Bunker Internal Review Welcome & Charge

Slides:



Advertisements
Similar presentations
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
Advertisements

Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Managing Accelerator Quality Matthew Conlon 13 April 2015.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
Neutron Chopper Technologies Work Package
Accelerator/program Mats Lindroos Head of accelerator April 21, 2015.
ESS Annual Review Science Directorate - Dimitri Argyriou The challenge for 2016: Matching instrument scope with budget Andreas Schreyer European Spallation.
Electrical Engineering for NSS - Status and Planning- Thomas Gahl Electrical Engineering Group Leader February 26, 2014.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
CDR for the ESS Linac Magnets for LWUs (pulsed quadrupoles and DC correctors) Closeout May 4, 2016 J.G. Weisend II, Chairman CDR.
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
European Spallation Source Overview and Status Technical Advisory Committee 1-2 April 2015 James H. Yeck ESS CEO & Director General
Overview of the Neutron Instrument Construction Project Shane Kennedy NSS Project Leader, ESS IKON 10, Düsseldorf, 16 February.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Interfacing instrument teams with ESS and STAPs Ken Andersen ICB5, Copenhagen 7 th March 2016.
Instrument Construction Phase 1 and beyond Rob Connatser Chief Instrument Project Engineer September, 2014.
ESS Annual Review Science Directorate - Dimitri Argyriou ESS update Andreas Schreyer Director for Science European Spallation Source ERIC Engineering STAP.
ESS Annual Review Science Directorate - Dimitri Argyriou Science Directorate Update Andreas Schreyer European Spallation Source ERIC Instrument Collaboaration.
Rob Connatser NSS Instrument Work Packages and XLPM.
ACCSYS Design Reviews J. G. Weisend II Deputy Head of Accelerator Projects.
ESS licensing process and Readiness Reviews
Welcome & Charge for the Meeting
Sample environment for Spectroscopy (TEFI, PREMP)
ESS Project Status Roland Garoby – Technical Director August 2018.
ESS Installation Binders Readiness Reviews Work Orders Mikael Jakobsson ESS Installation Manager Sep , 2018.
NSS Instrument Project Tollgate Coordinator
Action List.
STAP meeting for Imaging & Engineering October CHARGE & Organization
NSS Instrument Project Tollgate Coordinator
The Bunker Project Overview Zvonko Lazic
The Common Shielding Project
Basics for Bunker Installation Schedule Bunker CDR 2.0
Instruments Shielding Project Installation
Project Management Issues John N. Galayda, SLAC April 24, 2002
Science Support Systems at ESS
MET Session workshop Job description Integration Engineer
Imaging & Engineering STAP Meeting 12th-13th of April 2018
PSS verification and validation
Large Scale Structures
Bunker -Target interfaces
Bunker Project Schedule/Budget
Instruments – Bunker Wall interfaces
Welcome Update on ESS Construction Project
Charge for CSPEC Detector Construction Workshop
Radwaste: status & way forward
TG3 Process /Part 2 Gábor László NSS Lead Instrument Engineer
Technical Updates Gábor László NSS Lead Instrument Engineer
NSS integrated installation plan workshop Introduction
DOE Review of the LCLS Project October 2006
Bunker Project Schedule/Budget
Spectroscopy STAP Meeting ESS, 8th of April 2019
Licensing update ESHAC #7, October 2017
Imaging & Engineering Diffraction STAP Meeting ESS, 21th of March 2019
Update on ESS Construction Project Charge to the SANS STAP
Test Beamline System Requirements and Charge to PDR Committee
Introduction, Overview, Charge, Project Plan, Requirements
ESHAC Meeting # Peter Jacobsson Head of ESH
Shielding requirements for the baseline bunker shielding (current CATIA version ) Günter Muhrer
Charge and Agenda of the 18th TAC meeting
Bunker Critical Design Review Welcome & Charge
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Software Reviews.
Reflectometry STAP Meeting ESS, 29th of April 2019
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Bunker Internal Review Welcome & Charge Shane Kennedy NSS Project Leader www.europeanspallationsource.se 5th December 2017

