ENGINEERING MANAGEMENT (GE 404)

Slides:



Advertisements
Similar presentations
TK3333 Software Management Topic 7: Schedule Control.
Advertisements

Creating the Project Plan
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
Project Time Management
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Dr. Godfried Williams1 Project Management – Topic 6 Lecture Content Planning Tools/Techniques Optimization Techniques Resource Planning & Allocation Linear.
Project Monitoring and Control by Hateem Ghafoor, PMP.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
1 L U N D S U N I V E R S I T E T P rojektledning och Projektmetodik.
Project Time Con trol. Control = Monitor + Compare + Analysis + Action  Definition: Controlling  Controlling involves making sure that the results achieved.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
Geog 469 GIS Workshop Project Management.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
11/9/2015 9:42 AM 1 Project Time Control. 11/9/2015 9:42 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
PROJECT PLANNING AND SCHEDULLING
1 PROJECT MONITORING & CONTROL. 2 Project Monitoring and Control Why do we monitor? What do we monitor? When to we monitor? How do we monitor?
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
SCHEDULE MANAGEMENT MODULE 8. Required by Specification City/Caltrans Level 1 schedule – simple Less than $1 million, less than 100 working days Advanced.
Project Management PTM721S
Chapter 16 – Project Management
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Project Management – PTM721S
TOPIC-8B- PROJECT COST CONTROL
Time Planning and Control Time-Scaled Network
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Procuring Professional Services
Maintenance Scheduling
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Software Project Management
TOPIC-8A- PROJECT TIME CONTROL
Project Planning & Scheduling
Project Planning and Scheduling
Activity Planning.
Chapter 6: Project Time Management
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
Project Time Management
Software Project Management
Project Scheduling: networks, duration estimation, and critical path
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Time Planning and Control Time-Scaled Network
Software Project Management
Project Time Management
MGT 605: CH-13 Progress and Performance Measurement and Evaluation
ENGINEERING MANAGEMENT (GE 404)
Project management Lecture 9
Lecture 6: Time-Cost Trade-Offs
ENGINEERING MANAGEMENT (GE 404)
Project Time Management
ENGINEERING MANAGEMENT (GE 404)
ARCH 435 PROJECT MANAGEMENT
Project Planning By Phaik San Liew.
Chapter 6 Activity Planning.
Project Time Management
Project Time Management
Chapter 6 Activity Planning.
University of Debrecen Mongolian University of Life Sciences
Project Time Management
Managing Project Work, Scope, Schedules, and Cost
FACULTY OF ENGINEERING CONSTRUCTION AND BUILDING DEPARTMENT
CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING
Presentation transcript:

ENGINEERING MANAGEMENT (GE 404) بسم الله الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) Lecture #11 Project Time-Control This is a title slide. GE 404 (Engineering Management) May 4, 2019

Contents Objectives of the present lecture Introduction to Project time-control Process of Project time-control Network updating (rescheduling) Problem Further reading GE 404 (Engineering Management) May 4, 2019

Objectives of the Present lecture To discuss process involved in project time-control To explain how to carry out project rescheduling (or Network updating) GE 404 (Engineering Management) May 4, 2019

Project Time-Control Project time-control can be reduced to two basic components: Monitoring Monitoring consists of a means of understanding what is happening on a project, obtaining information about the project by some means Control Control consists of action taken in response to the information Trade-off (between something and something) the act of balancing two things that are opposed to each other a trade-off between increased production and a reduction in quality GE 404 (Engineering Management) May 4, 2019

Process of Project Time-Control Establish an operational schedule Measure the progress and report the progress Compare actual achievement with planned Check and analyze time progress and determine effect on completion date and milestones Plan for corrective action Implement corrective action Update operational schedule GE 404 (Engineering Management) May 4, 2019

Establish Operational Schedule For project control purposes a hierarchy of schedules may be needed, depending on who will use it Key Dates Schedule For owners and top-level management in terms of MILESTONES or KEY DATES. Detailed Schedule For engineers, work supervisors, material suppliers and subcontractors A schedule of that particular engineer/supervisor work responsibility Provide him with a day-to-day forecast of field operations Critical activities and free float values should be noted Covers limited time spans (2 weeks or 30 days) Tabular listings and computer-printed bar charts are common forms GE 404 (Engineering Management) May 4, 2019

