Cavity Degradation Experience at S1-Global

Slides:



Advertisements
Similar presentations
E. KAKO (KEK) 2010' Sept. 10 KEK Global Design Effort 1 Operational Results from STF-VTS and Cryomodule Tests at KEK Eiji Kako (KEK, Japan)
Advertisements

6/Nov/2012 TTC Meeting 1 Improvement of cavity performance by T-mapping/X-ray-mapping, optical inspection and local grinding Kirk.
KEK cavity status, March 2011 H. Hayano, ALCPG11, WG3, Eugene.
Stain appeared after EP acid renewal Field emission at low gradient happened on MHI-06, MHI-07, in VT. Kyoto-camera found brown stain trace in beam pipes,
Capture Cavity 2 Update Tim Koeth April 3 rd Testing at 4.5K.
1.3 GHz FNAL Dressed Cavity S-1 Global Deliverable to KEK 7 July 2009.
E. KAKO (KEK) 2009' Sept. 30 Albuquerque Global Design Effort 1 Cavity Test Items in S1-G Cryomodule Eiji Kako (KEK, Japan)
E. KAKO (KEK) 2010' Sept. 10 KEK Global Design Effort 1 Lorentz Force Detuning Eiji Kako (KEK, Japan)
2014/3/25TTC Meeting Radiation measurement and comparison between VT/CM tests at KEK-STF Kirk.
Test infrastructure and test programs at KEK-STF Kirk 2013/3/26TTC meeting
Accelerator R&D on LC - Activities of ATF & STF - 1. Introduction 2. ATF 3. STF 4. Summary Seiya Yamaguchi, KEK The US/Japan Collaboration in High Energy.
1.3 GHz SRF Cavity R&D Plan Jiyuan Zhai ILC Group, IHEP 3 rd IHEP-KEK 1.3 GHz SRF Meeting, 7 Dec 2010, Beijing.
Cavity status; recent KEK activities : Hayano (1) STF CM-1 cavities are; MHI-014: 3-rd VT:36MV/m (finished) MHI-015: 3-rd VT: > 18.4MV/m.
E. KAKO (KEK) 2009' Dec. 22 S1-G Webex meeting Global Design Effort 1 Final Results of KEK Cavities for S1-Global Eiji Kako (KEK, Japan)
1 Results from the 'S1-Global' cryomodule tests at KEK (8-cav. and DRFS operation) Shin MICHIZONO (KEK) LOLB-2 (June, 2011) Outline I. 8-cavity installation.
Status of cavity fabrication facility at KEK H. Hayano, KEK Cavity Industrialization Study at KEK Superconducting RF Cavity Technology and Industrialization.
Detail discussion of S1 Global at STF H. Hayano (KEK) GDE Mar 3-6, 2008.
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
Superconducting rf test facility STF 1 Optical Inspection update at KEK Ken Watanabe ( KEK ) ILWS08 in Chicago 17-Nov-08.
S.Noguchi (KEK) ILC08 Chicago , Nov . 17, Cavity Package Test in STF STF Phase-1 E. Kako, S. Noguchi, H. Hayano, T. Shishido, M. Sato, K. Watanabe,
1 E. KAKO (KEK) 2012' May 28 Clermont 1 A_RD_03 R/D for the High Power Couplers for ILC Walid KAABI (LAL-Orsay, France) Eiji KAKO (KEK, Japan)
E. KAKO (KEK) 2010' April 20 meeting Global Design Effort 1 Eiji Kako (KEK, Japan) Cavity Test Plan in S1-Global Cryomodule.
28/Jul/ Test Results of the International S1-Global Cryomodule Kirk.
Global Design Effort 1 S0 Status High-Gradient cavities Lutz Lilje DESY supplement by H. Hayano 04Sep2008 EC
Cavity status; recent KEK activities : Hayano (1)STF CM-1 cavities are; MHI MV/m for CM-1 ILC cryomodule (3-rd VT) MHI MV/m for.
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
KEK Status Report Kirk 04/Mar/20151LCC 5th SCRF Meeting.
E. KAKO (KEK) 2010' Nov. 02 S1-G Webex meeting Global Design Effort 1.
Dec/1/2015WG3 in TTC Meeting Test Result of STF-2 Cryomodule Kirk Jun/2013Jul/2015 Preliminary.
