQM : cold qualification model Delivery date of FM: June 2016 (August 2016 at worst) in the proposed scenario.

STM : Structure Thermal Model Description Mechanical I/F specifications (including disturbance sources) is equivalent to that of FM Required Function Same mechanical I/F specifications to FM Nearly the same thermal I/F (TBD, for spacecraft(PM) thermal test) Equipped with thermometers, acceleration sensors for measurement of I/F environmental condition Simulate mechanical disturbance according to the system operation modes Proposed Delivery Jan. 2013 : before starting of assembly of spacecraft (PM) for the system Mechanical Thermal Test

CQM : Cold Qualification Model Description Nearly equivalent to FM incorporating with detectors operable at low-temperature expected in orbit Required Function Same thermal, mechanical, electrical I/F specifications to FM Equipped with detectors operable at low-temperature, with the same noise performance as that of FM Simulate heat-dissipation (load to J-Ts), mechanical disturbance according to the system operation modes Proposed Delivery Apr. 2015 : when the PLM(FM) is available for us to test the items (a), (b), & (c) in page 2.

SPICA system test plan With STM: With CQM: With FM Measure disturbance at FPI from J-T/AOCS under Spacecraft MTM test in 2014 With CQM: Cooling test with J-T (PM) (in PLM (PM)) Evaluate effect of mechanical disturbances from J-T/AOCS simulator, electrical interferences among FPIs, J-T, AOCS in the latter half of FY2015 With FM FPI evaluation at cold (optical & electrical) STA optical performance test at cold PLM thermal test

SPICA AIV&T timeline (tentative)

Focal Plane Instrument Assembly (FPIA) = IOB+FPI TOB:Telescope Optical Bench IOB: Instrument Optical Bench

FPI Evaluation at cold (1) Date & Duration: latter half of 2016, 1-2 months Place: 6m Space Chamber at Tsukuba Space Centre(tbd) Configuration: IOB(FM dummy)+FPI(FM)+cooler(TBD)+FPI-E(FM)+STA Simulator Purposes: With all FM FPIs together, all functional, electrical & optical performance evaluation at cold (operating temperature in orbit) as well as interference test. Optical performance will be measures with a STA simulator.

FPI Evaluation at cold (2) IOB FPI LHe Mech. cooler

SPICA Telescope Assembly (STA) 3.5m is technically a good choice Monolithic Mirror Ceramic material (SiC) No deployable mechanism Simple, Feasible, Reliable Smooth PSF Essential for Coronagraph Herschel & AKARI Heritage SPICA: WFE 0.35μm, 5K (3.5m) AKARI: WFE 0.35μm, 6K (70cm) Herschel: WFE 6μm, 80K (3.5m)

STA Optical Performance test at cold (1) Date & duration: 1st harf of 2017, 1-2 months Place : 6m Space Chamber in Tsukuba Space Center Configuration IOB(FM)+STA(FM) Additional thermal sheild in the chamber Purposes: Optical performance evaluation of STA at <10K Multiple measurements are connected by the Stitching Method

STA Optical Performance test at cold (2)

PLM Thermal Test Purpose Method Evaluation of PLM cooling system performances Method Additional shields in the existing 13m(?) space chamber in Tsukuba Shields are externally lifted by mechanical coolers

Q & A : AIV (1) Definition of spacecraft level test program and consequent requirements on the instrument models delivered to JAXA - including alignment concept for spacecraft level integration. See previous pages. (related Q) the proposed schedule for SAFARI instrument models:     STM  : Jan 2013     CQM  : April 2015 (August 2015 at worst)     FM   : June 2016  (i.e. 2.5 yrs before launch)

Q & A: AIV (2) What are the ground test thermal conditions? Can we use lots of power for the mechanisms? To be answered by Sugita-san, Takahashi-san, Murakami-san More or less described above.

Q & A: AIV (3) Are the different orientations of the FPU during the test campaign on system and satellite level well known?. 1st system AIV : STA (& FPIA) in vertical FPI evaluation at cold : TBD, vertical? STA evaluation at cold : horizontal in 6m chamber PLM Thermal test & Final system V&T: vertical