The 9th Collaboration Meeting June 14-15, 2004, ANL LOI Status at ISIS ANL/ISIS/KEK Yoshiro Irie for the collaboration (JAERI/KEK) June 14-15, 2004, ANL The 9th Collaboration Meeting
Phasing of the LOI developments Phase I April-September, 2004. Preparations at the MICE Hall: full peak power, but with a reduced duty factor Phase II Installation at the SP8 for the beam test in 2005(?) June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting Results to date Almost all the LOI equipments are in place. New RF contacts attached to the LOI chassis panels. June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting Forward The second harmonic cavity and the bias supply are to be moved in with a cooling unit. Power requirements 733KW-peak, 283KW-average Water requirements 238liter/min for high purity & demin water, and 38liter/min of a tapped water. Conductivity of the demin water that will be supplied to the MICE Hall is 1 microsiemens/cm. Cabling of power and control lines Pulsed grid supplies June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting Minimum power/water requirements at Phase I June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting Issues AC voltage variations at RAL? Japanese modules are usually safe for ±10% variation. Is the RAL 400Vac range safe for the voltage limit(35KV) of the input capacitor of the buck regulator? probably yes (31.5KV×440/410=33.8KV). Work plan at the MICE Hall. Oil June 14-15, 2004, ANL The 9th Collaboration Meeting
The 9th Collaboration Meeting June 14-15, 2004, ANL The 9th Collaboration Meeting