Superconducting rf test facility LCWS 2010 in Beijing, 28 Mar 2010, Ken Watanabe Replica-method and local grinding repair K. Watanabe (KEK) LCWS 2010 in.
(1)[12~13/Dec/2009] Optical inspection (2)[14/Dec] frequency & field flatness measurement (3)[10/Mar/2010] pre-EP (5μm) (4)[11/Mar] EP1 (100μm) (5)[11/Mar]
E. KAKO (KEK) 2009' Oct. 26 ILC KEK Global Design Effort 1 Cavity Preparation for S1-Global Eiji Kako (KEK, Japan)
KEK-STF Vertical Test and Diagnostics Brief History & Future Plan Vertical Test Facility Cavity Diagnostic System Example of MHI#7 Cavity Summary of T-mapping.
2014/3/25TTC Meeting Beam Operation Experience at Quantum Beam Project in STF Kirk.
Cavity status; recent KEK activities MHI-06, MHI-7, MHI-8 were vertical tested on June, July.  EP acid (1000l) was re-newed on May 15. These cavity was.
Recent Results of Vertical Test for S1-Global Project at KEK-STF Y. Yamamoto, H. Hayano, E. Kako, S. Noguchi, H. Sakai, M. Satoh, T. Shishido, K. Umemori,
Explosive Events during V.T. in KEK ECFA (2013/5/30) 1.
Summary of Results and Development of Online Monitor for T-mapping/X-ray-mapping in KEK-STF Y. Yamamoto, H. Hayano, E. Kako, S. Noguchi, M. Satoh, T. Shishido,
Gradient Degradation Experience at Fermilab (NML/CM-1) Elvin Harms TTC Meeting, Beijing 5-8 December 2011.
1 Tuner performance with LLRF control at KEK Shin MICHIZONO (KEK) Dec.07 TTC Beijing (Michizono) S1G (RDR configuration) - Detuning monitor - Tuner control.
Superconducting Accelerating Cryo-Module Tests at DESY TESLA Technology Collaboration (TTC) Meeting, February 28 - March , Milano, Italy Denis Kostin,
Shuichi NoguchiTTC Meeting at Milano, Injector Cryomodule for cERL at KEK Cavity 2 Prototypes were tested. Input Coupler 2 Couplers were tested.
Plasma cleaning Laser re-melting technique at FANL M. Ge, G. Wu, J. Ruan, J. Ozelis, T. Nicol, D. Sergatskov, D. Hicks, L. Cooley Fermi National Accelerator.
Recent Result for the STF-2 Cryomodule Operation
Cornell Updates Commissioning of T-map for ILC single cell starts.
S1G Experiment Schedule Plan
ILC10 Beijing Global Design Effort
CW couplers; KEK injector couplers Eiji Kako (KEK, Japan)
Degradation and Recovery of Cavity Performance
ILC-SCRF Test Facilities considerations
Inspection of STF Baseline cavity #5 and #6
for the FNAL/ANL, JLab, and Cornell cavity teams
Input coupler assembly, high power and thermal performance in S1-Global at KEK E. KAKO (KEK) 2011' Dec. 07 TTC meeting in Beijing.
Crab Cavity R&D Plan Kirk 1 6/Dec/2016
S1-G Webex meeting Global Design Effort
Magnetic shields inside and outside LHe tank in S1-Global cryomodule assembly at KEK E. KAKO (KEK) 2011' Dec. 07 TTC meeting in Beijing.
Cost reduction activities in cavity fabrication at MHI
Jiyuan Zhai ( IHEP ) TTC Meeting, JLAB, 6 Nov 2012
Y. Yamamoto, H. Hayano, E. Kako, S. Noguchi, M. Sato, T. Shishido, K
Recent VT Results in the STF-2 cavities
Recent SCRF Activities in IHEP
Progress in Asia Hitoshi Hayano,KEK,
Degradation and possible sources Statistic of resonators
KEK injector cryomodule
Performance Degradation cERL Injector Cryomodule
Construction and First Coo-down Test of cERL Injector Cryomodule
EU-XFEL summary of performance degradation
Report of TTC-TB meeting at INFN-Milano
TTC meeting, Milano Global Design Effort
Cavity & Cavity Integration; recent KEK activities
Presentation transcript:

