Helium collector structural analysis

Slides:



Advertisements
Similar presentations
Use of diagonals and consoles when building Altrad Balliauw – all sites (Look out for site-specific rules!) Floor length Diagonal length Single.
Advertisements

Interface of Plug-Compatible Cryomodule Components KEK Norihito Ohuchi 2008/3/41GDE-Sendai Meeting.
Progress and Plan for Superconducting RF Cavity RF Group.
Felix Wamers, Technical Coordination Meeting, 12 th -13 th of May CERN-GSI Technical Coordination Meeting Felix Wamers, Yu Xiang,
Internal Cryomodule Instrumentation Sensors, Actuators, Heaters, and Wiring ERL Main Linac Cryomodule 9/5/2012 Peter Quigley Internal Design Review.
Interface issues on Super-FRS magnets test at CERN
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
SuperFRS Multiplett and Dipole Vacuum Interfaces Multiplett: Insulation vacuum: Insulation Vacuum Pumping flanges: Two CF flanges of the size DN160 must.
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
ESS Cryogenic Distribution System for the Elliptical Linac CM - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden J. Polinski.
The Sector 3-4 incident at the LHC: fault tree and corrective measures Ph. Lebrun Risk Analysis Review Committee CERN, 5 March 2009.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
INSTALLATION & COMMISSIONING. 5WSS Installation Hanging the Unit Hanging the Unit Location Considerations Location Considerations Refrigerant Piping Refrigerant.
Safety Requirements and Regulations 10/3/20121Safety Requirements & Regulations James Sears.
Static Analysis Static Analysis, Internal Forces, Stresses: Normal and Shear 1.
Status of Activities at CERN
1 HIGH ENERGY ACCELERATOR RESEARCH ORGANIZATION KEKB Review Committee/ NAKAI Hirotaka KEK Crab Cavity - Cryogenics - KEKB Crab Cavity Group - presented.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
A valve must be used to control water flow from ablution hose. Sample drawing for 6270 WC pan. ABLUTION HOSE APPLICATIONS.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
ESS Cryogenic Distribution System for the Elliptical Linac CDS Heat Loads Calculations Preliminary Design Review Meeting. 20 May ESS. Lund. Sweden.
S1 global: thermal analysis TILC09, April 19th, 2009 Serena Barbanotti Paolo Pierini.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Adam Carreon July 19, 2012 Technical Division SRF Department Dressed SSR1 Cavities.
Numerical modelling of cold helium safety discharges from the cryogenic distribution line Jonathan Persson MSc. Engineering Physics AD and ICS Retreat.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
Safety - Lessons learnt from the design, commissioning and operation of the HIE-ISOLDE cryomodules Safety overview ESS 8 June 2016 AP.Bernardes/EN on behalf.
Low Beta Cryomodule Development at Fermilab Tom Nicol March 2, 2011.
Overview of the ESS Linac Cryogenic Distribution System
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Extra / Discussion Slides. 2 1.Helium Top Fill Port Add extra CF/ISO flange as collar so that the weld-region is not disturbed 2.Helium bottom FillCF.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
ESS Cryogenic Distribution System for the Elliptical Linac SV calculation approach Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden J.
Design Status of the Spoke Cryomodule for MYRRHA SLHIPP Louvain la Neuve 17-18/04/2013 Design Status of the Spoke Cryomodule for MYRRHA SLHIPP Louvain.
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
Process Requirements and Design Approach
Sizing Group Vent, Stack , Stack vent
2 K Coldbox Safety and ESH
2K Cold Box FDR Introduction
Status of the PANDA Magnet mechanics (yoke & cryostat)
Stress and cool-down analysis of the cryomodule
IT-4189 Supply and installation of a cryogenic distribution system
Mechanical calculations of the CDS key elements
ESS Target Cryogenic System European Cryogenic Days CERN
Cryostat design Mechanical design: Thermal screens: Specifications:
SC1R Cold Box PDR Mechanical Design
2K Cold Box Process Design
Optimum cryomodule length at the ESS
Cryogenic System Commissioning Summary Report
ESS elliptical cryomodule
Alignment of Main Linac Cryomodule (MLC)
Jaroslaw Fydrych SHC Lead Engineer
Helium collector CFD analysis
ESS elliptical cryomodule
Double-Spoke Cavities
WP11: CDS-SL CDR Overview
Positioning, alignment strategy and assembly steps
Source Spallation European (ESS)
Vacuum System Design for the Target Monolith System
Presentation transcript:

Helium collector structural analysis Jonathan Moberg

Outline Overview Bellows Pipes Supports

Routing of the collector Cold box room vent line Total length of the collector < 400 m CDS vent line L = 12 m, DN400 CTL gallery L = 55 m Target left, source right Elliptical and Spoke Linac tunnel 310 m

Connections to the collector header

Bellows

Highest stress in the system

Deformation

SHC [L/R] Cryomodule Deformation 1 [mm] Deformation 2 Total Deformation L Spoke 21.84 2.64 24 Spoke transition 22.48 25 elliptical transition 9.19 21.8 31 elliptical 2.65 21.74 R 21.83 2.61 21.79 2.58 17.09 20 2.62 21.78

CDS vent line connection

Static pressure in the flexible inlet hose Stub loads   Static pressure in the flexible inlet hose Safety device Type Interface DN Interface PN Fz due to mass [N] valve opening [kN] Fx [kN] Fy [kN] Fz [kN] SV91 DIN EN 1092-1 Form B1 (DIN 2526 Form C) 80 16 -0.30 1.3 -1.4 SV92 40 -0.20 SV93 25 -0.15 0.8 -4.5 SV94 2 4.5 RD92 DIN EN 1092-1 Type 11 Form B 100 5.6 NA

Load cases Load case DN25 [N] dir DN40 [N] DN80 [N] DN100 [N] 1 -4500 z 4500 -1400 5600 y 2 3 x 4 5 6

Load case 3 1.4404 1.4307 Time step Plastic deformation [m/m] 1 6.19E-03 6.34E-03 3 6.44E-03 6.60E-03 5 6.62E-03 6.79E-03 7 6.75E-03 6.94E-03 9 6.84E-03 7.04E-03 11 6.90E-03 7.11E-03 13 7.15E-03 15 6.96E-03 7.17E-03 17 6.97E-03 7.18E-03 n_allowed 6328 4654  Load case 3 was identified as the worst case. Therefore another three load cycles were simulated the hardening of the material was thereby increased and the increment in plastic deformations was reduced between time step 9 and 11 compared to the increment between 3 and 5. By extrapolating the plastic deformations the structure can then withstand at least 1229 cycles.

Floor mounted support

Floor mounted support

F_5,5316e+005

F_5,5316e+005

Ceiling beam

Ceiling beam

Primary supports

Anchors

Supports in the corridor to the cold box

Supports in the corridor to the cold box

Fix after the L-shaped hole