ISRC and LEBT Vacuum System Design

Slides:



Advertisements
Similar presentations
31/03/11FV 1 CEDAR from flammable gas safety point of view.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
MICE Safety System DE Baynham TW Bradshaw MJD Courthold Y Ivanyushenkov.
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
The MICE vacuum system Presented by Mark Tucker at CM-39, 26 June 2014.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
E. Beebe LEBT & Ion Injection EBIS Project Technical Review 1/27/2005 LEBT and External Ion Injection Ed Beebe Preinjector Group Collider-Accelerator Department.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
FETS H - Ion Source Experiments and Installation Scott Lawrie, Dan Faircloth, Alan Letchford, Christoph Gabor, Phil Wise, Mark Whitehead, Trevor Wood,
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
NLC - The Next Linear Collider Project NLC Beam Delivery Lehman Review, May 1999 Vacuum System Cost Model Presentation by Leif Eriksson.
J. Alessi Implementation Plan EBIS Project Technical Review 1/28/05 Implementation Plan WBS exists Working on a “bottoms up” cost estimate The following.
Results of the argon beam test at Linac3 D. Küchler BE/ABP/HSL Including feedback from R. Scrivens and M. Bodendorfer.
Ion Sources – Hardware and Operation MACS Week Friday 8th October 2010 PP a-LPE, 8 th October 2010, MACS Week 2 Liviu Penescu, „Ion Sources.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Developments of the FETS Ion Source Scott Lawrie.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
H4F Physics Day 2014 C.Ullmann Proton injector status for FAIR and measurements at BETSI test bench (CEA/Saclay) 2014.
Status report on ICS interfaces (Accelerator, Target, NSS, CF) and related activities Miha Reščič Deputy Project Manager, ICS
ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert.
PS-ESS and LEBT State of the art Lorenzo Neri Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
The ESS high intensity proton source and the LEBT: status, planning & open points L. Celona on behalf the LNS team Istituto Nazionale di Fisica Nucleare.
PXIE LEBT Status Update Lionel Prost PIP-II “Friday” Meeting January 16 th, 2015.
ESS Vacuum Standardization
WBS2.11 Vacuum systems G.Vandoni …brainstorming presentation… VAT Technical & Scientific7 th July 2008.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
WU2 - Proton Source & LEBT Schedule 2013 L. Celona Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud.
ESS Front End diagnostic
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
PXIE Ion Source & LEBT Commissioning Update Lionel Prost on behalf of A. Shemyakin, R. Andrews, B. Brooker, K. Carlson, J. Czajkowski, R. D’Arcy, B. Hanna,
3 MeV Measurements at Lianc4 1 Veliko Dimov (for the source and linac team) (J-B Lallement, J. Lettry, A. Lombardi, D. Fink)
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
Slides for TAC meeting Oct/2015 Marcelo juni Ferreira Vacuum section leader October,
Report Technical Director Storage-Ring-Installation Completed
Cryomodule test stand at ESS site
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Sub-system integration for the VBOX
MICE Hall Summer Workplan
1.3-GHz Cavity Vacuum Furnace at IB4
Lesson learnt – WP3 S. Gammino.
XFEL Vacuum System Commissioning
Martin Dommach TDR ART Review, Hamburg, September 14, 2012
Introduction to W7-X Coil Testing at CEA – Saclay, France
Proton Source and LEBT Luigi Celona & Lorenzo Neri
Tom Shea Front End Meeting Catania
Andreas Jansson, Lali Tchelidze
Beam Commissioning at ESS
Ion Source and LEBT control system topology, Interlock strategy
Personnel Safety system 0 for the Ion Source and LEBT (PSS0)
PSS0 Design & Concept of Operations
Testing Coordination at ESS
LEBT water cooling system
PSS Verification and validation
Ion Source and LEBT Beam Diagnostics
(Beam) Commissioning Plan
Radiation Protection Handbook
Safety Readiness Review (SRR) Thomas Hansson, ESH
System tests at CEA O. Piquet 19/03/2019
Beam Commissioning Planning
Operation of Target Safety System (TSS)
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Target Safety System Interfaces
ISrc & LEBT – ICS Installation Readiness Review
Vacuum System Design for the Target Monolith System
Overview of the TARGET Monolith Rough Vacuum
Stuart Birch On behalf of Protection Systems Group
22-SAR MEBT Vacuum test Aitor Zugazaga Zamudio, 27 March 2019.
IS&LEBT Commissioning Review Safety and Radiation Protection
Presentation transcript:

ISRC and LEBT Vacuum System Design Simone Maria Scolari Vacuum System Engineer SRR 1 – Ion Source & LEBT 2018-07-17--18

System - Vacuum Low energy beam transport (LEBT) Plasma chamber Extraction system Pumping box Solenoid 2 x steerer Gate valve Iris Diagnostics tank Chopper EMU H+V Faraday cup NPM H+V Doppler shift 2 x TMP Repeller ACCT Commissioning tank (RFQ) HV power supply Isolation transformer Collimator Magnetron H2 bottle Ion source LEBT 1 LEBT 2 3 x solenoid Waveguide Primary pump High voltage (HV) platform Low energy beam transport (LEBT) PSS0 controlled area and radiation shielding Front End and Magnets Cooling water Vacuum PSS Beam Diagnostics Control system Voltage divider HV controls Ground potential controls Beam stop Alternative location of beam instruments for commissioning N2 bottle ACCT: AC current transformer EMU: Emittance measurement unit NPM: Non-invasive profile monitor TMP: Turbomolecular pump

Table of content System Requirements (high level) Specific safety systems (engineered control) Operating & safety procedures (administrative control) Test & Verification Allowed testing Envelope Open issues

System Requirements (high level) Operational pressure The gas throughput from the LEBT to the RFQ at the LEBT-RFQ mechanical interface shall not exceed 2x10-3 mbar l/s (P = 6E-5 mbar) Leak Tightness 2x10-10 mbar l/s for metal connections; 2E-8 mbar l/s for connections where polymeric gaskets are used

Specific safety systems No ”on-line” leak monitoring system is envisaged in the design. Leak Check of the delivery line will be executed at each bottle exchange according to ESS-0012897 – ”ESS Vacuum Handbook Part 4 – Helium Leak Test”. Bottle exchange will be carried only by trained operator. A self-venting regulator has been selected since the accidental release of the entire content of hydrogen is not considered hazardous. A 10 l, 100 bar bottle will be used.

Operation procedures Primary pump Turbomolecular pump Pneumatic angle valve Sector gate valve Gauge Mass Flow controller

Test & Verification Vacuum Control System (ICS scope) Leak Check Test and Verification is on going according to: ESS-0087031 - LEBT Vacuum Control System - System Requirement Specification ESS-0087038 - LEBT Vacuum Control System - Verification and Validation Plan Leak Check Leak Check according to ESS-0012897 – ”ESS Vacuum Handbook Part 4 – Helium Leak Test”. All the existing connection have been leck checked. The beam stop cooling system presents a water leak. Leak check on gas delivery systems to be executed.

Outstanding issues # System/Comp. Status Description Due date Remark 1 Iris cooling line OK Polymeric gaskets on cooling lines N/A Risk to run the IRIS with polymeric gasket when RFQ will be in place. 2 Turbomolecular pump Failure The pump is not working Not a stop for starting operations 3 H2 and N2 delivery system Not ready Gas delivery systems have not been installed yet End of July All part have been already procured 4 Beam stop Leaking A water leak has been found On going FC can be used; no issue for starting of operation. Beam stop will be substituted with a water cooled flange.

Questions First ESS proton is in this bottle!