Hall C Dump Status Beam Resuscitation Review Anthony DiPette 3/4/2016
Hall C Dump Status - BRR Required for March 14-17 Run Status Next Steps
Required for March 14-17 Run Hall C Dump Status - BRR Required for March 14-17 Run New Helium Tube Isolation Wall with Door & Radcon Lock Vacuum Tube with Temp Window Tune Mode Viewer
Hall C Dump Status - BRR Status Installed Install 3/4/16 Installed
Hall C Dump Status - BRR Status I & C to Complete Camera System Inst – Fill Helium and Vacuum Tube w/ Helium Radcon – Install Lock
Hall C Dump Status - BRR Status End Section of He Pipe
Hall C Dump Status - BRR Status Isolation Wall
Hall C Dump Status - BRR Status Downstream Vacuum Pipe Section Upstream Vacuum Pipe – with Actuators Installed
Camera Box with Periscope Tubes Hall C Dump Status - BRR Status Camera Box with Periscope Tubes
Hall C Dump Status - BRR Status High Power Viewer Periscope Tube, Diffuser Drive shaft, Iso Wall Door Hardware
Hall C Dump Status - BRR Next Steps Complete Mech: Diffuser Drive & Blower, Tunnel Shielding, Iso Wall Grouting/Sealing, Aperture Plate & Window Water Cooling System, Camera Box Shielding, N2 System Final Connect and Commission Complete Diag: Diffuser Drive & Blower, Tune Mode Viewer, Calibration Puck, Water Cooling System, N2 System, Helium Monitoring, Ion Chamber Install and Commission