NSS Neutron Instruments: Project scope -15 instruments + test beamline ESS Lead Partners for instrument construction + Nuclear Physics Institute BEER NMX + C-SPEC BIFROST MIRACLES MAGIC ODIN DREAM T-REX HEIMDAL Test Beam Line VESPA FREIA LOKI SKADI + ESTIA ESS In-Kind Partners also collaborate on sample environment, data management systems etc. ESS Instrument Layout (September 2017)

First access to NSS areas Internal* Neutron Beam Instrument Schedule Draft for Discussion V3.4, 15th September 2017 West sector North sector East and South sectors Current date First access to NSS areas Start User Program Beam on Target Hot Commission instruments * still under discussion with ESS-ERIC Council NOTES: Assumes 2MW maximum power until end 2025 Phases aligned with TG2 reviews on 1st 10 NBIs Installation & Integration (TG4) + Hot Commissioning (TG5) for first 8 NBIs aligned with draft BOI plan (schedule match typically within 1 month) This schedule assumes obtaining the radiological licenses in a timely fashion from SSM. A trigger ‘first optical instrument component outside the monolith’ and a 6 months period from submission of the application to obtaining the SSM license - have been assumed (pending formal confirmation from ESH).  an initial hot commissioning of Accelerator and Target (A&T) to establish reliable beam on target at design frequency and pulse width. In 2021, commissioning of the first (4-5) neutron instruments is to be conducted at low power, where possible, in order to minimize activation of in-bunker components of the neutron instruments. In the current plan, the duration of this initial commissioning period is 10-12 weeks. Over 2022 and 2023 beam power and availability will increase, as the first 8 or more neutron instruments start hot commissioning, with a goal of reaching 2 MW source power by the start of the user program and maintaining that level until 2026. Commencement of hot commissioning for the first 8 neutron instruments (TG5 in Table 1) is closely aligned with the schedules presented by those instrument build teams at TG2. This order matches well with the NSS “Early Science Success” strategy, and distributes responsibility for delivery widely among our experienced In-Kind partners. Changes to this order will be made if necessary to mitigate effects of delays to individual neutron instrument projects. TG5 dates for neutron instruments 9-15 will be delayed to concentrate on-site resources for installation and commissioning (both cold commission and hot commissioning) on the first eight instruments to facilitate early science success for those instruments. This is discussed further below and illustrated in the NSS Installation and Commissioning schedule (Fig. 3). TG3 dates refer to “final” approval of detailed design, when the integrated design of all major components is judged to be complete, and beyond which no further approval from NSS management is required for manufacturing. At this point in time these TG3 dates are not fixed, but NSS management plans for this to occur in staged manner. “Early procurement” approval dates for in-monolith optics and other critical path procurements (such as in-bunker components for the first instruments) are not shown in the figure Preliminary Design Detailed Design Manufacturing & Procurement Installation & Integration Hot Commissioning/Early science Operation 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

CDR committee members External members: Internal (ESS) Members: Erik Iverson (chair), SNS David Anderson, SNS Steven Lilley, STFC David Turner, STFC Internal (ESS) Members: Ken Andersen, Neutron Instruments Mark Anthony, Target Division Masatoshi Arai, Technical Coordinator Stuart Birch, ICS Division Peter Jacobsson, ESH François Javier, Systems Engineering

Charge for this review meeting Purpose: to assess whether bunker design satisfies all stated design requirements and whether it is defined at a level of detail consistent with release for fabrication and/or procurement; according to the procurement/production plan for the project: Specific questions: Are system requirements and interface requirements properly defined and complete? Have safety and hazards been properly considered and addressed? Do the System Design Description documents and related drawings adequately describe the design to the degree needed for fabrication or procurement; as per the project plan? Does the design satisfy the functional and performance requirements? Are the Manufacturing Plan, the Installation Plan, and System Analysis Reports finalized and do they support the stated design?