NORTH SAN JOSE ADP May 18th, 2019 BIA RPC Meeting
2005: North San José Policy Updated 2018: Housing Crisis Workplan BACKGROUND: 2005: North San José Policy Updated 2018: Housing Crisis Workplan
Plan Structure
Development Transportation 32,000 Housing units (6,400 affordable) 26.7 million Sq. Ft. Industrial At least 300,000 Sq. ft. Commercial Development 23 Intersection Improvements 9 Major Roadway Improvements Ped, bike and transit improvements Transportation
Development CMP Facility Improvements Non-CMP/Offsetting Improvements Phase 1 Industrial: 7 MSF 5 Intersection Improvements 4 Improvements Residential: 8,000 units (1,600 affordable) Phase 2 3 Intersection Improvements 2 Improvements Phase 3 2 Intersection Improvements Phase 4 Industrial: 5.7 MSF All Phases Ped, Bike, Transit and Grid Improvements
Progress to Date:
Development Allowed Built-to-Date Phase 1 Industrial: 7 MSF +1.8 MSF credit from demolitions 1.5 MSF built 6.9 MSF entitled Residential: 8,000 units 1,600 affordable 7,937 units 390 affordable
Transportation Phase 1 CMP Facility Improvements Non-CMP/Offsetting Improvements Phase 1 Completed North 1st and Montague Old Oakland and Montague Montague Widening Partial/Active Trade Zone Boulevard & Montague Expressway Zanker and Tasman Guadalupe River Trail Hwy 237 Bikeway US 101/Trimble Road Interchange Zanker Road/Skyport Drive Connection Charcot Avenue Extension Mabury Road Interchange North 1st Light Rail Improvements
Key Considerations
01 02 03 04 Balanced growth including housing and jobs near transit Lead the region in providing housing opportunities 03 Work within the existing Policy and Environmental Clearance 04 Accelerate investment in the area’s transportation network
Proposed Approach:
PROPOSED APPROACH: Current Phasing Proposed Phasing Phase 1 Industrial: 7 MSF Phase A Residential: 8,000 units (including 1,600 affordable) Phase 2 Phase 3 Phase B Phase 4 Industrial: 5.7 MSF
PROPOSED APPROACH: Proposed Phasing Plan 101-Trimble Interchange Zanker-Skyport/Fourth Street Connection McCarthy/O’Toole – Montague Interchange Trimble – Montague Flyover 880/Charcot Overcrossing Montague Expy Widening Zanker Rd. Widening 101-Mabury Interchange
PROPOSED APPROACH: Proposed Phase Change
Next Steps:
Spring 2019: Bring forward amendments to Policy, corresponding studies, and environmental clearance for Council adoption. Summer 2019: Amend VTA Deficiency Plan
Questions? Ramses Madou Interim Division Manager Department of Transportation City of San Jose Ramses.madou@sanjoseca.gov