Cavity Degradation Experience at S1-Global TTC Meeting 2011 @Beijing Kirk 7/Dec/2011

Outline Vertical test and Cryomodule test Performance improvement and degradation Optical inspection after S1-Global Summary 7/Dec/2011 TTC Meeting 2011 @Beijing

Vertical test and Cryomodule test CW operation Variable coupler with almost no reflection Several hundred W from RF Amplifier Cryomodule test Pulse operation (5Hz/1.5ms) Variable coupler with total reflection Several hundred kW from Klystron The duty factor is considerably different! 7/Dec/2011 TTC Meeting 2011 @Beijing

S1-Global Cryomodule Cryomodule-C Cryomodule-A (4 TESLA cavities) (4 TESLA-like cavities) 7/Dec/2011 TTC Meeting 2011 @Beijing

Cavity Performance @V.T. 2 cavities from FNAL 2 cavities from DESY 4 cavities from KEK 8 Cavities for S1-Global (ave. 30 MV/m) E. Kako 7/Dec/2011 TTC Meeting 2011 @Beijing

Cavity performance between V.T. and C.T. Ave. 30MV/m @V.T. Ave. 28MV/m @C.T. (single cavity) Ave. 26MV/m @C.T. (7 cavities) Two cavity performance was degraded and one cavity improved! 7/Dec/2011 TTC Meeting 2011 @Beijing

Cavity performance between V.T. and C.T. drastic improvement severe drop! 7/Dec/2011 TTC Meeting 2011 @Beijing

MHI#5 on 12/Nov/2010 In this day, we tried the LFD compensation by Piezo. But, before that, we had to adjust the F.B. tuning by LLRF system. During this adjustment, the F.B. parameter was not optimized, and abnormally input power had been supplied to this cavity. Therefore, the vacuum level was too high, and the vacuum interlock worked many times with the arc interlock! Cavity gradient 12:00 19:00 Vacuum at warm side He level He pressure He flow 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#5 after S1-Global 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#5 after S1-G 3rd V.T. @16/Apr/2009 π, 7π/9, 5π/9, 3π/9 @27.6MV/m 6cell equator, t=320 deg 4π/9, 6π/9 @30.7MV/m 5cell equator, t=154 deg 7/Dec/2011 TTC Meeting 2011 @Beijing

Transition of heating location for MHI#5 1st V.T. @4/Dec/2008 2nd V.T. @26/Feb/2009 3rd V.T. @16/Apr/2009 5π/9 (25.6MV/m) π, 7π/9, 5π/9, 3π/9 (27.6MV/m) 7π/9 (29.2MV/m) π, 3π/9 (~29.1MV/m) 4π/9 (20.4MV/m) 6π/9 (32.9MV/m?) 4π/9, 6π/9 (30.7MV/m) π, 8π/9, 4π/9, 3π/9 (~21.4MV/m) pre-EP : 5μm EP1 : 100+20μm EP2 : 50μm EP2 : 50μm EP2 : 20μm 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 154° in Cell#5 As received After EP1 25μm 7/Dec/2011 After EP1 100μm TTC Meeting 2011 @Beijing After anneal

History of defect at 154° in Cell#5 After EP2 and VT After 2nd EP2 and VT 7/Dec/2011 After S1-G TTC Meeting 2011 @Beijing

History of defect at 320° in Cell#6 As received After EP1 25μm 7/Dec/2011 After EP1 100μm TTC Meeting 2011 @Beijing After anneal

History of defect at 320° in Cell#6 After EP2 and VT After 2nd EP2 and VT 7/Dec/2011 After S1-G TTC Meeting 2011 @Beijing

Optical inspection for MHI#6 after S1-Global 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#6 after S1-G 6th V.T. @16/Sep/2009 4-5 iris, t=255 deg. 3 cell equator , t=9 deg. 5π/9 (35MV/m) 6π/9 (35MV/m) 4π/9, 8π/9, π (28~32MV/m) 4 cell equator , t=103 deg. 7/Dec/2011 TTC Meeting 2011 @Beijing 8-9 iris, t=261~280 deg.

