Thursday – Morning Energy matching at injection with H CODs

Slides:



Advertisements
Similar presentations
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Advertisements

5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
:30 meetingEBH 1  No beam during the morning:  4:15 – 9: V distributor: Recovery after electrical interruption  access for TI services.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Monday fill with 1092 bunches (6 h stable beams)
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Barbara Holzer, Jorg Wenninger
LHC Morning Meeting - G. Arduini
Coordination: Gianluigi Arduini & Jan Uythoven
Summary of week 22 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Wednesday 31 October: Morning
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Mike Lamont, Jorg Wenninger
Wednesday 8th August & night
LHC Morning Meeting - G. Arduini
Chromaticity can make a difference…
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
Friday Morning 7:30 injection for fill 2908
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Thursday morning 7:20 – 12:30 faults of BLM sanity check, RQX.L8 QPS trip and iris scanner in UJ47. Access: Pt 8 for ELQA on RQX.L8 (The voltage.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday – Morning Fill 3265 stable beams since 1:31
Wednesday Ramp single nominal bunches for loss maps
Thursday Physics fill 1250 (with 13b) dumped at 10.30
LHC Morning Meeting - G. Arduini
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Tuesday 17/5 10: TeV - colliding. Start roman pot alignment ...
Saturday 3rd November - morning
Saturday Nov Stop proton operation. Switch back to ions
Tue/Wed 12/ :00 Probe beam back again
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Tuesday – Morning and Evening
Another Immortal Fill….
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday morning / afternoon
Wednesday morning Waiting for PS – problem on RF cavity.
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Friday :47 stable beams fill 3273
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Saturday 26 November 2011.
Tuesday
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Presentation transcript:

Thursday 8.11. – Morning Energy matching at injection with H CODs Afterwards transfer line steering by injection team In parallel: Moderate ADT gain increase for the ramp (horizontal plane from 0.02 to 0.04) Batch-by-batch blow-up ON again with moderate 1.4ns target length 12:00 Filling for physics Emittances of 144 bunches B1H = 1.72 B2H = 1.67 B2V = 1.91 13:30 Stable Beams fill 3272, initial L ~7.3e33 cm-2s-1 CMS not publishing lumi data at the beginning 14:00 TCLs opened to 60 sigma, to measure the cryo load

Afternoon 16:25 increase RF voltage to 12 MV (reduce bunch length) 17:00 Beam dump, COD trip. Integrated L ~69 pb-1 in 3:23 hours Access for ALICE and for ROD/F in sector 56 (which had tripped earlier at 15:00) In parallel to the access LHCb polarity inverted for next fill Increasing BLM MF from 0.3 to 1.0 for TOTEM roman pots – BLMEI.06L5.B2E10_XRP and BLMEI.06R5.B1E10_XRP 19:30 intervention for octupoles finished 22:12 ALICE intervention finished Pre-cycle No test ramp – straight to nominal physics

NIght Emittances, 144b, at injection: B1H = 1.72 B1V = 1.63 2:38 colliding in IP1, IP2 and IP5 (CMS not publishing lumi values) 2:47 IP8 set-up finished; stable beams fill 3273 Initial luminosity ~6.9e33 cm-2s-1 5:49 RF voltage to 12MV

Last two fills

Access RF (Pierre Measen) UX45 during turn-around (IMPACT 21809) QPS for RB.67 (2 hours working hours) Wall Current Monitor (Pt 4 RF zone – RP piquet) R. Steinhagen

Pending 4 BPMs left of IP5 around TOTEM needed to be masked last night – to be looked at further Further increase ADT gain B1 during ramp (now that the tune is measured on the first 6 bunches, which are not damped by ADT) to reduce blow-up TOTEM tests at end of fill (separate CMS to reduce lumi by at least a factor of 10) - ~1 hour Slight tuning of tune splitting B1 (Vertical tune B1 trimmed down by 0.003) Following week(s): Loss maps (periodic) Heating test at 450 GeV TCP IR3 more closed (end of fill) Bunch length investigations Tuning of the mask for abort gap/injection cleaning to try to reduce influence on the rest of the beam