Why Sub-System monitor? Knowing what should be done for: Sub System for SIMOP, PRE-COM, CONST and COMISSIONING (i.e. communication of responsibilities) Contractors Construction supervisor Commissioning manager Operation manager PTW Authority SIMOP coordinator RSES (Responsible for HSE on sit) Subsystem Status Sub-System actions Follow-Up Comments long Action Status report Company 22 April 2019 http://adepp.webexone.com 1
What is Sub-System monitor? Location A PTW monitor is a secure online monitoring system which: UTILISES: P&ID, SLD, Layout and by Company, vendors, Contractors, and Third party to: Generate list of Sub-systems Generate related Sub-system activities Generate Sub-System related tasks Help the Follow-UP Print the updated Sub-System comments report at any time Sub-System) monior uses the friendly interfaces with expert support for traceability and audit purpose by Company, Contractors, Contractors and Verification Party Sub-System data and documents can be exported easily to Company, consultant or Contractor’s Intranet via Access datasbase Location C Location B Location D 22 April 2019 http://adepp.webexone.com 2
ADEPP monitor ( Login) Login Name: demo Password: adepp2009 22 April 2019 http://adepp.webexone.com 3
Sub-System monitor Click on New Enter Sub-System Save Click on View 22 April 2019 http://adepp.webexone.com 4
Sub-System monitor Insert Your name, your title, Sub-System, etc. Save 22 April 2019 http://adepp.webexone.com 5
Sub-System monitor Click on Send a Link 22 April 2019 http://adepp.webexone.com 6
Sub-System monitor Send the link to SIMOP Group , Commissioning Etc. 22 April 2019 http://adepp.webexone.com 7
Sub-System monitor To give your comments Click on Search Icon 22 April 2019 http://adepp.webexone.com 8
Sub-System monitor To give your comments Click on COPY 22 April 2019 http://adepp.webexone.com 9
Sub-System monitor Insert your name, your comments Save 22 April 2019 http://adepp.webexone.com 10
Sub-System monitor Click on View Click on PTW comments 22 April 2019 http://adepp.webexone.com 11
Sub-System monitor Click on Print Or Export to Excel, etc 22 April 2019 http://adepp.webexone.com 12
Sub-System monitor Click on Activity-Tasks For Validation 22 April 2019 http://adepp.webexone.com 13
Sub-System monitor Click on Activity-Task Icon 22 April 2019 http://adepp.webexone.com 14
Sub-System monitor Click on 1day week Reminder will be give by Email Validation to Edit Assign the task to other person 22 April 2019 http://adepp.webexone.com 15
Sub-System monitor Click on Edit 22 April 2019 http://adepp.webexone.com 16
Sub-System monitor Assign Task to others 22 April 2019 http://adepp.webexone.com 17
Sub-System monitor Click on Follow-Up Then click on Export Note: The follow-up status will be exported as excel file 22 April 2019 http://adepp.webexone.com 18
Terms of Us of ADEPP monitor. ADEPP monitor will be built based on requirement of project. HSE Manger or his representative can Edit the HSE actions register Others have access to Read & Add ( Project to advise) Projects can use ADEPP monitors if they sign the Terms of Us of ADEPP monitor. All SIMOP register can be exported to company intranet at any time. ( It is recommended to transfer data weekly to company intranet) ADEPP monitor uses the secure web server to allow project team members to view, add, modify and delete only the specific information they need. Secure Sockets Layer (SSL), is an extra level of security for ADEPP monitor. It requires the project team remember to log on through a secure server, which prevents hackers from accessing their information. SSL uses technology known as encryption. This is software that scrambles the data with secret code. Company, Contractors, Sub-contractors, Vendors are required to log in to the site with SSL encryption enabled, so the project can share very sensitive, confidential data through ADEPP monitor site. 22 April 2019 http://adepp.webexone.com 19
Thank your for your kind attention! Fabienne. F. SALIMI Director ADEPP Ltd. ( UK) www.adepp.webexone.com 22 April 2019 http://adepp.webexone.com 20