Profile of defect at 255° in Iris#4-5 4-5 iris, t=255 deg. Bump size 50×350[μm] 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 255° in Iris#4-5 As received After bulk EP After 1st VT After 2nd VT After 3rd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 261~280° in Iris#8-9 8-9 iris, t=261 deg. After 3rd VT After S1-G 8-9 iris, t=270 deg. After 3rd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 261~280° in Iris#8-9 8-9 iris, t=280 deg. After 3rd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#7 after S1-Global 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#7 after S1-G Top bp, t=324~350 deg. 2nd V.T. @15/Sep/2009 3, 5π/9 @35, 43MV/m Bottom bp, t=214~278 deg. No defect at every cell 6, 7, 8π/9, π @33~34MV/m Bottom bp, t=81 deg. 7/Dec/2011 TTC Meeting 2011 @Beijing

Problematic EBW at beam pipe 324° 333° 342° 350° 7/Dec/2011 TTC Meeting 2011 @Beijing

Problematic EBW at beam pipe Bottom bp, t=81 deg. Bottom bp, t=108 deg. Bottom bp, t=108 deg. 7/Dec/2011 TTC Meeting 2011 @Beijing

Problematic EBW at beam pipe Bottom bp, t=214~278 deg. 214° 223° 232° 242° 251° 261° 270° 278° 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#9 after S1-Global 7/Dec/2011 TTC Meeting 2011 @Beijing

Optical inspection for MHI#9 after S1-G 3rd V.T. @16/Dec/2009 4π/9, π @27~28MV/m 2 cell equator , t=222 deg. 7, 8π/9, π @17~27MV/m 5, 6, 7, 8π/9, π @27~35MV/m 8-9 iris, t=94 deg. 9 cell equator , t=317 deg. 7/Dec/2011 TTC Meeting 2011 @Beijing

Transition of heating location for MHI#9 1st V.T. @3/Sep/2009 2nd V.T. @12/Nov/2009 3rd V.T. @16/Dec/2009 3, 4π/9 @28~29MV/m 1st π @27MV/m 3, 4, 5, 7, 8π/9, π @16~18MV/m 4π/9, π @27~28MV/m 5π/9 @39MV/m 7, 8π/9, π @17~27MV/m 7, 8π/9, 2nd π @25~34MV/m 6π/9 @40MV/m 5, 6, 7, 8π/9, π @27~35MV/m pre-EP : 5μm EP1 : 100μm EP2 : 20μm Ethanol+HWR+HPR EP2 : 20μm Degreasing(FM-20) +HWR+HPR EP2 : 20μm Degreasing(FM-20) +HWR+HPR 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 222° in Cell#2 As received After bulk EP After 1st VT After 2nd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 317° in Cell#9 As received After bulk EP After 1st VT After 2nd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

History of defect at 94° in Iris#8-9 As received After bulk EP After 1st VT After 2nd VT After S1-G 7/Dec/2011 TTC Meeting 2011 @Beijing

Summary DESY and FNAL cavities should be also inspected Two cavity performances were degraded at cryomodule test. MHI#5 cavity had coupler trouble due to non-optimized F.B. system. MHI#6 cavity improved largely because of lower duty factor. Every MHI cavity has several defects at equator, iris or beampipe. DESY and FNAL cavities should be also inspected by Kyoto camera after disassembly! 7/Dec/2011 TTC Meeting 2011 @Beijing

Thank you for your attention. 7/Dec/2011 TTC Meeting 2011 @Beijing