Thursday 17/3 Morning: evaluation of the origin of the timing problem occurred over night and the implication on machine protection 09:00 – 12:00 Dry ramp.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Day ● 09:00-14:00: Collimation setup 3.5 TeV – Slowed down by losses induced by tune hump. – 48 collimators set up. – Beam dumped by ATLAS during.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Wednesday 21 March 2012.
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Summary of week 7 Hardware Commissioning:
Monday 11/07: Recovery Plenty of accesses.
Saturday 30th June - Sunday: Rocky !
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Machine availability reaching well over 80%
Summary of Week 11: 14 – 21 March
Monday – recovery from MKI flashover
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Friday March 4th 08h32: Access for beam dump system.
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
Monday Morning – recovery from cryo.
Thursday :00: Physics fill from the night shift
Yesterday’s morning’s controls issues
Friday Morning 7:30 injection for fill 2908
Yesterday morning Held 1647 for a while – SPS kicker problem
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 03/11 – The Plan Finish electron-cloud program:
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday Fill 1364 (24 bunch) dumped at 07h
Tuesday morning 08:30-09:00 Squeeze with probe.
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Programme for Friday 9 July
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
07/08/2010 Fill #1264 dump at 02:14:38.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary for LPC (March 7th, Ralph Assmann)
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
RAMP FOR COLLIMATOR SETUP
Another Immortal Fill….
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
31/3/2010 Difficult day… but at the end stable beams.
Wednesday 6.10 Morning: Quench test at 450 GeV
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Thursday 17/3 Morning: evaluation of the origin of the timing problem occurred over night and the implication on machine protection 09:00 – 12:00 Dry ramp to validate energy and b* limit functions for collimators Beam 1 not available from the SPS (steering issue in TT60-TI2) likely due to the remanent field of the HiRadMat/TI2 switching magnet after a test Beginning of the afternoon: decision to operate the machine with low intensity and progress with commissioning activities while waiting for deployment of new firmware for the timing distribution 14:00 – 19:00 several interruptions: BST NFS  concentrators not working (BLM/collimators logging 222 GB of data in 1 day) PS Booster 19:00 - Setting-up of ramp to 1.38 TeV 04:30 – FIDEL chromaticity and tune corrections at 450 GeV

Beam dump on Wed at 22:49 Discovered that RT_REF signal is mis-mapped between devices within the post-mortem logs (S. Page) Caused by the tune feedback likely reacting to wrong measurement of the tune as a result of the timing problem Actions: New release of the MTG firmware (tested yesterday after re-production of the error with old firmware) Update of the BBQ timing receiver firmware

SMP distribution during timing problem All energy values were correctly sent to the GMT. Energy and flags sent by the SMP during ramp-up I. Romera

Collimation - The dump from the TCTH.4L5.B1 is still under investigation. The reason for dump was "Position out of limits" but the position sensors remained well within the limits (even when looking at the fast acquisitions into the PM buffer). More news asap. - We set and tested without beam the energy limit functions for all collimators of type TCP, TCSG, TCLA, TCDQ in all points. This worked well. Limit thresholds are now active for the 3.5 TeV ramp (Settings are validated for operation). Other collimators have constant energy limits around the injection settings (500 um). - We tried a dry test with the TCT betastar limits during the squeeze. This did not work because there is a FESA bug in the interpolation of the gap limits vs betastar. The bug was identified and a solution is found. It will be implemented in the technical stop.

Timing problem See slide P.Charrue

“Replacement Program” Prepare ramp and collision for 1.38 TeV operation 2 ramps lost SIS on collimators not masked Losses on TCTVB.4R2, when bringing into collision – needs more setting up Found collisions in all IPs except ALICE FIDEL studies on chroma and tune decay at 450 GeV Chroma stable, tune can be improved Test ramp with pilots When switching On the radial modulation, with tune feedback still ON, some RQT tripped: RQTF.A81B2, RQTF.A23B2, RQTF.34B2, RQTF.A45B2

Plan 09:00 New firmware will be deployed on the operational timing server A 09:00 – 12:00 Ramp at low intensity (probe) to check timing behaviour (in particular SMP distribution) Aim for physics with 32 bunches 8:30 meeting