Cold compressor speed S45

Slides:



Advertisements
Similar presentations
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Advertisements

Saturday 6:13 – 15:00 STABLE BEAMS  scans etc. 15:00 moved to ADJUST Squeeze to 2 m in two steps 11 – 5 – 2  remarkably smooth  tertiary collimators.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Wednesday 3rd October - morning
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Machine Coordinators: G. Arduini, J. Wenninger
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 15th June 01:11 Injection.
Wednesday September 14th
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Summary Friday h38: Ramp down and pre-cycle.
Wednesday 17th August Rocky, short fills, initial luminosities are good LHCb polarity change to negative seems ok 18/08/2011 LHC 8:30 meeting.
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Wednesday 31 October: Morning
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
LHC Status Sun Morning 20-Mai
LHC Operations overview Week 28 – Getting back
Week 35 – Technical Stop and Restart
Monday Morning – recovery from cryo.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Thursday :00: Physics fill from the night shift
Wire almost entirely through beam before BLM triggers dump
Yesterday’s morning’s controls issues
Finally.... We had to wait a long time.... We had many problems....
Friday Morning 7:30 injection for fill 2908
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Summary Thursday h21: Stable beams fill #1303.
Monday – Morning Fill 3265 stable beams since 1:31
Aims for the week Recover from technical stop and precycle at 10A/s
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Mon Access for switching temperature probe DFB L7.
Monday 3rd September - morning
Saturday 3rd November - morning
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Friday morning 08:00 Stable beams with 840b.
Summary Tuesday h23: Machine closed. Precycle started.
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday 15th February - morning
Another Immortal Fill….
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday morning / afternoon
Wednesday morning Waiting for PS – problem on RF cavity.
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Tuesday
Sat :24 Fill 2669 stable beams, average bunch intensity 1.5e11, peak lumi: ~6.5e33 cm-2s-1. 14:37 Beams dumped by operation due to cryo problem.
Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Cold compressor speed S45 Saturday 20th August After last intervention, compressor tripped first time, not second time. Possibly due to missing temperature measurement on compressor. Calculated values used. Cryo Recovery Yesterday’s main event: Cold compressor speed S45 L.Tavian 21/08/2011 LHC 9:00 meeting

Other events....preparing for beam Free wheel diode fault cleared in 81, one more to be checked in Inner Triplet.L5 once cryo is available. Good to do pre-cycles as early as possible: Precycle (excluding 45 and 78) Replaced power converter corrector RCBV18.L4B1 Green light from MP3 to precycle sector 78 RCBWH5.L8B1 now on ok. The FGC was found in a bad state. Another 60A converter, RCBH29.R7B1 trips, again with VS_FAULT. Informing our faithful EPC piquet again! 23:10 Pre-cycle complete machine Some collimator issues. Called collimator piquet. 02:00 Injecting probe beams 03:30 Dump with PM for system check: OK 04:15 Beam2 injection line steering 06:41 Stable Beams ! 21/08/2011 LHC 9:00 meeting

Fill #2037 Ibeam around 1.2e11, rocky filling and initial lumi around 2e33: not bad for getting back! B1 lifetime worsened when IP8 leveling kicked in 21/08/2011 LHC 9:00 meeting

LHCb “The second thing to notice is that LHCb optimum in horizontal was at 104 micros distance. We trimmed step by step close to the maximum, monitoring TCT limits and background, and everything was OK. Then we re-optimize and level as usual. “ 21/08/2011 LHC 9:00 meeting

Outstanding TOTEM & ALFA moving in during stable beams Totem: earliest on Monday Alpha: on demand, allowed after 6h of stable beams -> soon, this fill if possible ‘End of fill’ tight collimators After about 10 h of stable beams and during day time -> after Alpha, assuming that beams stays in In Adjust Transverse damper set-up at injection for higher bunch intensities After Technical Stop 90m optics On Tuesday afternoon, before MD period starts Wednesday morning 20/08/2011 LHC 9:00 meeting