Measure and Report Progress Methods: Estimated number of working days required to complete the activity Estimated % completion of the activity Quantities of work units put in place Equations Based on the assumption of straight-line variation between time and work accomplishment Working days to complete = d (1 - P/100) Working days to complete = d (1 – (W/T)) d= total activity duration in working days P = estimated percentage of completion W= number of work units put into place T= total number of work units associated with the activity GE 404 (Engineering Management) May 4, 2019

Contd. Weekly Progress reports A common procedure in many industries Listing those activities that started, finished, or were in progress during the week and indicating their stages of completion Must include procurement, material delivery information etc. Chose a cutoff date, to be selected to serve both time management and labor cost accounting GE 404 (Engineering Management) May 4, 2019

WEEKLY PROGRESS REPORT Working days to complete Contd. WEEKLY PROGRESS REPORT Project: Highway bridge Week ending: Wednesday, July 21 (working day 27) Job. No: 7903-50 Prepared by: K.M. Activity Activity Number Date Started Date Completed Percent Complete Working days to complete A 110 - July 15 100 B 115 13 C 130 80 2 D 150 July15 E 160 July 16 July 21 GE 404 (Engineering Management) May 4, 2019

Contd. Field Progress Narrative To accompany weekly progress reporting Discussion of projected project features General statement about time status Critical or low float activities in difficulty Potential trouble spots Exceptionally well project areas GE 404 (Engineering Management) May 4, 2019

Compare and Analysis of Project Progress Concerned primarily with determining the effect of the latest information on the project completion date and any milestone goals 1st - A quick and simple check for critical activities status 2nd - Check the possibility of a new critical path Signs of Danger Activities fall behind LS schedule Resource availability delays Realizing that time duration of future activities have been materially underestimated Change logic becomes necessary GE 404 (Engineering Management) May 4, 2019

Corrective Actions When there are small delays that are within network time contingency, no action is usually required Otherwise use Time Reduction Technique to bring project back on schedule Make periodic (Weekly, biweekly, or monthly) job progress meetings with project managers, field supervisors, major subcontractors, material suppliers, and owner representative to enhance time management efficiency GE 404 (Engineering Management) May 4, 2019

Network Updating (Rescheduling) Concerned with determining the effect of schedule deviations and plan changes on the portions of the project yet to be constructed This requires making necessary network corrections and re-computing activity times and float times Information required for Rescheduling New activities to be added Existing activities to be deleted Changes in the resource availability and delivery dates Changes in the job logic New estimate of the time (for completing unfinished activities) Changes in the scope of work etc. GE 404 (Engineering Management) May 4, 2019

Problem-1 The initial AON diagram for a small engineering project is shown below with its planned activity times in days. At the end of the 15th day, the field progress report gives you the following information: Activity “A” was completed on schedule Activity “B” started as planned but four days were lost due to waiting for the required resources Activity “C” was completed one day earlier The remaining duration of Activity “D” is 2 days The duration of activity “H” will be reduced to 12 days instead of 17 days. The activity “F” cannot start until the morning of day 22 Activity “Z” is expected to take two days more Due to owner requirement the volume of work of activity “X” will be increased by 50% Construct the updated AON diagram, calculate the early and late start times of each activity, and indicate the critical path. GE 404 (Engineering Management) May 4, 2019

Solution Note: For activity E: 13-5-18 is changed to 15-3-18 Note: In duration cell, mention the time required/ remained w.r.t. date of reporting. Note: For activity E: 13-5-18 is changed to 15-3-18 ES is changed from 13 to 15 because the current date of rescheduling is Day 15 Duration is changed from 5 to 3 because EF = 18 has to be maintained GE 404 (Engineering Management) May 4, 2019

Further Reading Read more about the Project Monitoring and Control from: Jimmie W. Hinze. “Construction Planning and Management,” Fourth Edition, 2012, Pearson. GE 404 (Engineering Management) May 4, 2019

Thank You Questions Please GE 404 (Engineering Management) May 4, 2019